HomeMy WebLinkAboutResolution - 042778E - Water_Sewer Improvements- Holloway Co- Lots 1-121 & Tract A, Sandelwood Addition - 04_27_1978I?rQOT TTTT()TT
Resolution accepting water and sewer system improvements for Lots 1-221
and Tract "A", Sandlewood Addition.
WHEREAS, the developer of Lots 1-221 and Tract "A" Sandlewood Addition
have complied with the provisions of the City of Lubbock Code, Chapter 34, Article 2
by providing the water and sewer improvements for said addition in accordance with
paragraph 61 of said Chapter 34, and,
WHEREAS, the total utility cost to the developer is $135,022.01 with the
improvements constructed by Holloway Contracting Company having a value of
$125,402.58 as determined by the unit prices established by said Chapter 34, and
$9,619.43 cash paid to the City, with Stagecoach Investments, Inc., the developers,
to receive a refund of $15,811.93 in accordance with Chapter 34 of the Code of the
City of Lubbock, and,
WHEREAS, the construction of the said water and sewer improvements was
performed under the supervision of the City Engineer and said improvements have
been completed in accordance with the City of Lubbock's plans and specifications,
NOW THEREFORE BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF LUBBOCK:
1. That the improvements be and the same are hereby accepted as
an integral part of the water and sewage system of the City
of Lubbock.
2. That refund of the refundable cost in the amount of $15,811.93
be made in accordance with said Chapter 34.
3. This resolution shall take effect and be in force from and after
its passage.
PASSED AND APPROVED THIS 27th DAY OF April , 1978.
00'-
Dirk West. Mavor
"Attested:
Treva Phillips, C Secretary
Approved:
c
Watson, City Engineer
Approved:
Fred 0. Senter, Jr., City