March 23, 2006
Item No. 5.27
RESOLUTION
BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF LUBBOCK:
THAT the Mayor of the City of Lubbock BE and is hereby authorized and
directed to execute for and on behalf of the City of Lubbock, a Change Order #5 to the
Contract for Milwaukee Avenue Paving Improvements, 92nd to 341h Street, ITB #05-029-
VK, by and between the City of Lubbock and Granite Construction, and related
documents. Said Change Order is attached hereto and incorporated in this resolution as if
fully set forth herein and shall be included in the minutes of the City Council.
Passed by the City Council this
23rd day of March , 2006.
TOM MARTIN, MAYOR PRO TEM
ATTEST:
Rebecca Garza, City Secretary
APPROVED AS TO CONTENT:
D. Heyfel, City Engineer
APPROVED AS TO FORM:
M.
City Attorney
gs/ccdocs/Res-Ch Orde5-Milwaukee Ave Pav Imp
3.14..06
Resolution No. 2006-RO148
i
-, March 23, 2006
CITY OF LUBBOCK CHANGE ORDER Item No. 5.27
Change Order #: j 5 Contractor: Granite Construction
Date: 3/15/06 BID/ITB #: 05-029-VK
Contract #: 9035590405 Project Name: Milwaukee Avenue Paving Impf6vements -
92nd to 34th Street
Change Order within the scope of the contract means a Change Order that DOES NOT ALTER THE NATURE OF THE THING
TO BE CONSTRUCTED AND THAT IS AN INTEGRAL PART OF THE PROJECT OBJECTIVE. After performance of a
construction contract begins, Change Orders may be approved if necessary to 1) make changes in plans or specifications; or 2)
decrease or increase the quantity of work to be performed or materials, equipment, or supplies to be furnished. This DOES NOT
mean that a department can redefine the project. All work that alters the nature of the thing to be constructed or that is not an
integral part of the project objective must be let out for public bid by the Purchasing_Department. Description of change
(alteration, deviation, addition, or deletion) caused by conditions encountered during construction not covered by the
specifications,and drawipgs of the ro'ect (attach additional a es if necessary):
Change the contract to add concrete paving and 20" waterline from 92nd Street to 90 Street along Milwaukee
and extend the costruction completion date to June 1, 2006.
Change Orders must either be negotiated in the best interest of the City of Lubbock or put out for public bid by the Purchasing
Department. Where the Change Order is negotiated, the Change Order must be fully documented and itemized as to costs,
including material quantities, material costs, taxes, insurance, employee benefits, other related costs, profit and overhead. Where
certain unit prices are contained in the initial contract, no deviations are allowed in computing negotiated change order costs.
ITEMIZED COSTS MUST BE FULLY DOCUMENTED AND ATTACHED TO THIS FORM.
ITEM DESCRIPTION AMOUNT
A. ORIGINAL CONTRACT VALUE: $17,316,932.50
B. AMOUNT OF THIS CHANGE ORDER: Council approval required if over $25, 000 OWNS,
,�C. PERCENT OF CONTRACT VALUE THIS CHANGE ORDER (B/A):
D. AMOUNT OF PREVIOUS CHANGE ORDERS: $424,995.33
E. TOTAL AMOUNT OF ALL CHANGE ORDERS (B+D): $917,731.18
F. PERCENT OF CONTRACT OF ALL CHANGE ORDERS (E/A): 25%Maximum a� 3.
.� IV
G. NEW CONTRACT AMOUNT (A+E): $18,234,663.68
It is mutually agreed that the above dollar amount and the time extension, as applicable, as set forth in this Change Order constitutes
full compensation to the Contractor for all costs, expenses and damages to the Contractor, whether direct, consequential or otherwise,
in anyway incident to, or arising out of or resulting directly or indirectly; from the work performed or modified by the Contractor
under this Change Order.
Purchashig and Contract Man rent Department):
(I) CONTRACTOR ate
Date
fo Content: (/ Approved as to Form:
P A ace ATT RNEY
AL PROJECTS MANAGER Date (6) PURCHASING AN CONTRACT MANAGER Date
Change Orders over $25,000 require a Contract Cover Sheet and the following signatures:
c�FLUBBOCK _ 3/23/06A T efl•�t�� ��— 3/23/06
(7) _ Date (8) CITY 9ECRETARY Date
Council Date: March 23, 2006 Agenda Item #: 5.27 Resolution #:
PUR-045 (Rev 02/06)
ITEM DESCRIPTION
QUANT UNIT
CHANGE ORDER
TOTAL
UNIT PRICE
PREP ROW
6.04
STA
$500.00
$3,020.00
20" C-905 WTR LINE
604
LF
$66.00
$39,864.00
20" BTRFLY VAL / VALT
1
EA
$5,500.00
$5,500.00
TRENCH PROT
604
LF
$5.00
$3,020.00
EXCAVATION
6000
CY
$2.50
$15,000.00
SUBGRD PREP
6590
SY
$1.50
$9,885.00
CONC PAVING
5983
SY
$41.50
$248,294.50
CONC CURB & GUTTER
1071
LF
$8.00
$8,568.00
CONC SIDEWALK
46
SY
$35.00
$1,610.00
SIDEWALK RAMP
4
EA
$1,800.00
$7,200.00
CONC DRVWY & ALLEY
164
SY
$90.00
$14,760.00
PVY MRK 4"W
604
LF
$1.00
$604.00
PVY MRK 24"W
20
LF
$6.00
$120.00
PVY MRK 4"Y
1510
LF
$1.00
$1,510.00
RFLCT PV MRK TYI-C
60
EA
$4.00
$240.00
RFLCT PV MRK TYII-A-A
30
EA
$4.00
$120.00
SMALL SIGN ASSEM
1
EA
$60.00
$60.00
SEEDING
1250
EA
$1.50
$1,875.00
TRAFFIC CONTROL
2
MO
$1,100.00
$2,200.00
EROSION CONTROL
1
LOT
$2,000.00
$2,000.00
MOBILIZATION
1
EA
$127,285.35
$127,285.35
Total $492,735.85
GiRRnITr:
co1151 Humon
compnny 1N22
P.O. Box 3130
Lubbock, TX 79452
(806) 748-9170
FAX (806) 748-9468
Resolution No. 2006-RO148
March 23, 2006
Item No. 5.27
MEMO
TO: Larry Hertel C
FROM: Gary Dawson
SUBJECT: Milwaukee A15 teving Improvements - Extension to 94th Street
DATE: March 16, 2006 PSC Job No: 01-2872-05
Lary,
When Mike Oliver delivered the proposed costs for extending the Milwaukee Ave. paving limits to 94th
Street, he gave some explanation about the prices. The unit prices are identical to the original bid items
except for 20" C-905 Water Line, Traffic Control, Erosion Control, and Mobilization.
The Unit price for C-905 Water line was increased from $55.00/LF to $66.00/I.F to reflect an $1 l .00/LF
increase in pipe material cost.
Traffic Control was reduced from $12,500/1vIonth to $1,100lMonth due to the limited traffic control
required for this portion of work.
The original bid for Erosion Control was lump sum for the entire job. The original bid for the entire job
was $150,000. The proposed cost for this change order is $2,000,
Mobilization was also in the original bid as lump sum for the entire job. The original bid price for
mobilization was $1,730,000 for the job, but a direct comparison cannot be made to the original bid item.
Granite's proposal for this change order has $127,285.35 labeled as mobilization. Mike Oliver explained
that this line item is not based on mobilization costs alone, but has three costs combined together.
1. The striping subcontractor will have to remobilize from the Dallas area to do the striping for this
section. The cost for striping mobilization is included in this number.
2. There is reduced efficiency in preparing and paving the 604-foot section. Mike Oliver offered the
example that the concrete paving for this section will require one day for each "pass" and there
will be four passes. However, the total area of concrete in this section is normally placed in one
day where the roadway length will allow. The construction cost due to lower production rates is
included in this number.
3. The largest component of this number is overhead; the cost of necessary items that are not
directly related to the utility line and paving. Included in this would be things such as salaries for
supervisors and bookkeepers, oil and lube trucks and drivers, mechanics, field offices and phone
lines for contractor and RPR, etc. Mike Oliver said that they made a big effort to minimize this
cost by sharing resources with other Granite construction projects in town, but it accounts for
approximately $100,000 of the proposed mobilization item.
Please call me if you have any questions.
R 11n.)eCtN3i1i1?Ri?RKlV1t..Ylgnre ckdenlL'sarr�e Ordef 45 eKPUratrreaf A10.LXX