HomeMy WebLinkAboutResolution - 2010-R0026 - Contract 8119 Change Order 9 Eagle Contracting For Southeast Water Reclamation - 01_14_2010Resolution No. 2010-R0026
January 14, 2010
Item No. 5.18
RESOLUTION
BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF LUBBOCK:
THAT the Mayor of the City of Lubbock BE and is hereby authorized and
directed to execute for and on behalf of the City of Lubbock, Change Order No. 9 to that
certain Contract No. 8119 by and between the City of Lubbock and Eagle Contracting,
L.P., for Southeast Water Reclamation Plant Improvements per Bid # 07-730-13M, and
related documents. Said Change Order No. 9 is attached hereto and incorporated in this
resolution as if fully set forth herein and shall be included in the minutes of the City
Council.
Passed by the City Council this 14th
ATTEST:
Rebec Garza, City Secretary
APPROVED AS TO CONTENT:
day of January , 2010.
TOM MARTIN, MAYOR
ood ranklir/P.E., Chief Water Utilities Engineer
APPROVED AS TO FORM:
Ch � Wea er, Assistant City Attorney
sj:ccdocs/RES.ChangeOrder#9 Eagle Contracting LP #8119
12.29.09
CITY OF LUBBOCK
CHANGE ORDER
Change Order #: 9 Contractor: Eagle Contracting, L.P.
Date: December 22, 2009 BID/ITB #: I 07-730-BM
Contract #: I
81 19 I Project Name: I Southeast Water Reclamation Plant
Improvement
Change Order within the scope of the contract means a Change Order that DOES NOT ALTER THE NATURE OF THE THING
TO BE CONSTRUCTED AND THAT IS AN INTEGRAL PART OF THE PROJECT OBJECTIVE. After performance of a
construction contract begins, Change Orders may be approved if necessary to 1) make changes in plans or specifications; or 2)
decrease or increase the quantity of work to be performed or materials, equipment, or supplies to be fumished. Description of
change (alteration, deviation, addition, or deletion) caused by conditions encountered during construction not covered by
the specifications and drawings of the project (attach additional pages if necessary):
This change Order includes the addition of a new electrical duct bank to feed the new BNR electrical building, the removal of
the demolition of the washwater detention basin from the contract, the addition of PVC coating to the electrical conduit in the
Solids Building, the addition of an end stop on the IMLS monorail, the purchase of a manhole to protect the UV basin
chemical drain, the addition of a 6-inch sleeve beneath the road at EPS1, the replacement of mud valve MV-102, the addition
of in -situ process monitoring for BNR basin No. 3, the conversion of the hoist trolleys in the Headworks from manual to
electric, the addition of a concrete arch encasement on the Plant 3 Filter Influent line, and the realignment of the TWAS pump
piping. The total cost of this change order is $247,599,31. The total time extension of this change order is seven days.
Change Orders must either be negotiated in the best interest of the City of Lubbock or put out for public bid by the Purchasing
Department. Where the Change Order is negotiated, the Change Order must be fully documented and itemized as to costs,
including material quantities, material costs, taxes, insurance, employee benefits, other related costs, profit and overhead.
ITEMIZED COSTS MUST BE FULLY DOCUMENTED AND ATTACHED TO THIS FORM.
ITEM DESCRIPTION AMOUNT
A. ORIGINAL CONTRACT VALUE: $ 43,520,000.00
B. AMOUNT OF THIS CHANGE ORDER: Crnwcil approval repired if over $25,000 $ 247,599.31
C. PERCENT OF CONTRACT VALUE THIS CHANGE ORDER (B/A): 0.569%
D. AMOUNT OF PREVIOUS CHANGE ORDERS: $ 705,079.35
E. TOTAL AMOUNT OF ALL CHANGE ORDERS (B+D): $ 952,678.66
F. PERCENT OF CONTRACT OF ALL CHANGE ORDERS (E/A): 259E Atarinwm 2.189%
G. NEW CONTRACT AMOUNT (A+E): $ 44,472,678.66
It is mutually agreed that the above dollar amount and the time extension, as applicable, as set forth in this Change Order constitutes
full compensation to the Contractor for all costs, expenses and damages to the Contractor, whether direct, consequential or otherwise,
in anyway incident to, or arising out of or resulting directly or indirectly; from the work performed or modified by the Contractor
under this Change Order.
Date (2) PROJECT ARCHITECT/ENGINEER Date
/Appoved as to Cont t: Appro Form;
R'S RESENTAT D e (4�) jC�IT/Y ATTORNEY Date
Date
VK��31 c���J+ 1"4— 20/fl
(5) CAPIT PROJECTS MANAGER Date (6) PURCHASDV AND CONTRACT MANAGER Date
Change Orders over $25,000 require a Contract Cover Sheet and the following signatures:
CITY OF LU/B9E1S oe, � 1 14 10 A ST: 1/14/10
(7) MAYDate (8) CITNNSECRETARY Date
Council Date: January 14, 2010 Agenda Item #: 5.18 Resolution #: 2010—R0026
PUR-045 (Rev 02/06)
Capital Project Number:
Capital Project Name:
City of Lubbock, TX
Capital Project
Project Cost Detail
January 14, 2010
Resolution No. 2010-R0026
92126
Southeast Water Reclamation Plant Improvements
Budget
Encumbered/Expended
Construction - Eagle Contractors
43,520,000
Adendum #4 - B&V Engineering
3,219,686
Eagle Contractors Change Order # 1
29,583
Eagle Contractors Change Order #2
117,047
Eagle Contractors Change Order #3
56,622
Eagle Contractors Change Order #4
174,458
Eagle Contractors Change Order #5
23,353
Eagle Contractors Change Order #6
170,741
Eagle Contractors Change Order #7
435
Eagle Contractors Change Order #8
132,838
Agenda Item January 14, 2010
Eagle Contractors Change Order #9 247,599
Encumbered/Expended To Date 47,692,362
Estimated Costs for Remaining Appropriation
3,202,027
Remaining Appropriation 3,202,027
Total Appropriation $ 50,894,389
City of Lubbock, TX
Capital Project
Change Order 9 Itemized Detail
January 14, 2010
Capital Project Number: 92126
Capital Project Name: Southeast Water Reclamation Plant Improvements
Cost
Item 1
29,676.35
Item 2
-62,934.24
Item 3
2,228.52
Item 4
915.67
Item S
7,685.45
Item 6
1,481.62
Item 7
2,674.76
Item 8
215,078.26
Item 9
35,543.11
Item 10
5,872.85
Item 11
9,376.96
Agenda Item January 14, 2010
Eagle Contractors Change Order #9 247,599.31
REQUEST FOR INFORMATION
PROJECT: SOUTHEAST WATER RECLAMATION PLANT IMPROVEMENTS PROJECT NUMBER:
OWNED THE CITY OF LUBBOCK. TEXAS 92129
CONTRACTOR: EAGLE CONTRACTING, LP 171
ENGINEER BLACK & VEATCH CORPORATION
REFERENCE DATA:
Contractor RFI No. 094 Spec Section: Page No. Para.
Drawing No. E3 & E5
CONTRACTOR REQUESTS: ® Information 0 Interpretation 0 Clarification
The existing duct Bank detail No. 18 shown on drawing E5 indicates that there are spare conduits to be
Used for the two new Primary feeders to the new BNR Substations 1 TI-9 and 2TI-9. ACME Electric has
discovered that there Is only one empty conduit In this Duct Bank. Please advise on how to route the
second power feeder. (Reference attached Request from ACME Electric).
CONTRACTOR'S PROPOSED SOLUTION:
Is there the possibility that some of the wires in this existing Duct Bank are abandoned and can be
removed for use of the new second power feeder?
REQUESTED BY: OD4. DATE: 08/31/09
ENGINEER'S RESPONSE: 0 Information 0 Interpretation D Clarification
For the items described above or in the attached material referenced:
RFI-094 Response — September 3, 2009
Based on conversations during Progress Meeting 17, the preferred method will
be to install a new manhole and duct bank on the west side of the plant road.
Please refer to the attached figure. The duct bank will extend from the new
manhole to the south end of the 15 KV Switchgear vault. The new duct bank
RES should have the same conduit schedule as shown in Section 17/E3. Refer to
sheet E5. The manhole shall include the same conduits on its north, east, and
mm..-. west sides.
The Contractor should proceed with extreme caution in excavating in this area
due to the presence of other utilities. Refer to sheet CY3.
A cost proposal should be submitted detailing this work.
S:IBandilEegie Contnding I llesUob Files%171- Lubbock WWTPWFI's%RFW84-8pero Conduit In existing Dud Bank far BNR suhstatlons.doc 14 1
October 29, 2009
Black & Veatch Corp.
9441 LB7 Freeway —Suite 114
Dallas, Texas 75243
Attn: Ms. Laura Stratton
RE: Southeast Water Reclamation Plant Improvements
Contract ITB # 07-730-BM —Project # 92126
The City of Lubbock, Texas
Black & Veatch Corporation
Subj.: Proposed Contract Modification (PCM-36A) — Install new electrical duct bank
for the primary power feeders into the BNR Electrical Building Substations.
(Additional information).
Dear Laura:
Per your request in your e-mail to me dated 10-15-09, attached is the additional
information andcost breakdowns—Ui tfie aFo—ie ii e encedMNn- 3_6A-List_RF eZow are
the responses to your queries.
1. I have revised the contract time extension request to seven (7) days.
2. The asphalt patch repair costs shown are only for the road patch by the digesters
and does not include the patch across the main road.
3. Acme has enclosed the backup data for their manhole cost.
4. Acme has explained how they arrived at their 5" conduit footage.
5. Acme has explained what they used an air compressor for.
6. Acme has revised their cost proposal to show labor breakdowns.
7. Acme has revised their cost proposal to show a separate line item for overhead
and profit.
The cost to perform this work is Twenty Nine Thousand Six Hundred Seventy Six
Dollars and Thirty -Five Cents ($29,676.35).
Sincerely,
Dave Mullenix
Eagle Contracting L.P.
cc: File (Proposals) & Field
P.O. Box 1600 0 Keller, Texas 76244 0 Metro (817) 379-1897 In Metro (817) 379-0610 Fax
I Aah,
December 10, 2009
Black & Veatch Corp.
9441 LBJ Freeway — Suite 114
Dallas, Texas 75243
Attn: Ms. Laura Stratton
RE: Southeast Water Reclamation Plant Improvements
Contract ITB # 07-730-BM — Project # 92126
The City of Lubbock, Texas
Black & Veatch Corporation
Subj.: Proposed Contract Modification (PCM-39A) — Delete Demolition of the Existing
Washwater Detention Basin
Dear Laura:
Per the request in your e-mail dated December 04, 2009 and our subsequent telephone
conversation yesterday, Eagle Contracting L.P. has revised our cost proposal for the
above referenced PCM to reflect the items we discussed. The revised Credit proposal to
delete this work is Sixty Two Thousand Nine Hundred Thirty Four Dollars and Twenty -
Four Cents—($62,934.24). Let me know if you require any further information.
Sincerely,
JDa'-'0_
Dave Mullenix
Eagle Contracting L.P.
cc: File (Proposals) & Field
P.O. Box 1600 0 Keller, Texas 76244 - Metro (817) 379-1897 0 Metro (817) 379-0610 Fax
14-p wI 9
REQUEST FOR INFORMATION
PROJECT: SOUTHEAST WATER RECLAMATION PLANT IMPROVEMENTS PROJECT NUMBER:
OWNER: THE CITY OF LUBBOCK, TEXAS 92126
CONTRACTOR: EAGLE CONTRACTING, LP 171
ENGINEER: BLACK & VEATCH CORPORATION
REFERENCE DATA:
Contractor RFI No. 099 Spec Section: Page No. Para.
Drawing No. E49
CONTRACTOR REQUESTS: N Information ❑ Interpretation ❑ Clarification
Please reference the attached information from Acme Electric. Drawing E49 has no special notation of
using a different type of conduit for the existing Solids Building so Acme intended on using the specified
Galvanized Rigid Steel Conduit. The existing conduit in this area appears to be PVC Coated Steel
Conduit. Is Galvanized Rigid Steel conduit the material you wish installed in this area?
CONTRACTOR'S PROPOSED SOLUTION:
REQUESTED BY: O&a4,,jL DATE: 10/06/09
ENGINEER'S RESPONSE: ❑ Information .❑ Interpretation ® Clarification
For the items described above or in the attached material referenced:
As discussed at the Progress Meeting on October 7th, the conduit in the
eauitiment area of the Solids Building shol=l1d he PVC coated steel conchli
RESPONSE BY: Laura A. Stratton/wml DATE: 10/09/2009
SASandREagle Contracting FIIesVob Files1171 - Lubbock WWTP1RFrs1RFl-099-Conduit In SoNds Eldg.doo
I � P r,., 3
October 30, 2009
Black & Veatch Corp.
9441 LBJ Freeway — Suite 114
Dallas, Texas 75243
Attn: Ms. Laura Stratton
RE: Southeast Water Reclamation Plant Improvements
Contract ITB # 07-730-BM — Project # 92126
The City of Lubbock, Texas
Black & Veatch Corporation
Subj.: Proposed Contract Modification (PCM-40) — Provide PVC coated steel conduit
inside the existing Solids Building in lieu of Galvanized Steel Conduit
Dear Laura:
Per the response to RFI-099, enclosed is a cost proposal to install PVC coated steel
electrical conduit inside the existing Solids Building in lieu of the specified galvanized
steel conduit. The cost to perform this work is Two Thousand Two Hundred Twenty
Eight Dollars and Fifty -Two Cents ($2,228.52).
Sincerely,
Dave Mullenix
Eagle Contracting L.P.
cc: File (Proposals) & Field
P.O. Box 1600 0 Keller, Texas 76244 0 Metro (817) 379-1897 0 Metro (817) 379-0610 Fax
I1_,__ -.:?
BLACK & VEATCH
r. building a world of difference -
ENERGY WATER INFORMATION GOVERNMENT
City of Lubbock, Texas
Southeast Water Reclamation Plant
Contract No. 6
Mr. Glenn Grant
Eagle Contracting, L.P.
P.O. Box 1600
Keller, TX 76244
Subject:
Dear Mr. Grant:
B&V Project 140092.6100
B&V File G-1.6
October 23, 2009
Addition of an end stop at the IMLS monorail
During the course of the project, it was determined that a detail for the end stop was not included in the
Contract Documents. An end stop will be required at the end of the monorail at the Intermediate Lift
Station. Attached, please find a detail for the end stop. Please have this added to the existing monorail
prior to the use of the system to remove the submersible pumps.
Please feel free to call me at 214/570-7076 should you have any questions.
Sincerely,
Laura A. Stratton, P.E.
Engineering Manager
LAS
cc: Mr. Soo Koon Soon, City of Lubbock, pdf copy
Mr. John Kelley, Parkhill, Smith & Cooper, pdf copy
Mr, Roland Holder, Parkhill, Smith & Cooper, pdf copy
Mr. Gary Smith, Black & Veatch, pdf copy
Mr, Rich Houghton, Black & Veatch, pdf copy
Black & Veatch Corporation • 9441 LBJ Freeway • Sulte 114 • Dallas, TX 75243 USA • Telephone: 214.570.7000
Black & Veatch Corporatlon - Registration No. F-258
nE
November 2, 2009
Black & Veatch Corp.
9441 LBJ Freeway — Suite 114
Dallas, Texas 75243
Attn: Ms. Laura Stratton
RE: Southeast Water Reclamation Plant Improvements
Contract ITB # 07-730-BM — Project # 92126
The City of Lubbock, Texas
Black & Veatch Corporation
Subj.: Proposed Contract Modification (PCM-41) — Add End Stops to the IMLS
Monorail
Dear Laura:
As requested by you, Eagle Contracting will install 4each end stops on the IMLS
Monorail per the attached instructions for the Total Lump Sum Amount of Nine Hundred
and Fifteen Dollars and Sixty Seven Cents ($915.67).
Sincerely
t
Project Manager
cc: File (Proposals) & Field
P.Q. Box 1600 a Keller, Texas 76244 0 Metro (817) 379-1897 0 Metro (817) 379-0610 Fax
November 2, 2009
Black & Veatch Corp.
9441 LBJ Freeway —Suite 114
Dallas, Texas 75243
Attn: Ms. Laura Stratton
RE: Southeast Water Reclamation Plant Improvements
Contract ITB # 07-730-BM — Project # 92126
The City of Lubbock, Texas
Black & Veatch Corporation
Subj.: Proposed Contract Modification (PCM-42) — Purchase the remaining RCP
Manhole Material that the City of Lubbock cannot provide.
Dear Laura:
As requested by Lubbock, Eagle Contracting is providing the remainder of the
72" RCP Manhole material that Lubbock could not provide as they said they would in
PCM-22 for the Total Lump Sum Amount of Seven Thousand Six Hundred and Eighty
Five Dollars and Forty Five Cents ($7,685.45).
Sincerely
ant
Project Manager
cc: File (Proposals) & Field
P.O. Box 1600 Keller, Texas 76244 - Metro (817) 379-1897 0 Metro (817) 379-0610 Fax
11 C
November 30, 2009
Black & Veatch Corp.
9441 LBJ Freeway —Suite 114
Dallas, Texas 75243
Attn: Ms. Laura Stratton
RE: Southeast Water Reclamation Plant Improvements
Contract ITB # 07-730-BM — Project # 92126
The City of Lubbock, Texas
Black & Veatch Corporation
Subj.: Proposed Contract Modification (PCM-43R) — Install 6" diameter Sleeve under
Concrete Paving east of Plant 4 UV for Future Chlorine Line
Dear Laura:
Eagle Contracting has added a 6" diameter sleeve under the Concrete Paving just
east of Plant 4 UV Basin for a Future Chlorine Line. The Total Lump Sum Amount of
this extra work is One Thousand Four Hundred and Eighty One Dollars and Sixty Two
Cents ($1,481.62).
Sincerely
ant
Sincerely
Manager
cc: File (Proposals) & Field
P.O. Box 1600 i Keller, Texas 76244 0 Metro (817) 379-1897 0 Metro (817) 379-0610 Fax
1 !'
S42kr�kC'(owdY ncea
ENERGY WATER INFORMATION 80E11NMENT
City of Lubbock, Texae
Southeast Water Reclamation Plant
Contract No: e.
Mr. Glenn Grant.
Ee Cohtracting,.L.P.
P-2 66X 1 wo
kelter; TX: 76244
Subject:
17.ear Mr. Grant:
B&V Project 140692.e10b
Mv. File ii-1.0
0ctoberr29, 2MG
Replaceiment of mud valve MV-102
it, has CorKre to our attention that when the screening channel for riew $cream FS-1202 was drained, mind
valve MVj102 +Has disc oVorod to be severely deteriorated and In need of replacement. The original shop
drawing data for the mud: valve was transmitted on April 14, 2Q09. the new -stem shall be -wrench nut
operated, non -rising, and shall match the length of the original stem. Thestem and gaides shell meet tha
requirements of -Sections 15100 and 15180.
We request that Eagle provide a cost proposal for the work.
Please feel frea to call me at 2141570=7076 should you have any questions.
Sincerely,
BLACK '& VEATCH
Laura A. Stratton, P.E.
B'ngfneering Mahager
LAS
cc: Mr. Soo Koon Soon, Cityof Lubbock, pdf copy
Mr. Gary Smith, Black & Veatch, pdf copy
Mr. Rich Houghton, Black & Veatch, pdf copy,
Black A Vo" Corporation • UO LBJ Freeway • sule 114.Oai&, TX 75243 USA • Telephone: 214570.7000
Bieck & Veetch.Co refm - REgishaBcn No. F•258
November 3, 2009
Black & Veatch Corp.
9441 LBJ Freeway —Suite 114
Dallas, Texas 75243
Attn: Ms. Laura Stratton
RE: Southeast Water Reclamation Plant Improvements
Contract ITB # 07-730-BM — Project # 92126
The City of Lubbock, Texas
Black & Veatch Corporation
Subj.: Proposed Contract Modification (PCM-44) —Replace Mud Valve NW-102 in the
Headworks.
Dear Laura:
As requested by You, Eagle proposes to remove and replace Mud Valve MV-102
for the Total Lump Sum Amount of Two Thousand Six Hundred and Seventy Four
Dollars and Seventy Six Cents ($2,674.76). I know that you only asked for a new Stem
and Stem Guide but we cannot remove the existing stem from the existing mud valve
without tearing up the mud valve so I included and new mud valve.
Sincerely,
Grant
Project manager
cc: File (Proposals) & Field
P.O. Box 1600 a Keller, Texas 76244 0 Metro (817) 379-1897 0 Metro (817) 379-0610 Fax
a�/ � a w•
*/ L ,t_.
/CI
November 10, 2009
City of Lubbock Water Engineering
1625 131h Street
Lubbock, Texas 79401
Attn: Mr. Wood Franklin
RE: Southeast Water Reclamation Plant Improvements
Contract ITB # 07-730-BM — Project # 92126
The City of Lubbock, Texas
Black & Veatch Corporation
Subj.: Proposed Contract'Modification (11CUI-46)-- Provide and insult new Ha::k
Analyzers in BNR Basin No. 3.
Dear Wood:
Per your request during the last progress meeting, enclosed is a cost proposal to provide
and install five new Hach Analyzers in BNR Basin No. 3. These Analyzers will be
installed and powered per the attached scope of work. The cost to perform this work is
Two Hundred Fifteen Thousand Seventy Eight Dollars and Twenty -Six Cents
($215,078.26). Please give me a call if you have any questions.
Sincerely,
0& a`t'
Dave Mullenix
Eagle Contracting L.P.
cc: File (Proposals) & Field
P.O. Box 1600 do Keller, Texas 76244 0 Metro (817) 379-1897 a Metro (817) 379-0610 Fax
BLACK & VEATCH
r. building a world of difference -
ENERGY WATER INFORMATION GOVERNMENT
City of Lubbock, Texas
Southeast Water Reclamation Plant
Contract No. 6
Mr. Glenn Grant
Eagle Contracting, L.P.
P.O. Box 1600
Keller, TX 76244
Dear Mr. Grant:
B&V Project 140092.6100
B&V File G-1.6
October 23, 2009
Subject: Electrical trolley on Headworks hoists
As discussed during the progress meeting on October 7, 2009, Eagle is being requested to revise the
manual trolley on the two 5 ton hoists over the screens in the Headworks to an electric trolley. Paragraph
2-4.02.02 of Section 14622 shall be revised to say:
"The trolley drive shall be a sealed worm or spur gear unit, permanently lubricated with
an oil bath. Drive wheels shall have integrally cut spur gear teeth or machine -cut gears
pressed on hubs. Drive wheel treads shall be hardened.
When a festooned power cord type power system is required, the hoist trolley shall have
a suitable member to contact and push the bumper of the adjacent conductor cord
trolley."
Please provide a cost proposal to complete the requested work. The work will not be authorized until a
change order has been processed.
Please feel free to call me at 214/570-7076 should you have any questions.
Sincerely,
X•CK & VX'tTCri'
Laura A. Stratton, P.E.
Engineering Manager
LAS
cc: Mr. Soo Koon Soon, City of Lubbock, pdf copy
Mr. Gary Smith, Black & Veatch, pdf copy
Mr. Rich Houghton, Black & Veatch, pdf copy
Black & Veatch corporation • 9441 LBJ Freeway • Sub 114 • Dallas, TX 75243 USA • Telephone: 214.570,7000
Black & Veatch Corporation - Reostrallon No. F-258
November 11, 2009
Black & Veatch Corp.
9441 LBJ Freeway —Suite 114
Dallas, Texas 75243
Attn: Ms. Laura Stratton
RE: Southeast Water Reclamation Plant Improvements
Contract ITB # 07-730-BM — Project # 92126
The City of Lubbock, Texas
Black & Veatch Corporation
Subj.: Proposed Contract Modification (PCM-47) — Convert the two (2) each five ton
hoists in the Headworks from manual to electric trolleys
Dear Laura:
As requested by the owner during the last progress meeting and your letter dated October
23, 2009, attached is a cost proposal to provide electric trolleys to the two existing five -
ton hoists at the Headworks. Due to the nature of this work this conversion cannot be
done on the project site and has to be done in Ga.ffey's shop in Fort Worth. This proposal
therefore includes freight costs for shipping the Hoists from Lubbock to Fort Worth and
back to Lubbock.
The cost to perform this work is Thirty Four Thousand Five Hundred Forty Three Dollars
and Eleven Cents ($34,543.11).
Sincerely,
VD4'..�M�
Dave Mullenix
Eagle Contracting L.P.
cc: File (Proposals) & Field
P.O. Box 1600 a Keller, Texas 76244 & Metro (817) 379-1897 0 Metro (817) 379-0610 Fax
. ..
BLACK & VEATCH
building a world of difference -
ENERGY WATER INFORMATION GOVERNMENT
City of Lubbock, Texas
Southeast Water Reclamation Plant
Contract No. 6
Mr. Glenn Grant
Eagle Contracting, L.P.
P.O. Box 1600
Keller, TX 76244
Dear Mr. Grant:
B&V Project 140092.6100
B&V File G-1.6
December 9, 2009
Subject: Arch Encasement at Plant 3 Filter Influent
At the progress meeting on December 2, 2009, we discussed the protection of the joints of the 42-inch
Filter Influent line at Plant 3 where is crosses underneath the plant road north of Primary Clarifier No. 1.
From our discussion, the pipe supplier is recommending protection of the joints that are located beneath
the road. This recommendation comes from the cover of the pipe being approximately 4-feet. Black &
Veatch has reviewed the arrangement and we recommend that the pipe beneath the road be protected
with a concrete arch encasement. This concrete arch encasement will be as shown in Detail F/CY15.
The encasement will begin south of the retaining wall and extend to the north side of the road, as
indicated on the attached sketch.
If the Contractor believes this to be additional work, a cost proposal shall be submitted.
Please feel free to call me at 214/570-7076 should you have any questions.
Sincerely,
BLACK & VEATCH
Laura A. Stratton, P.E.
Engineering Manager
LAS
cc: Mr. Wood Franklin, City of Lubbock, pdf copy
Mr. Zoltan Fekete, City of Lubbock, pdf copy
Ms. Mary Gonzales, City of Lubbock, pdf copy
Mr. Rich Houghton, B&V, pdf copy
Black & Veatch Corporation 9441 LBJ Freeway • Sub 114 • Dallas, TX 75243 USA - Telephone: 214.570.7000
Black & Veatch Corporation - Registration No. F-258
December 10, 2009
Black & Veatch Corp.
9441 LBJ Freeway — Suite 114
Dallas, Texas 75243
Attn: Ms. Laura Stratton
RE: Southeast Water Reclamation Plant Improvements
Contract ITB # 07-730-BM — Project # 92126
The City of Lubbock, Texas
Black & Veatch Corporation
Subj.: Proposed Contract Modification (PCM-49) — Add Concrete Arch Encasement for
the Plant 3 — 42" Filter Influent Piping under the Paving
Dear Laura:
Eagle Contracting, L.P. proposes to add Concrete Arch Encasement for the Plant
3 — 42" Filter Influent Piping that lies under the Paving and has about 4 foot of cover.
The Total Lump Sum Amount we request for this work is Five Thousand Eight Hundred
and Seventy Two Dollars and Eighty Five Cents ($5,872.85).
Sincerely,
Grant
Project Manager
cc: File (Proposals) & Field
P.O. Box 1600 0 Keller, Texas 76244 0 Metro (817) 379-1897 a Metro (817) 379-0610 Fax
REQUEST FOR INFORMATION
PROJECT: SOUTHEAST WATER RECLAMATION PLANT IMPROVEMENTS PROJECT NUMBER:
OWNER: THE CITY OF LUBBOCK, TEXAS 92126
CONTRACTOR: EAGLE CONTRACTING, LP 171
ENGINEER: BLACK & VEATCH CORPORATION
REFERENCE DATA:
Contractor RFI No. 104 Spec Section: Page No. Para.
Drawing No. MSS
CONTRACTOR REQUESTS: ®information 0 interpretation 0 Clarification
Drawing MS6 calls for the Suction Piping for the two New Penn Valley Double Disc Pumps to have two
90-degree horizontal bends prior to entering the Pumps. The Manufacture recommends that the Suction
Piping not have these horizontal bends (the suction piping from the Gravity Belt Thickeners should be in
line with the Suction of the TWAS Pumps). Please note that this is a minimum requirement. The
manufactures best -case scenario would be for the horizontal suction & discharge to be in line with the
Pump. Please get with the Plant to see if you want this piping changed. Se the attached letter from
SWEET and their drawing.
CONTRACTOR'S PROPOSED SOLUTION:
REQUESTED BY: DATE: 11/25/09
ENGINEER'S RESPONSE: 91 Information ❑ Interpretation O Clarification
For the items described above or in the attached material referenced:
See attached for response.
RESPONSE BY: Laura A. Stratton/al DATE: 12/11/2009
SASandflZaple Caftactlnp FllesUab FlIesN 71 - Lubbock WMPIRM'SWI-104-TWAS Suction Plping.doc
RFI-104 Response, 12/11/2009
There are two options to remove the horizontal bends from the suction piping.
See attached sketches. After reviewing the associated cost, a decision will be
made on which Option to incorporate.
Option 1:
This involves moving the horizontal bends to the discharge piping. The
discharge piping will connect to the existing header in the location indicated on
MS6. All of the existing pipe as designed would be reused, just in a modified
configuration.
The 10-112" spool piece (Item 1318 from Ferguson drawing B04217) will be
placed on the suction side of the pump, after the two 900 bends. The 8-114"
spool piece (Item 1316) will be located between the check valve and the
diaphragm valve on the discharge.
The modifications apply to all three trains. The Contractor shall submit a cost
proposal to make the piping modifications to the train with existing pump P-2502.
Option 2:
This involves providing a straight run of pipe on both the suction and the
discharge side. Most of the pipe would be used in a modified configuration.
The 10-1 /2" spool piece (Item 1318) will be placed on the suction side of the
pump, after the two 900 bends. The 8-1/4" spool piece (Item 1316) will be
located between the check valve and the diaphragm valve on the discharge.
The Contractor shall use EBAA Iron series 2100 Megaflanges, or other equal
wedge -style restrained flange system, where making the connection of the
existing Tee into the new location on the discharge header. A flange system that
uses set screws is not acceptable.
The modifications apply to all three trains. The Contractor shall submit a cost
proposal to make the piping modifications to the train with existing pump P-2502.
The cost shall also include the work for cutting into the existing header and
reinstalling the existing Tee. A credit should be indicated for not installing Item
1323, 1325, and two pieces of Item 1315. These pieces of pipe would be
handed over to the Owner.
Resolution No. 2010-R0026
December 22, 2009
Black & Veatch Corp.
9441 LBJ Freeway — Suite 114
Dallas, Texas 75243
Attu: Ms. Laura Stratton
RE: Southeast Water Reclamation Plant Improvements
Contract ITB # 07-730-BM — Project # 92126
The City of Lubbock, Texas
Black & Veatch Corporation
Subj.: Proposed Contract Modification (PCM-50A) — Realign the TWAS Pumps &
Piping in the Solids Handling Building to enhance the Pumps Performance &
Reliability
Dear Laura:
As requested, Eagle Contracting, L.P. is offering Option 2 as amended by the
Owner to remove the Manufactures Start -Up and resetting of the Pumps Switches to
enhance all three TWAS Pumps performance and reliability. The Owner will now be
responsible for start-up and resetting Pump 2502 switches.
Option #2 entails realigning the pumps Suction and Discharge lines to be in line
with the Pumps. We have added two existing 6" Diaphragm Valves in the reworked
Discharge Header because the Plant Personnel have voiced a wish to have them. The
addition of these valves will allow us to keep pumps on line while we perform this work.
We will start by installing Pump 2501 1" since the existing pump is about to fail. During
the tie-in of this pump all three pumps will have to be off line. Amer this Pump is
running and the diaphragm valves are installed then the Plant will have at least one pump
on line during the installation of the other pumps. The Total Lump Sum Amount we
request for Option #2 is Nine Thousand Three Hundred and Seventy Six Dollars and
Ninety -Six Cents ($9,376.96).
Sincerely,
fin Grant
Project Manager
cc: File (Proposals) & Field