HomeMy WebLinkAboutResolution - 020978L - Accept Paving Improvements - CCC Co - GWO 10,922 - 02_09_1978r RESOLUTION
RESOLUTION ACCEPTING IMPROVEMENTS ON PORTIONS OF ALLEYS, STREETS, AND
AVENUES AS LISTED BELOW AND ORDERING THE ISSUANCE OF CERTIFICATES IN EVIDENCE OF
ASSESSMENTS LEVIED.
WHEREAS, the City of Lubbock heretofore passed various street improvement
ordinances and resolutions and entered into contract with Commercial Concrete
Construction Company (G.W.O. 10,922) for the making and construction of street
and alley improvements on portions of numerous alleys, streets and avenues in said
City including among others the following:
East-West Alley between 14th Street and 15th Street from the
West property line of Quaker Avenue to the East properth line
of Raleigh Avenue known and designated as Sub -Unit Number 12
of Unit Number A-460.
North -South Alley between Avenue "d" and Avenue "K" from the
South property line of 6th Street to the North property line
of 7th Street known and designated as Sub -Unit Number 27 of
Unit Number A-460.
Englewood Avenue from its intersection with a line 13.00
feet South of the South property line of 46th Street to
its intersection with the North lip line of 50th Street
known and designated as Sub --Unit Number 83 of Unit Number
2229.
48th Street from its intersection with a line 15.00 feet
East of the East property line of Englewood Avenue (North
Side) to its intersection with a line 16.00 feet West of
the West property line of Elkhart Avenue known and designated
as Sub -Unit Number 8 of Unit Number 2233.
AND WHEREAS, the improvements upon the said portions of the abovementione
alleys, streets and avenues, have been inspected and found to have been constructed
in accordance with terms of said contract (G.W.O. 10,922).
THEREFORE, BE IT RESOLVED BY THE CITY OF LUBBOCK, TEXAS:
I.
That the improvements on said portions of the abovementioned alleys,
streets, and avenues be and the same are hereby accepted, and the City Engineer be
and he is hereby authorized to direct payment of the City's portion of the cost.
II.
That the Mayor and City Secretary be, and they are hereby instructed to
execute and deliver certificates in evidence of the assessments levied against the
parcels of property abutting upon the said portions of the alleys, streets and
avenues listed above and against the owners of such property in accordance with
law and in the manner provided in said contract, and the proceedings with reference
to said improvements and assessments where such assessments were levied.
This resolution shall take effect and be in force from and after its
passage.
PASSED AND APPROVED THIS 9TH DAY OF FEBRUARY, 1978.
v - Roy Bass, Mayor
ATTEST:
Treva.Phill ps, Ci Secretary
APPROVED:
Wilf& d Watson, City Engineer
APPROV :
Fred 0. Senter, Jr., City A rney
r 'r
CONSOLIDATED FINAL ESTIMATE
G.W.O. 10,922
Accepted February 9, 1978
QUANTITIES
S.Y. S.Y. S.Y. S.Y. L.F.
Unit & Alley Paving L.F. Alley Valley C & G
Sub -Unit Location Paving 6" Base C & G Return Gutter Removal
A-460-12 E-W Alley between 14th
Street and 15th Street
from W.P.L. of Quaker
Avenue to E.P.L. of
Raleigh Avenue. 652.00
A-460-27 N-S Alley between
Avenue "J" and Avenue
"K" from S.P.L. of 6th
Street to N.P.L.
of 7'.th Street. 342.00 85.50 34.00
2229-83 Englewood Avenue from
13' S. of S.P.L. of
46th Street to N.L.L.
of 50th Street. 5,264.02 2,520.02 20.20 55.88
2233-8 48th Street from 15'
E. of E.P.L. of
Englewood Avenue to
16' W. of W.P.L. of
Elkhart Avenue. 2,215.40 1,049.40
Toal Quantities 994.00 7,479.42 3,654.92 20.20 55.88 34.00
COST ESTIMATE
7,479.42
S.Y.
Paving 6" Base
@
$ 2.58
$19,296.91
3,654.92
L.F.
Curb & Gutter
@
$ 2.85
$10,416.52
20.20
S.Y.
Alley Return
@
$11.00
$ 222.20
55.88
S.Y.
Valley Gutter
@
$11.00
$ 614.68
34.00
L.F.
C & G Removal
@
$ 1.00
$ 34.00
994.00
S.Y.
Alley Paving
@
$12.25
$12,176.50
CONTRACT COST $42,760.81
COST DISTRIBUTION
Unit &
Contract
Property
City
Sub -Unit
Cost
Owner Cost
Cost
A-460-12
$ 7,987.00
$ 4,659.20
$3,327.80
A-460-27
4,467.18
3,546.40
920.78
2229-83
21,600.11
17,857.88
3,742.23
2233-8
8,706.52
9,820.82
-1,114.30
Total
$42,760.81
$35,884.30
$6,876.51
Total Contract Cost $42,7.60.81
Amount Paid on Monthly Estimates 37,918.37
Amount Due Contractor $ 4,842.44