HomeMy WebLinkAboutResolution - 081276E - Paving Improvements - New Subdivision Unit 67 - Boston Ave. & Regis St. - 08_12_19764 F107(e C
RESOLUTION
WHEREAS, the City Council has heretofore determined that the City would
contribute the customary city portion of the cost of street paving improve-
ments, as determined by City of Lubbock paving policy, to be constructed in
accordance with the standard City of Lubbock street plans and specifications
as approved by the City Engineer, and the -m ers of property abutting Boston
Avenue from the centerline of Regis Street to 13' S. of the S.P. L. of
Newcomb Street, have requested permission to have pavement improvements
constructed on the aforementioned street and the paving of said street is
needed to provide access to the area during its construction period, and the
City Engineer has approved the plans and specifications for such improvements,
and,
WHEREAS, O.A. Webb, Merle Rodgers and David Hester, the owners of the
property abutting on the herein described street will contract separately
with a competent contractor for the above street improvements,. and said
improvements will be constructed in accordance with the abovementioned plans
and -specifications under the supervision of the City Engineer, and the
saiiT _owners desire that the City contribute its customary share towards
such paving, and,
WHEREAS, the contract cost of the paving improvements will not exceed
$20,164.86, the total cost not over $21,374.76, and the City's share in
connection therewith would not exceed $3,239.64, leaving the property owner's
portion not to exceed $18,135.14, such costs being well within the current
prices for paving obtained by competitive bidding, and that such payment to
be made by the City is reasonable, fair and just to the abutting property
owners, the City and all other persons affected thereby, and that the sum of
$3,239.64 will be duly budgeted, THEREFORE,
BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF LUBBOCK:
Section 1. THAT, the City Engineer be and he is hereby authorized to
approve plans and specifications for paving on the street herein described,
provided that such plans and specifications meet the usual requirements for
paving on streets within the corporate limits of the City of Lubbock; said
street being as follows, to -wit:
Boston Avenue from its intersection with the centerline of Regis Street
to 13.00 feet south of the south property line of Newcomb Street, known and
designated as New Subdivision Unit Number 67 of Unit Number 2018.
The City Engineer is further authorized and directed to duly inspect
said paving construction on said street and to require strict compliance
with the approved plans and specifications, and upon completion of said paving
and upon final approval by the City Engineer and acceptance of such improve-
ments by the City Council, the City Engineer is authorized to pay the
contractor in full and final payment of the City's share of the cost of the
abovementioned improvements a sum not to exceed $2,029.74 which is the City's
share ($3,239.64 less $1,209.90 engineering), leaving the amount due the
contractor from the property owners not to exceed $18,135.14.
Section 2. This authority is conditioned that the owners of abutting
property and the contractor will pay for all material and labor and costs
incidental to such construction, indemnify the City of Lubbock against any
costs, claims, or damages of every nature pertaining thereto, and that the
Contractor furnish the City Engineer with acceptable evidence that the con-
tractor and his sub -contractors, if any, are adequately covered by public
liability and property damage insurance, policies, that the said owners of
abutting property will cause such paving to continue to be done according to
the approved plans and specifications, and that upon completion thereof and
final approval of the City Engineer all improvements designated herein shall
be a permanent part of said street and the property of the City of Lubbock,
without any liability whatsoever, except for the payment of a sum of $2,029.74
to the contractor.
On motion of Councilman , seconded by Councilman
, the foregoing resolution was unanimously
passed by the City Council this 12th day of August 1976.
ATTEST:
Treva Phillips, C i�l
Secretary
Roy Bd`ss, Mayor
.Awmwasto
Senter, Jr., City rney
The owners of abutting property on the abovementioned street, and W.D. Turner
Construction Co., Contractor, do here kept and agree to fully abide by th
foregoing provisions for the consiy,67atig6s therein stated.
.`$."Turner Construction Co.
Mr. O.A. Webb (unplatted part)
773,51 S.Y. of Paving @ $2.90 = $2,243.18
435.10 L.F. of C & G @ 3.00 = 1,305.30
= $3 , .548.48 by
O.A. Webb
Mr. O.A. Webb, Lots 1 and 28, Crest Hill Addition �//��
354.00 L.F. of side footage @ $10.16 = $3,596.64 by (/.
O.A. Webb
.*
Mr. Merle Rodgers, Lot 29, Crest Hill Addition
177.27 L.F. of side footage @ $10.16 = $1,801.06 by
Merle Rodgers
David Hester, Lots 1 thru 56 Colonia Addition.
1,015.11 S.Y. of Paving @ $2.90 = $2,943.82 .�
523.00 L.F. of C & G-: @ 3.00 = 1,569..00
$4,512.82 by
avid Hester?
David Hester (Part of Tract "B" Hillcrest)
1,019.32 S.Y. of Paving @ $2.90 = $2,956.03
573.37 L.F. of C & G : @ 3.00 = 1,720.11
$4,676.14 by
David Hester