HomeMy WebLinkAboutResolution - 091478S - Street Improvements - Kerr Construction Co - 19Th St. - 09_14_1978RESOLUTION
�l
RESOLUTION ACCEPTING IMPROVEMENTS ON A PORTION OF STREETS AND/OR AVENUES
AS LISTED BELOW:
WHEREAS, the City of Lubbock passed a resolution authorizing the construction
of street improvements by Kerr Construction Company, F. R. S. 4068, on a
portion of the following street:
Compress Ave. from East 19th St. to 900.00 feet North of East 19th St.
known and designated as sub unit number 3 of unit number 1921.
WHEREAS, the improvements upon the said portion of the abovementioned street
has been inspected and found to have been constructed according to the
approved plans and specifications.
THEREFORE, BE IT RESOLVED BY THE CITY OF LUBBOCK, TEXAS
I.
That the improvements on said portion of the abovementioned street be, and
the same are hereby accepted and the City Engineer be and he is hereby
authorized to direct the payment of the City's share and release escrow money.
II.
This resolution shall take effect and be in force after its passage.
PASSED AND APPROVED THIS 14th DAY OF SEPTEMBER, 1978.
irk West, Mayor
ATTEST:
Evelyn Ga fga., City S cr t y
APPROVED:
W' or D. Watson, City Engineer
APPRO D:
c �
J Ross, City Attorney
CONSOLIDATED FINAL ESTIMATE
COMPRESS AVENUE F.R.S. 4068
Accepted September 14, 1978
QUANTITIES
S. Y.
Paving
S. Y.
L. F.
Unit And
6" ',
L. F. Drainage
48"
Sub -Unit Location
Base
C & G Slab
R.C.P.
1921-3 Compress Ave. from North
4,853.91
1,672.60 102.91
100.00
i4* edge of E. 19th St.
to 900.00' North of E. 19 St.
COST ESTIMATE
4,853.91 S.Y. Paving 6" Base
1,672.60 L. F. Curb & Gutter
102.91 S.Y. Drainage Slab
100.00 L.F. 48" R.C.P.
@ $ 4.95 $24,026.85
@ $ 4.65 7,777.59
@ $ 21.50 2,212.57
@ $ 48.60 4,860.00
CONTRACT COST $38,877.01
COST DISTRIBUTION
Unit And Contract Property City
Sub -Unit Cost Owner Cost Cost
1921-3 $38,877.01 -0- $38,877.01