HomeMy WebLinkAboutResolution - 2012-R0028 - Contract - Minnix Commercial Partners Ltd.- Fire Station Roof Repair - 01_12_2012solution No. 2012—R0028
nuary 12, 2012
em No. 5.29
RESOLUTION
LL IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF LUBBOCK:
THAT the Mayor of the City of Lubbock is hereby authorized and directed to
execute for and on behalf of the City of Lubbock, Contract No. 12-10480-JOC for Fire
Station 11 roof repair, by and between the City of Lubbock and Minnix Commercial
Partners, Ltd., and related documents. Said Contract is attached hereto and incorporated
in this resolution as if fully set forth herein and shall be included in the minutes of the
City Council.
Passed by the City Council on January 12, 2012
TOM MARTIN, MAYOR
ATTEST:
Rjb.cVa Garza, City Secretary
APPROVED AS TO CONTENT:
Mark arwoo , Assistant City Manager
Chief Information Officer
APPROVED AS TO FORM:
Chad Weaver, Assistant City Attorney
vw:ccdocs/RES.Comract-Minn ix
December 20, 2011
Contract No. 10480
Resolution No. 2012—R0028
Work Order Signature Document
BUYBOARD EQIQC Contract No.: Area I —1 MCP — Option 1
1-1 New Work Order1-1 Modify and Existing Work Order
Work Order Number: 011604.00 Work Order Date:11/04/2011
Work Order Title: City of Lubbock — Fire Station 11 Roof Repair
Owner Name: City of Lubbock Contractor Name: Minnix Commercial Partners, LTD.
Contact: Brad Reed Contact: Keenan Davis
Phone: (806) 790-7301 Phone: (806) 798-7335
Work to be Performed
Work to be performed as per the Final Detailed Scope of Work Attached and as per the terms and conditions of
BuyBoard EZIQC Contract No Area I —1 MCP — Option 1.
Brief Work Order Description:
Fire Station 11 Roof Repair
Time of Performance See Schedule Section of the Detailed Scope of Work
Work Order Number
011604.00
CITY OF LUBBOCK
/ /leis-s
Tom Martin, Mayor
Attest:
Rebecca Garz , City Secretary
Location
Fire Station 11
APPROVED AS CONTENT:
Mark)rei-rwcW Assistant City Manager
Amount of Contract
$125,797.53
Keenan ftaff!Project Manager
Minnix Commercial Partners, LTD
0 . er's Representative
NW-91ey Everett, Director of Facilities
A7PD TO FORM:
Assistant City Attorney
Resolution No. 2012-R0028
W�Boarde`
$I C
Detailed Scope of Work
To: Keenan Davis From: Brad Reed
Minnix Commercial Partners, LTD City of Lubbock
PO Box 64895 1625 13th St
Lubbock, TX 79464 Lubbock, TX 79401
(806)798-7335 806 790-7301
Date Printed: November 04, 2011
Work Order Number: 011604.00
Work Order Title: City of Lubbock - Fire Station #11 Roof Repair
Brief Scope: Fire Ststion #11 Roof Repair.
Preliminary Revised ❑X Final
The following items detail the scope of work as discussed at the site. All requirements necessary to accomplish the
items set forth below shall be considered part of this scope of work.
We propose to furnish labor and materials necessary to complete the work outlined below:
Upper roof
1) Remove and haul away existing roofing and insulation.
2) Prime existing concrete deck, and mop on one layer of 1" C6S wood fiber roof insulation.
3) At eaves, install 1/2" plywood nailers to level up the new insulation in (2) above. Secure the nailer with nail -in type
concrete anchors. At all eaves except those with gutter, add one extra 2X4 nailer and tapered edge strip to create a
raised edge.
4) Mop on four plies of Type IV fiberglass felt using Type IV asphalt.
5) Flood surface with Type IV asphalt and install gravel surfacing.
6) At walls and curbs, install perlite cant strip, one ply of Type IV fiberglass felt, and one ply of modified bitumen
membrane as base flashing. Secure top of base flashing with aluminum termination bar.
7) Fabricate and install 24 ga. prefinished gravel guard, counterflashing, gutter, and expansion joint cover; gravel guard
to be secured on outer face with a continuous 22 ga. clip.
8) Furnish and install new 04 pipe supports as needed for horizontal lines.
9) Fabricate and install 24 ga. GI pitch pans and square vent base flashings.
10) Furnish and install new 4 lb. lead plumbing flashings and roof drain flashings.
11) Upon completion, and inspection and approval by GAF, a 15-year labor and material guarantee will be issued.
Lower Roof
1) Remove and haul away existing roofing.
2) Nail on one ply of #75 fiberglass base sheet.
3) Mop on four plies of Type IV fiberglass felt using Type IV asphalt.
4) Flood surface with TYpe IV asphalt and install gravel surfacing.
5) At walls and curb, install perlite cant strip, one ply of Type IV fiberglass felt, and one ply of modified bitumen base
flashing. Secure top of base flashing with aluminum termination bar,
6) Fabricate and install 24 ga. prefinished coping and counterflashing.
7) Furnish and install new 04 pipe supports as needed for horizontal lines.
8) Fabricate and install 24 ga. GI square vent base flashing and pitch pan.
9) Furnish and install 4 lb. lead plumbing flashings and roof drain flashings.
10) Upon completion and inspection and approval by GAF, a 15 year labor and material guarantee will be issued.
Scope of VNmk Page 1 of 2
EZ/QC - Buy Board f 1i4r2o1 f
Contractor's Price Proposal CSI - Detail
Date: November 04. 2011
Re: IQC Master Contract #: Area I - 1 MCP - Option 1
Work Order #: 011604.00
Owner PO #:
Title: City of Lubbock - Fire Station #11 Roof Repair
Contractor: Minnix Commercial Partners, LTD
Proposal Value: $125.797.53
_ Sect Item Modtfer UOM Description Line Total
Labor Equip. Material (Excluded If marked with on R)
01 - General Requirements
1 01000 0019 FA Investlpathre Consulting
$7,113.64
Quantity
Unit Price
Factor
Total
NPP Installation 1.00 x
7,113.64 x
1.0000
7,113.64
2 01520 0005 MO ADA Portable Toilets, Chemical
$131.25
Quantity
Unit Price
Factor
Total
Installation 100 x
1D4.99 x
1.2501
131.25
Subtotal for 01 - General Requirements
$7,244.89
06 - Wood, Plastic, and Composites
3 06110 0094 LF 4'x4" (10cm x 10cm) Post
$0.00
Quantity
Unit Price
Factor
Total
Installation 0.00 x
1.66 x
1.2501
0.00
4 06110 0139 LF 2"x4" (5cm x 10cm) Pressure Treated Blocking To Concrete
$0 00
Quantity Unit Price
Factor
Total
Installation 0.00 x 1.61 x
1.2501
0.00
Subtotal for 06 - Wood, Plastic, and Composites
$0.00
07 - Thenml & Moisture Protection
5 07213 0005 SF 1" (25mm) Mineral Fiberboard Roofing Insulation, R2.78
$15,322AS
Quantity Unit Price
Factor
Total
Installation 11 900 00 x 0.86 x
1.2501 =
12,793.52
Demolition 11,900.00 x 0.17 x
1.2501 =
2.528.95
6 07MOD 0005 0038 SF For Setting In Hot Asphalt, Add
$1.785.14
Quantity Unit Price
Factor
Total
Installation 11.900.00 x 0.12 x
1.2501 =
1,785.14
7 07510 0040 SF 10001.25000 SF Fiberglass Felt Bituminous Roofing AssemblyNote: Including
$79,318.85
base sheet, 2 ply of fiberglass felt, drip edge, gravel stop, cant strip, flashing
and ballast
Quantity Unit Pnce Factor
Total
Installation 14,100.00 x 4,02 x 1.2501
70,858.17
Demolition 14,100.00 x 0.48 x 1.2501 =
8,460.68
6 07MOD 0040 0146 For Each Additional Sheet Of Fiberglass Ply, Add
$21,151.69
Quantity Unit Price Factor
Total
Installation 28,200.00 x 0.60 x 1.2501
21.151.69
9 07515 0014 SO Water Based Asphaltic Primer applied to smooth surfaces (200 SF/Gallon)
$0 00
Quantity Unit Price Factor
Total
Installation 0.00 x 25.33 x 1,2501
0.00
Contractors Price Proposal - Detail Page 1 of 2
EZ10C - Buy Board 11/412011
Contractor's Price Proposal - Detail Continues..
Work Order Number: 011604.00
Work Order Title: City of Lubbock - Fire Station #11 Roof Repair
Sect
Item
Modihr 1.1011i1 Description
Line Total
Labor
Equip.
Material
(Excluded If marked with an X)
07 - Thermal 3 Moisture Protection
10
07620
0070
LF 12-14' Wide (Stretch -out). 0.04" Thick Aluminum Coping System, Mill Finish
$0 00
With Galvanized Steel Cleats
Quantity Unit Price
Factor
Total
Installation 0.00 x 12.49 x
1,2501
000
11
07020
0088
LF 24" Galvanized Steel Roof Transition Cover
$0.00
Quantity Unit Price
Factor
Total
Installation 0.00 x 6.95 x
1.2501
0.00
12
07831
0073
LF 6" Galvanized Steel Gutter, 28 Gauge
$0.00
Quantity Unit Price
Factor
Total
Installation 0.00 x 3.20 x
1,2501
0.00
13
07MOD
0073
0220 For 24 Gauge. Add
$142.51
Quantity Unit Price
Factor
Total
Installation 150.00 x 0.76 x
1.2501
142.51
14
07680
0024
LF 24 Gauge Galvanized Steel Gravel Stop, 6" Face, With Continuous Cleat
$0.00
Quantity Unit Price
Factor
Total
Installation 0.00 x 5.11 x
1,2501
0.00
15
07720
0002
EA 4" x 4" Pitch Pocket, Galvanized Sheet Metal, 24 Gauge, Filled
$0.00
Quantity Unit Price
Factor
Total
Installation 0.00 x 36.61 x
1.2501
0.00
Subtotal for 07 - Thermal & Moisture Protection
$117,720.67
15 - Mechanical
16 15770 0037 FA 5 Ton Coding, 100 M8H Gas Heeling Self Contained Package Rooftop Unit $631.97
Quantity Unit Price Factor Total
X Installation 2.00 x 221.81 x 1.2501 ' 554.57
X Demolition 2.00 x 110.95 x 1.2501 = 277.40
Subtotal for 15 - Mechanical $831.97
Proposal Total
This total represents the correct total for the proposal. Any discrepancy between line totals,
sub -totals and the proposal total is due to rounding.
The Percentage of NPP on this Proposal: 5.65%
$125,797.53
Contractor's Price Proposal - Detail Page 2 of 2
EZ/QC - Buy Board 11i4i2011
Contractor's Price Proposal CSI - Summary
Date: November 04, 2011
Re: IQC Master Contract #
Area I - 1 MCP - Option 1
Work Order #:
011604.00
Owner PO #:
Title:
City or Lubbock - Fire Station 011 Root Repair
Contractor:
Minnix Commercial Partners, LTD
Proposal Value:
$125,797,53
01 - General Requirements
$7,2".89
06 - Wood, Plastic, and Composites
$0.00
07 - Thermal & Moisture Protection
$117,720.67
15 - Mechanical
$831.97
Proposal Total
The Percentage of NPP on this Proposal: 5.65%
$125,797.53
Contractor's Price Proposal - Summary Page 1 or 1
EZIQC - Buy Board 1114n011