HomeMy WebLinkAboutResolution - 2009-R0148a - Amendment To Contract - Parkhill, Smith, & Cooper Inc.- Engineering Services - 04_09_2009Resolution No. 2009-R0148a
April 9, 2009
Item No. 5.29
RESOLUTION
BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF LUBBOCK:
THAT the Mayor of the City of Lubbock is hereby authorized and directed to
execute an Amendment No. I and any associated documents to a professional services
Contract with Parkhill, Smith & Cooper, Inc., of Lubbock, Texas, for engineering
services for Project #91 I03, Slide Road from 4`h Street to the Loop 289 South frontage
road, which Amendment No. l is attached hereto and made a part hereof for all intents
and purposes.
Passed by the City Council this 9th day of April _, 2009.
TOM MARTIN, MAYOR
ATTEST-
Rebe ca Garza, City Secretary
APPROVED AS TO CON
harry Herqq, PE
City Engineer
APPROVED AS TO FORM:
Vandiver;
DDres/PSC-SkideRdConAmend 109Res
March 31.2009
Resolution No. 2009-R0148a
AMENDMENT NO. 1
TO AGREEMENT
CITY OF LUBBOCK, TEXAS
AND
PARKHILL, SMITH & COOPER, INC.
FOR ENGINEERING SERVICES
(CONSTRUCTION PERIOD SERVICES)
ENGINEERING SERVICES FOR PAVING IMPROVEMENTS: Slide Road from 4'h Street to the
Loop 289 Frontage Road.
THIS IS AN AMENDMENT TO THE AGREEMENT dated May 22, 2008 and entered into by and
between CITY OF LUBBOCK. TEXAS hereinafter called "Owner" and PARKHILL, SMITH &
COOPER, INC. hereinafter called the "Engineer," of 4222 851h Street, Lubbock, Texas, a corporation
duly chartered under the laws of the State of Texas. The original agreement was approved by City
Council action on May 22, 2008, Resolution No. 2008-RO193.
The purpose of this amendment is to provide additional services to the agreement, namely to include
Construction Period Services that were not included in the original agreement. This amendment will
also extend the time of the original agreement to provide time to provide the Construction Phase
Services until March I, 2010, as stipulated in paragraph 11.13 of Attachment A. Attachment A,
Attachment B, Table B-1, Exhibit A-1 and Exhibit 13-1 to this Amendment No. l are herein added to
this agreement for engineering services. All attachments hereto are made a part of this Amendment
for all purposes.
Executed in three counterparts (each of which is an original) on behalf of the Engineer by its Vice
President shown below and on behalf of the Owner by its Mayor (thereunto duly authorized) this
9th day of April , 2009.
OWNER:
CITY OF LUBBOCK
By e7— -- .
Tom Martin
Mayor
ATTEST:
By P ,
Re ecca Garza
City Secretary
APPROVED TO CONTENT:
y d
Larry D Hertel, P.E.
City Engineer
ENGI1`?EER:
PARKHILL, SM & R, INC.
By '11
dwin . avis,
Vice President
APPROVED AS TO FORM:
By
Don Vandiver
City Attorney
Resolution No. 2009-R0148a
ATTACHMENT A
TO
AMENDMENT NO. 1
TO AGREEMENT
CITY OF LUBBOCK, TEXAS
AND
PARKHILL, SMITH & COOPER, INC.
FOR ENGINEERING SERVICES
(CONSTRUCTION PERIOD SERVICES)
Owner: City of Lubbock, Texas
Project #91103: Slide Road from 4"' Street to Loop 289
A DESCRIPTION OF SCOPE OF SERVICES
The scope of services for this project is as follows: Work will not proceed until Owner has
authorized Engineer in writing to proceed.
DEFINED TERMS
A. Wherever used in this Agreement (including Attachments hereto), the terms listed below
have the meanings indicated, which are applicable to both the singular and plural
thereof:
1. Addenda — Written or graphic instruments issued prior to the opening of Bids
which clarify, correct, or change the Bidding Documents.
2. Application for Payment — The form acceptable to Engineer which is to be used
by Contractor in requesting progress or final payments for the completion of its
Work and which is to be accompanied by such supporting documentation as is
required by the Contract Documents.
3. Bid — The offer or proposal of the bidder submitted on the prescribed form setting
forth the prices for the Work to be performed.
4. Bidding Documents —The advertisement or invitation to Bid, instructions to
bidders, the Bid form and attachments, the Bid bond, if any, the proposed Contract
Documents, and all Addenda, if any.
5. Change Order — A document recommended by Engineer which is signed by
Contractor and Owner to authorize an addition, deletion or revision in the Work, or
an adjustment in the Contract Price or the Contract Times, issued on or after the
Effective Date of the Construction Agreement.
b. Construction Agreement The written instrument which is evidence of the
agreement, contained in the Contract Documents, between Owner and Contractor
concerning the Work.
7. Construction Contract — The entire and integrated written agreement between the
Owner and Contractor concerning the Work.
8. Continuous Observation Observation of construction on a basis that is sufficient
to reasonably assure substantial compliance with the plans and specifications and is
considered continuous as opposed to intermittent observation. Personnel
A-]
performing continuous observation are not required to be on a specific site 100
percent of the time, but may leave a specific site for indefinite periods of time to
observe other sites, observe other portions of project work, perform other
assignments, or leave the site if no work is being performed that, in the opinion of
the Engineer, requires observation.
9. Continuous Presence See Continuous Observation.
10. Contract Documents — Documents that establish the rights and obligations of the
parties engaged in construction and include the Construction Agreement between
Owner and Contractor, Addenda (which pertain to the Contract Documents),
Contractor's Bid (including documentation accompanying the Bid and any post -Bid
documentation submitted prior to the notice of award) when attached to the
Construction Agreement, the notice to proceed, the bonds, appropriate
certifications, the General Conditions, the Special Provisions, the Specifications
and the Drawings as the same are more specifically identified in the Construction
Agreement, together with all Written Amendment, Change Orders, Work Change
Directives, Field Orders, and Engineer's written interpretations and clarifications
issued on or after the Effective Date of the Construction Agreement. Approved
Shop Drawings and the reports and drawings of subsurface and physical conditions
are not Contract Documents.
11. Construction Contract Times — The numbers of days or the dates stated in the
Construction Agreement to: (i) achieve Substantial Completion, and (ii) complete
the Work so that it is ready for final payment as evidenced by Engineer's written
recommendation of final payment.
12. Contractor — An individual or entity with whom Owner enters into a Construction
Agreement.
13. Correction Period — The time after Substantial Completion during which
Contractor must correct, at no cost to Owner, any Defective Work, normally one
year after the date of Substantial Completion or such longer period of time as may
be prescribed by Laws or Regulations or by the terms of any applicable special
guarantee or specific provision of the Contract Documents.
14. Defective — An adjective which, when modifying the word Work, refers to Work
that is unsatisfactory, faulty, or deficient, in that it does not conform to the Contract
Documents, or does not meet the requirements of any inspection, reference
standard, test, or approval referred to in the Contract Documents, or has been
damaged prior to Engineer's recommendation of final payment.
15. Documents — Data, reports, Drawings, Specifications, Record Drawings, and other
deliverables, whether in printed or electronic media format, provided or furnished
in appropriate phases by Engineer to Owner pursuant to this Agreement.
lb. Drawings That part of the Contract Documents prepared or approved by
Engineer which graphically shows the scope, extent, and character of the Work to
be performed by contractor. Shop Drawings are not Drawings as so defined.
17. Effective Date of the Construction Agreement — The date indicated in the
Construction Agreement on which it becomes effective, but if no such date is
indicated, it means the date on which the Construction Agreement is signed and
delivered by the last of the two parties to sign and deliver.
18. Engineer's Consultants Individuals or entities having a contract with Engineer to
furnish services with respect to this Project as Engineer's independent professional
A-2
associates, consultants, subcontractors, or vendors. The term Engineer includes
Engineer's Consultants.
19, Field Order — A written order issued by Engineer which directs minor changes in
the Work but which does not involve a change in the Contract Price or the Contract
Ti mes.
20. General Conditions — That part of the Contract Documents which sets forth terms,
conditions, and procedures that govern the Work to be performed or furnished by
Contractor with respect to the Project.
21. Intermittent Observation — Observation of construction on a basis such that
specific milestones of construction progress are observed for substantial
compliance with the plans and specifications prior to beginning work toward the
next milestone. An example is checking steel reinforcement placement prior to
concrete being placed, but not being on -site continuously while the reinforcement is
being assembled.
22. Intermittent Presence See Intermittent Observation.
23. Record Drawings — The drawings as issued for construction on which the
Engineer, upon completion of the Work, has shown changes due to Addenda or
Change Orders and other information Engineer considers significant based on
record documents furnished by Contractor to Engineer and which were annotated
by Contractor to show changes made during construction.
24. Resident Project Representative — The authorized representative of Engineer,
assigned to assist Engineer at the Site during the Construction phase. The Resident
Project Representative will be Engineer's agent or employee and tinder Engineer's
supervision. As used herein, the term Resident Project Representative includes any
assistants of Resident Project Representative agreed to by Owner.
25. Samples — Physical examples of materials, equipment, or workmanship that are
representative of some portion of the Work and which establish the standards by
which such portion of the Work will be judged.
26. Shop Drawings — All drawings, diagrams, illustrations, schedules, and other data
or information which are specifically prepared or assembled by or for Contractor
and submitted by Contractor to Engineer to illustrate some portion of the Work.
27. Site Lands or areas indicated in the Contract Documents as being furnished by
Owner upon which the Work is to be performed, rights -of -way and easements for
access thereto and such other lands furnished by Owner which are designated for
use of Contractor.
29. Specifications — that part of the Contract Documents consisting of written
technical descriptions of materials, equipment, systems, standards, and
workmanship as applied to the Work and certain administrative details applicable
thereto.
29. Substantial Completion — The Date of Substantial Completion shall be determined
by the Engineer and Owner as the Date that construction is sufficiently complete, in
accordance with the Contract Documents, so the Owner can occupy or utilize the
Work for the use for which it is intended. Minor items of Work may still remain to
be completed following the Date of Substantial Completion, such as minor repairs,
aesthetic items, and final cleanup. The terms "substantially complete" and
"substantially completed" as applied to all or part of the Work refer to Substantial
Completion thereof.
A-3
30. Special Provisions — That part of the Contract Documents which amends or
supplements the General Conditions. Also may be referenced as Special
Conditions.
31. Work The entire completed construction or the various separately identifiable
parts thereof required to be provided under the Contract Documents with respect to
this Project. Work includes and is the result of performing or furnishing labor,
services, and documentation necessary to produce such construction and furnishing,
installing, and incorporating all materials and all equipment into such construction,
all as required by the Contract Documents.
32. Work Change Directive A written directive to Contractor issued on or after the
Effective Date of the Construction Agreement and signed by Owner upon
recommendation of the Engineer, ordering an addition, deletion, or revision in the
work, or responding to differing or unforeseen subsurface or physical conditions
under which the Work is to be performed or to emergencies. A Work Change
Directive will not change the Contract Price or the Contract Time but is evidence
that the parties expect that the change directed or documented by a Work Change
Directive will be incorporated in a subsequently issued Change Order following
negotiations by the parties as to its effect, if any, on the Contract Price or Contract
Times.
33. Written Amendment — A written amendment of the Contract Documents signed by
Owner and Contractor on or after the Effective Date of the Construction Agreement
and normally dealing with the non -engineering or non -technical rather than strictly
construction -related aspects of the Contract Documents.
II. BASIC CONSTRUCTION PERIOD SERVICES
A. Upon written authorization from Owner, Engineer shall:
l . General Administration of Construction Contract Consult with Owner and act as
Owner's representative as authorized by Owner.
2. Resident Project Representative (RPR) — Provide the services of an RPR at the
Site to assist the Engineer and to provide more extensive observation of
Contractor's work. Duties, responsibilities, and authority of the RPR are as set
forth in this Agreement. The furnishing of such RPR's services will not extend
Engineer's responsibilities or authority beyond the specific limits set forth
elsewhere in this Agreement.
3. Pre -Construction Conference Participate in a Pre -Construction Conference prior
to commencement of Work at the Site.
4. Visits to Site and Observation of Construction — In connection with observations
of Contractor's work in progress while it is in progress:
a. Make visits to the Site at intervals appropriate to the various stages of
construction, as Engineer deems necessary, in order to observe as an
experienced and qualified design professional the progress and quality of the
Work. Such visits and observations by Engineer, and the Resident Project
Representative, if any, are not intended to be exhaustive or to extend to every
aspect of Contractor's work in progress or to involve detailed inspections of
Contractor's work in progress beyond the responsibilities specifically
A-4
assigned to Engineer in this Agreement and the Contract Documents, but
rather are to be limited to spot checking, selective sampling, and similar
methods of general observation of the Work based on Engineer's exercise of
professional judgment as assisted by the Resident Project Representative, if
any. Based on information obtained during such visits and such observations,
Engineer will determine in general if Contractor's work is proceeding in
accordance with the Contract Documents, and Engineer shall keep Owner
informed of the progress of the Work.
b. Perform periodic construction materials testing as spot checks of the
Contractor's work and Contractor's testing agency. The bulk of the
construction materials testing will be performed by the Contractor's testing
agency.
c. Provide minor construction, property or other special field surveys.
d. Engineer shall not, during such visits or as a a'esult of such observations of
Contractor's work in progress, supervise, direct, or have control over
Contractor's work, nor shall Engineer have authority over or responsibility for
the means, methods, techniques, sequences, or procedures of construction
selected by Contractor, for safety precautions and programs incident to
Contractor's work, or for any failure of Contractor to comply with Laws and
Regulations applicable to Contractor's furnishing and performing the Work.
Accordingly, Engineer neither guarantees the performance of any Contractor
nor assumes responsibility for any Contractor's failure to furnish and perform
its work in accordance with the Contract Documents.
5. Defective Work --Recommend to Owner that Contractor's work be disapproved and
rejected while it is in progress if, on the basis of such observations, Engineer
believes that such work will not produce a completed Project that conforms
generally to the Contract Documents or that it will prejudice the integrity of the
design concept of the completed Project as a functioning whole as indicated in the
Contract Documents.
6. Clarifications and Interpretations; Field Orders --Issue necessary clarifications and
interpretations of the Contract Documents as appropriate to the orderly completion
of Contractor's work. Such clarifications and interpretations will be consistent with
the intent of and reasonably inferable from the Contract Documents. Engineer may
issue Field Orders authorizing minor variations from the requirements of the
Contract Documents.
7. Change orders and Work Change Directives --Recommend Change Orders and
Work Change Directives to Owner, as appropriate, and prepare Change Orders and
Work Change Directives as required.
8. Shop Drawings and Samples --Review and approve or take other appropriate action
in respect to Shop Drawings and Samples and other data which Contractor is
required to submit, but only for conformance with the information given in the
Contract Documents and compatibility with the design concept of the completed
Project as a functioning whole as indicated in the Contract Documents. Such
reviews and approvals or other action will not extend to means, methods,
techniques, sequences or procedures of construction or to safety, precautions and
programs incident thereto.
9. Substitutes and "or -equal --"Evaluate and determine the acceptability of substitute
or "or -equal" materials and equipment proposed by Contractor.
A-5
10. Inspections and Tests --Require such special inspections or tests of Contractor's
work as deemed reasonably necessary, and receive and review all certificates of
inspections, tests, and approvals required by Laws and Regulations or the Contract
Documents. Engineer's review of such certificates will be for the purpose of
determining that the results certified indicate compliance with the Contract
Documents.
11. Disagreements between Owner and Contractor --Render formal written decisions on
all claims of Owner and Contractor relating to the acceptability of Contractor's
work or the interpretation of the requirements of the Contract Documents pertaining
to the execution and progress of Contractor's work. In rendering such decisions,
Engineer shall be fair and not show partiality to Owner or Contractor and shall not
be liable in connection with any decision rendered in good faith in such capacity.
12. Applications for Payment --Based on Engineer's observations as an experienced and
qualified design professional and on review of Applications for Payment and
accompanying supporting documentation:
a. Determine the amounts that Engineer recommends Contractor are paid. Such
recommendations of payment will be in writing and will constitute Engineer's
representation to Owner, based on such observations and review, that, to the
best of Engineer's knowledge, information and belief, Contractor's work has
progressed to the point indicated, the quality of such work is generally in
accordance with the Contract Documents (subject to an evaluation of the
Work as a functioning whole prior to or upon Substantial Completion, to the
results of any subsequent tests called for in the Contract Documents and to
any other qualifications stated in the recommendation), and the conditions
precedent to Contractor's being entitled to such payment appear to have been
fulfilled in so far as it is Engineer's responsibility to observe Contractor's
work. In the case of unit price work, Engineer's recommendations of
payment will include final determinations of quantities and classifications of
Contractor's work (subject to any subsequent adjustments allowed by the
Contract Documents).
13. Contractor's Completion Documents.
a. Receive and review maintenance and operating instructions, schedules, and
guarantees.
b. Receive bonds, certificates, or other evidence of insurance not previously
submitted and required by the Contract Documents„ certificates of inspection,
tests and approvals, Shop Drawings„ Samples, annotated record drawings, and
other data which are to be assembled by Contractor in accordance with the
Contract Documents to obtain final payment.
C. Engineer shall transmit these documents to Owner.
14. Substantial Completion --Promptly after notice from Contractor that Contractor
considers the entire Work ready for its intended use, in company with Owner and
Contractor, conduct an inspection to determine if the Work is Substantially
Complete. If after considering any objections of Owner, Engineer considers the
Work Substantially Complete, Engineer shall deliver a certificate of Substantial
A-6
Completion to Owner and Contractor. The certificate of Substantial Completion
shall not be issued so long as major items of Work remain to be completed.
Normally, only minor "punch list" items that do not affect the function of the Work
can remain when a substantial completion certificate is issued.
15. Final Notice of Acceptability of the Work --Conduct a final inspection to determine
if the completed Work of Contractor is acceptable so that Engineer may
recommend, in writing, final payment to Contractor. Accompanying the
recommendation for final payment, Engineer shall also provide "Notice of
Acceptability of Work" that the Work is acceptable to the best of Engineer's
knowledge, information, and belief and based on the extent of the services provided
by Engineer under this Agreement. Such notice shall not be issued until all items of
the Work, including "punch list" items, are satisfactorily completed.
B. Duration of Construction Period Services. The Construction Period Services will
commence with the execution of this Amendment No. 1 and subsequent notice to proceed
from Owner to Engineer, and will terminate upon written recommendation by Engineer
for final payment to Contractors and subsequent delivery of record drawings to Owner.
In no case shall the duration of the Construction Period Services exceed March 1, 2010 as
set forth in Exhibit B-1, without modification of the professional services agreement and
schedule.
C. Limitation of Responsibilities. Engineer shall not be responsible for the acts or omissions
of any Contractor, or of any of their subcontractors, suppliers, or of any other individual
or entity performing or furnishing any of the Work on behalf of the Contractor. Engineer
shall not be responsible for failure of any Contractor to perform or furnish the Work in
accordance with the Contract Documents.
D. Resident Project Representative
This section of the Agreement defines the duties, responsibilities and limitations of
authority of Resident Project Representative.
1. Engineer shall furnish Resident Project Representative ("RPR"), assistants, and
other field staff to assist Engineer in observing progress and quality of the Work.
2. Through such additional observations of Contractor's work in progress and field
checks of materials and equipment by the RPR and assistants, Engineer shall
endeavor to provide further protection for Owner against defects and deficiencies in
the Work. However, Engineer shall not, during such visits or as a result of such
observations of Contractor's work in progress, supervise, direct, or have control
over the Contractor's Work nor shall Engineer have authority over or responsibility
for the means, methods, techniques, sequences, or procedures selected by
Contractor, for safety precautions and programs incident to the Contractor's work in
progress, for any failure of Contractor to comply with Laws and Regulations
applicable to Contractor's performing and furnishing the Work, or responsibility of
construction for Contractor's failure to furnish and perform the Work in accordance
with the Contract Documents.
A-7
3. The duties and responsibilities of the RPR are limited to those of Engineer in this
Agreement with the Owner and in the Contract Documents, and are further limited
and described as follows:
a. General: RPR is Engineer's agent at the Site, will act as directed by and under
the supervision of Engineer, and will confer with Engineer regarding RPR's
actions. RPR's dealings in matters pertaining to the Contractor's work in
progress shall in general be with Engineer and Contractor, keeping Owner
advised as necessary. RPR's dealings with subcontractors shall only be
through or with the full knowledge and approval of Contractor. RPR shall
generally communicate with Owner with the knowledge of and under the
direction of Engineer.
b. Schedules: Review the progress schedule, schedule of Shop Drawing and
Sample submittals, and schedule of values prepared by Contractor and consult
with Engineer concerning acceptability.
C. Conferences and Meetings: Attend meetings with Contractor, such as
preconstruction conferences, progress meetings, job conferences and other
project -related meetings, and prepare and circulate copies of minutes thereof.
d. Liaison:
I) Serve as engineer's liaison with Contractor, working principally
through Contractor's superintendent and assist in understanding the
intent of the Contract Documents.
2) Assist in obtaining from Owner additional details or information,
when required for proper execution of the Work.
e. Interpretation of Contract Documents: Report to Engineer when clarifications
and interpretations of the Contract Documents are needed and transmit to
Contractor clarifications and interpretations as issued by Engineer.
f. Shop Drawings and Samples.
I) Record date of receipt of Samples and approved Shop Drawings.
2) Receive Samples which are furnished at the Site by Contractor, and
notify Engineer of availability of Samples for examination.
3) Advise Engineer and Contractor of the commencement of any portion
of the Work requiring a Shop Drawing or Sample submittal for which
RPR believes that the submittal has not been approved by Engineer.
g. Modifications: Consider and evaluate Contractor's suggestions for
modifications in Drawings or Specifications and report with RPR's
recommendations to Engineer. Transmit to Contractor in writing decisions as
issued by Engineer.
h. Review of Work and Rejection of Defective Work:
I) Conduct on -Site observations of Contractor's work in progress to
assist Engineer in determining if the Work is in general proceeding in
accordance with the Contract Documents.
2) Report to Engineer whenever RPR believes that any part of
Contractor's work in progress will not produce a completed Project
that conforms generally to the Contract Documents or will prejudice
the integrity of the design concept of the completed Project as a
functioning whole as indicated in the Contract Documents, or has
been damaged, or does not meet the requirements of any inspection,
A-8
test or approval required to be made; and advise Engineer of that part
of work in progress that RPR believes should be corrected or rejected
or should be uncovered for observation, or requires special testing,
inspection or approval.
i. Inspections, Tests, and System Startups:
1) Consult with Engineer in advance of scheduled major inspections and
tests of important phases of Work.
2) Verify that tests, equipment, and operating and maintenance training
are conducted in the presence of appropriate Owner's personnel, and
that Contractor maintains adequate records thereof.
3) Observe, record, and report to Engineer appropriate details relative to
the test procedures and systems startups.
4) Accompany visiting inspectors representing public or other agencies
having jurisdiction over the Project, record the results of these
inspections, and report to Engineer.
j. Records:
1) Maintain at the Site or at Engineer's offices orderly tiles for
correspondence, reports of job conferences, reproductions of original
Contract Documents including all Change Orders, Field Orders, Work
Change Directives, Addenda, additional Drawings issued subsequent
to the execution of the Contract, engineer's clarifications and
interpretations of the Contract Documents, progress reports, Shop
Drawing and Sample submittals received from and delivered to
Contractor, and other Project related documents.
2) Prepare a daily report or keep a diary or log book, recording
Contractor's hours on the Site, weather conditions, data relative to
questions of Change Orders, Field Orders, Work Change Directives,
or changed conditions, Site visitors, daily activities, decisions,
observations in general, and specific observations in more detail as in
the case of observing test procedures: and send copies to Engineer.
31) Record names, addresses and telephone numbers of Contractors,
subcontractors, and major suppliers of materials and equipment.
4) Maintain records for use in preparing Project documentation.
5) Upon completion of the Work, furnish original set of all RPR Project
documentation to Engineer.
k. Reports:
I) Furnish to Engineer periodic reports as required of progress of the
Work and of Contractor's compliance with the progress schedule and
schedule of Shop Drawing and Sample submittals.
2) Draft and recommend to Engineer proposed Change Orders, Work
Change Directives, and Field Orders. Obtain backup material from
Contractor.
3) Furnish to Engineer and Owner copies of all inspection, test, and
system startup reports.
4) Report immediately to Engineer the occurrence of any Site accidents,
any hazardous environmental conditions, emergencies, or acts of God
endangering the Work, and property damaged by fire or other causes.
A-9
1. Payment Requests: Review Applications for Payment with Contractor for
compliance with the established procedure for their submission and forward
with recommendations to Engineer, noting particularly the relationship of the
payment requested to the schedule of values, Work completed, and materials
and equipment delivered at the Site but not incorporated in the Work.
m. Certificates. Operation and Maintenance Manuals: During the course of the
Work, verify that materials and equipment certificates, operation and
maintenance manuals and other data required by the Specifications to be
assembled and furnished by Contractor are applicable to the items actually
installed and in accordance with the Contract Documents, and have these
documents delivered to Engineer for review and forwarding to Owner prior to
payment for that part of the Work.
n. Completion:
1) Before Engineer issues a Certificate of Substantial Completion.
submit to Contractor a list of observed items requiring completion or
correction.
2) Observe whether Contractor has arranged for inspections required by
Laws and Regulations, including but not limited to those to be
performed by public agencies having jurisdiction over the Work.
3) Participate in a final inspection in the company of Engineer, Owner,
and Contractor and prepare a final list of items to be completed or
corrected.
4) Observe whether all items on final list have been completed or
corrected and make recommendations to Engineer concerning
acceptance and issuance of the Notice of Acceptability of the Work.
o. Resident Project Representative shall not:
l) Authorize any deviation from the Contract Documents or substitution
of materials or equipment (including "or -equal" items).
2) Exceed limitations of Engineer's authority as set forth in this
Agreement or the Contract Documents.
3) Undertake any of the responsibilities of Contractor, subcontractors,
suppliers, or Contractor's superintendent.
4) Advise on, issue directions relative to or assume control over any
aspect of the means, methods, techniques, sequences or procedures of
Contractor's work unless such advice or directions are specifically
required by the Contract Documents.
5) Advise on, issue directions regarding, or assume control over safety
precautions and programs in connection with the activities or
operations of Owner or Contractor.
6) Participate in specialized field or laboratory tests or inspections
conducted off -site by others except as specifically authorized by
Engineer.
7) Accept Shop Drawing or Sample submittals from anyone other than
Contractor.
8) Authorize Owner to occupy the Project in whole or in part.
A-10
E. Frequency of Construction Observation and Coordination
1. The frequency of construction observation and coordination is dependent on the
Contractor's schedule, type of operation being performed, demonstrated quality of
work, compliance with the plans and specifications, and site conditions.
2. The Engineer shall perform continuous or intermittent observation, as the
Contractor's quality of work dictates, of the following typical construction
activities expected for the Project:
a. Laying of storm sewer pipe and box culvert and adjacent trench backfilling.
b. Excavation and backfill.
C. Placement of concrete for inlets, manholes and headwalls.
d. Placement of rock riprap and concrete riprap.
C. Placement of street flexible base and asphalt stabilized base.
f. Placement of hot -mix asphaltic -cement concrete pavement.
g. Placement of Portland cement concrete paving, curb and gutter and sidewalk.
h. Preparation of surface for seeding and sod placement to include fertilizer
application to subgrade.
i. Seeding operations to include placement of seed.
j. Pavement markings.
k. Traffic Signals
I. Signs.
3. The Engineer shall perform intermittent observation of the following typical
construction activities expected for the project:
a. Construction materials field tests for density of soils, density of hot -mix
asphalt pavement, compressive strength of concrete, air content of concrete,
slump of concrete, and other such types of field testing called for in the
Contract Documents.
b. Headwall construction involving excavation phase, subgrade preparation,
reinforcing steel placement, formwork and backfill.
C. Inlet construction involving excavation phase, subgrade preparation,
reinforcing steel placement, formwork, and backfill.
d. Solid sod placement for areas receiving sod.
e. Manhole construction.
f. Temporary items such as:
1) Traffic control devices.
2) Storm water pollution prevention devices.
3) Temporary facilities and controls.
4) Project cleanup.
g. Portland cement concrete pavement and curb -and -gutter subgrade, formwork,
steel placement, pavement thickness, applicable dowels and finishes.
F. Post -Construction Period Services
1. Record Drawings. Prepare record drawings from information and drawing markups
supplied by Contractor.
A-11
G. Deliverables
1. One reproducible set of record drawings delivered to Owner.
2. One non -reproducible set of record drawings delivered to Owner.
3. Compact discs containing the electronic files of the record drawings delivered to
Owner.
4. One set of RPR inspection logs delivered to Owner.
5. Owner copies of Contractor submittals.
b. Owner copies of test results
H. Supplemental Construction Period Services
None.
I11. ADDITIONAL SERVICES
A. At the request of the Owner, the Engineer will provide Additional Services as included
herein or upon agreement between Owner and the Engineer defining the extent of such
Additional Services and the amount and manner in which Engineer will be compensated
for such Additional Services.
B. Additional Services may include but are not limited to:
l . Providing extensive construction, property or other special field surveys.
2. Construction materials testing services beyond spot checking of the work.
3. Evaluating an unreasonable claim or an excessive number of claims submitted by
Contractor or others in connection with the Work.
4. Excessive presence on the project or on project -related items above the man-hour
allowances in Exhibit A-1.
C. Any work requested by the Owner that is not included in one of the items listed in any
other place will be classified as Additional Services.
D. Additional services may be authorized by a notice -to -proceed in writing from the City
Engineer and addressed to the Engineer.
END ATTACHMENT A TO AMENDMENT NO. 1
A-12
ATTACHMENT B
TO
AMENDMENT NO. 1
TO AGREEMENT
CITY OF LUBBOCK, TEXAS
AND
PARKHILL, SMITH & COOPER, INC.
FOR ENGINEERING SERVICES
(CONSTRUCTION PERIOD SERVICES)
Owner: City of Lubbock, Texas
Project #91103: Slide Road from 4'h Street to Loop 289
COMPENSATION
BASIC SERVICES
For these services covered by this Agreement, the Owner agrees to pay the Engineer as follows:
A. GENERAL
1. The Engineer will be paid on an hourly rate basis shown in Table B-1 and
subcontract personnel services will be billed at cost. Engineer and subcontractor
reimbursable expenses will be billed at cost plus 15 percent surcharge.
Reimbursable expenses are shown in Table 13-1.
2. The Engineer agrees to use its best efforts to perform services as defined herein
within the billing limits stated below.
3. It is understood and agreed that the maximum billings of each of the items listed
below are based on the start of Services being authorized not later than
May 1, 2009, and are also contingent on the construction Contractor's diligent
prosecution of the Work. If start of Basic Services is not authorized by date
given, it is understood and agreed that the upper billing limit will be adjusted
accordingly by a supplement to this Agreement.
4. Monthly payments shall be madc to the Engineer by the Owner based on
Engineer's statement. The statement shall be itemized to indicate the amount of
work performed and the associated reimbursable expenses and subcontract costs.
5. The uncontested amount of each statement shall be due and payable upon receipt
by the Owner. Carrying charges of 1-1/2 percent per month from the billing date
shall be due for accounts that are not paid within 60 days after the billing date.
6. The Engineer shall keep records on the basis of generally accepted accounting
practices of costs and expenses and which records shall be available for
inspection by Owner during normal business hours.
7. The Engineer shall provide adequate resources to complete the services described
herein within the schedule established in Exhibit B-1, provided the construction
Contractor completes the project within the same period of time starting with a
notice -to -proceed to the Contractor. The attached schedule can be adjusted based
B-1
on the actual date of the Owner's notice -to -proceed and subsequent time
extensions given to Contractor.
B. BASIC CONSTRUCTION PERIOD ENGINEERING SERVICES
1. The maximum billed for Basic Construction Period Engineering Services
including personnel services and reimbursable expenses for the Engineer and
Subcontractors is shown as follows:
Agreement Summary for Engineering Services:
Original Basic Services Agreement $ 509,530.00
Amendment No. 1 $ 390,977.00
TOTAL ENGINEERING SERVICES NOT $ 900,507.00
TO EXCEED WITHOUT AUTHORIZATION
2. The Owner's authorized representative may use the Amendment No. I amount, or
portions thereof, to maintain adequate professional engineering services related to
the Construction Phase Services.
C. ADDITIONAL SERVICES
Additional services must be authorized in writing by the Owner.
I. The maximum billed for Additional Services will be determined by mutual
consent before the Additional Services are authorized by the Owner.
2. The Engineer shall start the performance of the authorized Additional Services
within ten (10) days of the receipt of notice to proceed and will complete the
Additional Services within the time period determined by mutual consent before
the Additional Services are authorized by the Owner.
B - 2
Resolution No. 2009-R0148a
TABLE B-1
TO
AMENDMENT NO. 1
TO AGREEMENT
CITY OF LUBBOCK, TEXAS
AND
PARKHILL, SMITH & COOPER, INC.
FOR ENGINEERING SERVICES
(CONSTRUCTION PERIOD SERVICES)
Owner: City of Lubbock, Texas
Project #91 103: Slide Road from 4"' Street to Loop 289
COMPENSATION RATES
Hourly tees listed herein will apply until December 31, 2009. Hourly fees shall be adjusted beyond
December 31, 2009 by multiplying the hourly fee by the Consumer Price Index increase published on
or after January 1, 2010 and each successive year thereafter.
A. BASIC PERSONNEL SERVICES
Catmory of Personnel /HR
Parkhill. Smith & Cooaer. Inc.
Principal -in -Charge 162.00
Project Manager or Senior Professional Engineer 137.00
Senior Professional Engineer 122.00
Professional Engineer 105.00
Engineer -In -Training 89.00
Technician/Designer/RPR (Project Representative) 78.00
Drafter/CADD Operator 71.00
Clerical 63.00
Hugo Reed & Associates. Inc.
Principal -in -Charge or Officer 140.00
Enginecring Project Manager or Surveying Project Manager 127.00
Senior RPLS or Senior Engineer 116.00
Professional Engineer 105.00
Engineer -In -Training 87.00
Technician, Survey Crew Manager, or Senior CADD Technician 75.00
Survey Crew 175.00
ME
Category of Personnel /HR
Yvonne Newman EnuineerinQ, Inc.
Principal -in -Charge
140.00
Project Manager
127.00
Senior Professional Engineer
116.00
Professional Engineer
105.00
Engineer -In -Training
97.00
Technician or Designer
75.00
Drafter CADD
39.00
REIMBURSABLE EXPENSES
The following expenses are reimbursable:
1. Travel, subsistence and incidental costs.
2. Use of motor vehicles on a monthly basis for assigned vehicles and on a current
mileage basis or rental cost basis for vehicles used for short periods.
3. Telegraph costs, long distance telephone costs, cell phone usage and project
"onsite" telephone costs.
4. Reproduction of reports, drawings and specifications.
5. Postage and shipping charges for project -related materials.
6. Computer time charges, including program use charges.
7. Rental charges for use of equipment.
S. Cost of acquiring any other materials or services specifically for and applicable to
only this Project.
9. GPS equipment for usage for survey.
END ATTACHMENT B TO AMENDMENT NO. 1
AMENDMENT NO. I TO AGREEMENT
EXHIBIT A -I
BASIC CONSTRUCTION PERIOD SERVICES
TASKING, MAN-HOURS, REIMBURSABLES, AND SUBCONTRACTORS
AMENDMENT NO. 1
EXHIBIT A-1
CITY OF LUBBOCK, TEXAS
ENGINEERING SERVICES
Slide Road from 4th Street to Northwest Loop 289 - Project # 91103
ESTIMATE OF MAN-HOURS and TASKS - CONSTRUCTION PHASE SERVICES
SUMMARY
Basic
Basic
Personnel
Reimbursable
Company
Services
Expenses
TOTAL
Parkhill, Smith & Cooper, Inc.
$304,863
$15,693
$320,556
Hugo Reed & Associates
$39,780
$605
$40,385
Yvonne Newman Engineering, Inc.
$22,036
$1,156
$23,192
Terra Engineers, Inc.
$6,844
$6,844
TOTALS
$366,679
$24,298
$390,977
1 Of i o
AMENDMENT NO. 1
EXHIBIT A-1
CITY OF LUBBOCK, TEXAS
ENGINEERING SERVICES
Slide Road from 4th Street to Northwest Loop 289 - Project #91103
ESTIMATE OF MAN-HOURS and TASKS - CONSTRUCTION PHASE SERVICES
WORKSHEET 1
Parkhill, Smith & Cooper, Inc
30-Mar-09
Task
Prin.
Pro).
Sr.
Prot.
EIT
RPR
Drafter
Clerical
Total
Total
in
Mgr.
Prof.
Engr
or
CADD
Hours
Extension
Charge
Engr,
Technician
f$1
«««««« Rates »»»»»»
$162.00
$137.00
$122.00
$105, 00
$88.00
$78.00
$71.00
563.00
A
f�ffiERVNC-
Resident Project Representation - See RPR
1
Detail Below.
Pre Construction Conference:
2
Prepare Agenda (1 hr.). Attend Meeting (4
4
8
4
2
18
$1 ,866
hr.). Prepare and Distribute Meeting Minutes
(3 hr.).
Biweekly Progress Meetings:
7 Month Duration'2 meetings/mo. = 14
Progress Meetings:
Attendees.
3
14 m1gs.'4 hrs./mtg. = 56 hrs.
56
112
14
182
$20,314
Proiect Manager:
Each Meeting = Prepare Agenda (1 hr.),
Attend Meeting (4 hr.), Prepare and
Distribute Meeting Minutes (3 hr.).
14 mtgs."8 hrs./mtg. = 112 hrs.
Visits to Site and Observation of
Construction:
4
7 month duration, Estimate 2 visit/week @ 2
4
28
120
152
$17,084
hrs/visit:
7 mo'4 wks/mo'2 vists/wk'2 hrs/visit = 112
hr.s (use 120 hrs)
Coordination, Correspondence, and
Responses to Questions from Contractor,
5
City of Lubbock, RPR, and Public:
a
100
375
80
563
$59,411
7 month duration, Estimate 2.5 hrs/day:
7 mo'21 wkng days/mo`2.5 hrs/day = 367
hrs (use 375 hrs).
Detective Work:
6
Time is Included Above.
Clarifications and Interpretations: field
7
Orders:
5
10
40
80
10
145
$12,690
Estimate 10 field orders at 4 hrs/field order.
Change Orders and Work Change
8
Directives:
2
10
20
40
5
77
$6,949
Estimate 5 Change Orders at 4 hrs/change
order.
9
Shop Drawings and Samples
5
10
10
25
$2,365
Estimate 10 Submittals at 1 hr/submittal.
20110
AMENDMENT NO. 1
EXHIBIT A-1
CITY OF LUBBOCK, TEXAS
ENGINEERING SERVICES
Slide Road from 4th Street to Northwest Loop 289 - Project #91103
ESTIMATE OF MAN-HOURS and TASKS - CONSTRUCTION PHASE SERVICES
wORKSHEET 1
Parkhill, Smith & Cooper, Inc
30-Mar-09
Task
Prin.
Proj,
Sr.
Prof.
EIT
RPR
Drafter
Clerical
Total
Total
in
Mgr.
Prof.
Engr
or
CADD
Hours
Extension
Charge
Engr,
Technician
($)
<«««««< Rates »»»rr»»
$162.00
$137,00
$122.00
$105.00
$88.00
$78.00
$71.00
$63.00
Inspections and Tests:
10
Coordination with Geotech, Review test
16
16
86
$9,080
reports. etc.
Applications for Payment:
Estimate seven (7) progress payment
applications, one (1) substantial completion
payment application, and one (f) final pay
11
application for a total of nine (9) payment
5•
18
90
$9,270
applications.
Estimate 6 hours per payment application
for RPR and 2 hours per payment
application for PM.
Contractor's Completion Documents:
12
Receive and review documents, transmit to
2
16
34
$3,372
Owner.
Substantial Completion:
Includes Site Visit with Owner, Preparation
13
of Punch List Items, Verification that Project
4
$2,856
is Complete, and Preparation of a Certificate
of Substantial Completion.
Final Notice of Acceptability of the Work:
14
Includes Site Visit with Owner and
4
6
2
20
$2.436
Preparation of Acceptance Documents.
Full Time RPR:
Construction Period 7 months.
Average of 21 working days/month,
1
Full Time Average of 10 hourslday.
20
$11&260
7 months'21 wkng days/mo.'10 hrs/day =
1470 hours.
Full Time RPR use 1500 hours.
Part Time RPR:
Necessary only 2 months.
2
Part Time Average = 4 hours/day.
175
175
$13,650
2 months`21 wkng days/mo.'4 hrs/day =
168 hours.
Part Time RPR use 175 hours.
3of10
AMENDMENT NO. i
EXHIBIT A-1
CITY OF LUBBOCK, TEXAS
ENGINEERING SERVICES
Slide Road from 4th Street to Northwest Loop 289 - Project #91103
ESTIMATE OF MAN-HOURS and TASKS - CONSTRUCTION PHASE SERVICES
WORKSHEET 1
Parkhill, Smith & Cooper, Inc 30-Mar-09
Task
Prin.
Proi.
Sr.
Prof.
EIT
RPR
Drafter
Clerical
Total
Total
in
Mgr
Prot.
Engr
or
CADD
Hours
Extension
Charge
Engr,
Techntcjan
1$)
<<<<«««« Rates »»»»»»
$162 00
$137.00
$122.00
$105.00
$88.00
$78.00
S71.00
S63 00
C
PM Construction Period Servlcw
Record Drawings:
116 sheets @ 2 hrs per sheet for CADD
4
16
232
8
260
$19,204
D
DelfveM lea
1 Reproducible Set of Record Drawings
1116 sheets mylar).
1 Print of Record Drawings (116 sheets
Papas)
8
16
32
16
72
$6,056
1 CD of files.
1 Set RPR logs.
1 Owner set of Contractor submittals.
Total Hours
29
275
0
855
20
1675
384
207
3445
Subtotals for Worksheet 1
PSC Basic Services
$4,698
$37.675
$0
$89,775
$1.760
$1313,650
$27,264
$13,041
$304, 633
4 of 10
AMENDMENT NO. 1
EXHIBIT A-1
CITY OF LUBBOCK, TEXAS
ENGINEERING SERVICES
Slide Road from 4th Street to Northwest Loop 289 - Project #91103
ESTIMATE OF MAN-HOURS and TASKS - CONSTRUCTION PHASE SERVICES
WORKSHEET 2
Hugo Reed & Associates, Inc.
30-Mar•09
Task
Principle
Engr. or
Senior
Prof.
EIT
Technician,
Survey
Total
Total
In
Surveying
RPLS or
Engineer
Survey Crew
Crew
Hours
Extension
Charge
PM
Engineer
Mngr.Or.
Sr. CADD
I$}
o<««<c<«< Rates >->»»»»»
$140.00
$127.00
$116.00
$105.00
S87.00
$75.00
$175,00
t?ON5TRUCTtON PHASE SERVICES - EWINEERING:
Pre Construction Conference & Other
1
Appropriate Meetings:
10
20
30
$3,59G
Estimate Attendance for up to 10 meetings,
Visits to Site and Observation of
Construction:
2
Estimate 1 visit per week for 7 months at 2
7
21
28
56
56,2(5
hours/visit:
7 mo.'4 wks/mo.'t visittwk'2 hrs./visit = 56
hrs.
Coordination. Correspondence, and
Responses to Questions from Contractor,
3
City of Lubbock, RPR, and Public:
10
30
80
120
$13,150
7 month duration, Estimate 4 hrs/week:
7 mo'4 wks/mo.'4 hrs/wk = 112 hrs (use
120 hrs).
Clanhcations and Interpretations; Field
4
Orders.
2
6
12
20
$2,210
Estimate 5 field orders at 4 hrs/fiold order.
Change Orders and Work Change
5
Directives:
2
6
12
?n
52n
Estimate 5 Change Orders at 4 hrs/change
order.
8
Shop Drawings and Samples
5
5
$525
Estimate 5 Submittals at 1 hr/submittal.
7
Modifications to Plan Sheets,
8
16
16
40
$3,806
GflNOTAUCTION PHASE SURVEYING.
0
$o
Su veying as needed to verily contractor
24
24
$4,200
survey data.
Flail Construction Period Services
0
$0
Record Drawings:
2
4
a
20
34
$31058
10 sheets ® 2 hrs per sheet for CADD.
IVWSWOS
1 Reproducible Set of Record Drawings (10
Sheets mylar),
2
2
4
$764
1 Print of Record Drawings (10 sheets
paper). 1 CD of files.
Total Hours
0
35
95
163
0
40
24
357
$39,780
Subtotals for Worksheet 2
HRA Basic Services
$
$ 4,445
$ 11,020
$ 17,115
$ -
$ 3,000
$ 4,200
$39,780
5 of 10
AMENDMENT NO. 1
EXHIBIT A-1
CITY OF LUBBOCK, TEXAS
ENGINEERING SERVICES
Slide Road from 4th Street to Northwest Loop 289 - Project #91103
ESTIMATE OF MAN-HOURS and TASKS - CONSTRUCTION PHASE SERVICES
WORKSHEET 3
Yvonne Newman Engineering, Inc.
30-Mar-09
Task
Principle
Proj.
Sr.
Prof.
EIT
Tech.
Drafter
Total
Total
In
Manager
Prof.
Engineer
or
CADD
Hours
Exlensior
Charge
Engine ra
Designer
f51
<<<«<<««< Rates
$140.00
$127.00
$116.00
$105.00
$87.00
$75.00
$39.00
A
CONSTRUCTION PHASE SERVICES- ENIGINEERINGII
Coordination. Correspondence, and
Responses to Questions from PSG,
1
Contractor, City of Lubbock, and RPR:
120
7 month duration, Estimate 4 hrs/week:
7 mo"4 wkslmo.•4 hrslwk = 112 hrs (use
120 hrs),
Clarifications and Interpretations; Field
2
Orders
12
S1,4
Estimate 3 field orders at 4 hrs/field order.
3
Shop Drawings and Samples
10
$1,160
Estimate 5 Submittals at 2 hdsubmittal.
4
Modifications to Plan Sheets.
S
12
$1,160
S
Post Construction Period Services
Record Drawings:
^^
$3,352
40 sheets ® 2 hrs per sheet for CADD.
C
Di0vambi its
1 Reproducible Set of Record Drawings (40
sheets mylar).
1 Print of Record Drawings (40 sheets
1
9
$612
paper)
1 CD of files.
Total Hours
10
0
139
0
16
7
80
245
$22,036
Subtotals for Worksheet 3
YNE Basic Services
$ 1,400
$
$ 16,124
$ -
$ 1,392
$
$ 3,120
$22,036
6of10
AMENDMENT NO. 1
EXHIBIT A-1
CITY OF LUBBOCK, TEXAS
ENGINEERING SERVICES
Slide Road from 4th Street to Northwest Loop 289 - Project # 91103
ESTIMATE OF REIMBURSABLE EXPENSES - CONSTRUCTION PHASE SERVICES
WORKSHEET 4
PARKHILL, SMITH & COOPER, INC.
30-Mar-09
Reimbursable Expenses
Oty.
Unit
Unit Price
Unit Extension
Mileage (Engineer)
84 trips at 30 mile/trip = 2520 miles
2520
Miles
@
$0.505
per mile
$1,273
Mileage (Full Time RPR)
147 trips at 60 mile/trip = 8,820 miles
8820
Miles
@
$0.505
per mile
$4,454
Mileage (Part Time RPR)
42 trips at 60 mile/trip = 2,520 miles
2520
Miles
@
$0.505
per mile
$1,273
Reproduction
11 x17 Copies (Paper, includes checking prints)
1000
Sheets
@
$0.20
per copy
$200
11x17 Copies (Mylar)
116
Sheets
®
$2.00
per copy
$232
8.5x11 Copies
500
Sheets
@
$0.10
per sheet
$60
Miscelaneous
Postage, shipping and delivery, misc.
25
Mailings
@
$10.00
per mailing
$260
Long Distance Telephone
1
Project
@
$500.00
per project
$500
Cellular phone
1-1/2 phones at 7 months
11
months
(9
$150.00
per month
$1,575
CADD charges
384
Hours
@
$10.00
per hour
$3,840
Subtotals for Worksheet 4
PSG Reimbursables $13,646
w' Contract multiplier for reimbursables = 1.15 $15,693
Total PSC Expenses $15,693
7 of 10
AMENDMENT NO. 1
EXHIBIT A-1
CITY OF LUBBOCK, TEXAS
ENGINEERING SERVICES
Slide Road from dth Street to Northwest Loop 289 - Project # 91103
ESTIMATE OF REIMBURSABLE EXPENSES - CONSTRUCTION PHASE SERVICES
WORKSHEET 5
Hugo Reed & Associates, Inc.
30-Mar-09
Reimbursable Expenses
oty.
Unit
Unit Price
Extension
Survey Equipment - Trimble 5800, Trimble 5603
2
Days
$200.00
$400
Mileage
250
Miles
d
$0.51
$126
Subtotals for Worksheet 5
Hugo Reed & Associates, Inc. Reimbursables $526
w/ Contract multiplier for reimbursables = 1.15 $605
Total Hugo Reed & Associates, Inc. Expenses $605
8 of 10
AMENDMENT NO. 1
EXHIBIT A-1
CITY OF LUBBOCK, TEXAS
ENGINEERING SERVICES
Slide Road from 4th Street to Northwest Loop 289 - Project # 91103
ESTIMATE OF REIMBURSABLE EXPENSES - CONSTRUCTION PHASE SERVICES
WORKSHEET 6
Yvonne Newman Engineering, Inc.
30-Mar-09
Reimbursable Expenses
aty.
Unit
Unit Price
Unit Extension
Travel
Airfare
1
Each
a
$275.00
round trip
$275
Car Rental
1
Days
@
$90.00
per day
$90
Fuel 8 - trips @ 40 miles/trip, 15 mpg
5
Gallons
@
$3.40
per gallon
$17
Parking
1
Days
@
$5,DO
per day
$5
Mileage
0
Miles
@
$0.505
per mile
$0
Meals
3
Each
@
$20.00
per meal
$60
Overnight Stay 1 night, 2 each
1
Nights
@
$100.00
per night
$100
Reproduction
11 x1 7 Copies (Paper, includes checking prints)
80
Sheets
@
S0.20
per copy
$16
11 x1 7 Copies (Mylar)
40
Sheets
@
$2.00
per sheet
S80
8.5xl 1 Copies
120
Sheets
@
$0.10
per copy
$12
Miscellaneous
Postage, shipping and delivery, misc.
15
Mailings
@
$10.00
per mailing
$150
Overnight
5
Overnight
@
$40.00
per mailing
$200
Long Distance Telephone
0
Project
@
$500.00
per project
$0
Cellular phone
50 minutes/mo @ 0.45/min
0
Minutes
@
$0.45
per Minute
$0
CADD charges
0
Hours
@
$10.00
per hour
$0
Subtotals for Worksheet 6
YNE Reimbursables $1,005
w/ Contract multiplier for reimbursables = 1.15 $1,156
Total YNE Expenses $1,156
9of10
AMENDMENT NO. 1
EXHIBIT A-1
CITY OF LUBBOCK, TEXAS
ENGINEERING SERVICES
Slide Road from 4th Street to Northwest Loop 289 - Project # 91103
ESTIMATE OF REIMBURSABLE EXPENSES - CONSTRUCTION PHASE SERVICES
WORKSHEET 7
Terra Engineers, Inc.
30-Mar-09
No.
Subconsultant Expenses Qty Unit Unit Price I Total
1.
Quantities herein are to establish a budget allowance for testing materials as spot checks on the Contractor's work and Contractor's testing agency. Actual
testing quantity subject to Contractor's operations and materials furnished. Testing may vary from these quantities and budgeted amounts, however the
budgeted amount shall not be exceeded unless authorized by City Council. Should the budgeted amount be met without additional monies being approved
by City Council for nacessary spot check testing, then testing will be suspended. Testing by the Engineer is for spot check testing only of the Contractor's
work and of the Contractor's testing agency. The bulk of the materials testing will be by the Contractor's testing agency.
2
Technician time (Regular Rate)
40
hours
$45.00
$1,800.00
2ti/wk average
3
Mileage
840
miles
$0.45
$378.00
1 tripslwk at 30ml/trip
CONCRETE
4
Testing concrete cylinders 1 test13000 SY avg (slip form machine)
10
each
$100.00
$1,000.00
5
Testing concrete cylinders 1 test/pour avg (intersections)
3
each
$100,00
$300.00
6
Slump
15
each
$15.00
$225.00
7
Air
15
each
$45,00
$675.00
8
Deleterious materials
2
each
$45.00
$90.00
9
Inside city limits trip charges
5
each
$20.00
$100.00
10
Core drilling
each
$75.00
11
Core preparation
each
$45.00
12
Capping and testing cores
each
$10.00
13
Patching
each
$50.00
14
Coring machine rental charges
each
$100.00
SOILS
12
Mechanical analysis with hydrometer
each
$250.00
13
Standard Proctor density
each
$100.00
14
Field soil density test (nuclear) - a set of 3 per trip
20
each
$75.00
$1,500.00
15
Field soil density test (sand cone)
1
each
$100,00
$100.00
16
Atterberg Limits
2
each
$45.00
$90.00
17
Shrinkage tests
2
each
$75.00
$150.00
18
Wet ball mill tests
2
each
$175.00
$350.00
19
Classification
2
each
$8.00
$16.00
20
Compressive strength of molded sample
2
each
$35.00
$70.00
ASPHALT
21
Marshall Stability & Flow
each
$225.00
22
Maximum Theoretical Sprcific Gravity
each
$125.00
23
Asphalt extraction with gradation
each
$250.00
24
Bulk Specific Gravity
each
$150.00
25
Percent Air Voids
each
$50.00
26
Marshall tests series
each
$225.00
27
Coring drilling for Thickness of asphalt
each
$75.00
28
Core preparation
each
$45.00
29
Patching
each
$50.00
30
Coring machine rental charges
each
$100,00
31
Insurance carrier surcharge for subrogation requirements
each
$500.00
Subtotal Construction Material Testing Services -Terra Engineers
S6,844.00
UNIT PRICE ---- Valid for Calendar Years 2008, 2009 & 2010 with an escalation rate of 3% per year over the three year contract.
1. Minimum call -out charge for technician and equipment or sample pickup is 2 hours. Charges are accreued portatl to portal.
2. Overtime rates of 1.5 times the regular overly rates are applicable to Bme worked in excess of 8 hours per day, Monday through Friday,
hours worked before 8:00 am and after 5:00 pm; and all hour worked on Saturdays, Sundays and holidays.
3. Call for any tests that not listed above.
10of10
Resolution No. 2009-R0148a
AMENDMENT NO. 1 TO AGREEMENT
EXHIBIT B-1
BASIC CONSTRUCTION PERIOD SERVICES SCHEDULE
Resolution No. 2009-R0148a
EXHIBIT B-I
TO
AMENDMENT NO. 1
TO AGREEMENT
CITY OF LUBBOCK, TEXAS
AND
PARKHILL, SMITH & COOPER, INC.
FOR ENGINEERING SERVICES
(CONSTRUCTION PERIOD SERVICES)
Owner: City of Lubbock, Texas
Project #91 103: Slide Road from 4"' Street to Loop 289
2009
?OIU
Description
Alir
May
June
July
Aug
Sep
Oct
Nov
Dec
Jan
Feb
Mar
Notice to Proceed (estimated)
•
Construction Period Services
Record Drawings
Extension of Basic Services agreement purpose is to provide construction period services and the
schedule is dependent on the contractor's construction progress on Slide Road.