HomeMy WebLinkAboutResolution - 062377F - Pavement Improvements - Kerr Construction Co - Horizon West Addition - 06_23_1977RESOLUTION
RESOLUTION ACCEPTING IMPROVEMENTS ON A PORTION OF STREETS AND AVENUES AS
LISTED BELOW:
WHEREAS, in conformance with the paving requirement provisions of City
Ordinance 1331, the subdivider of Horizon West Addition, Lots 1-113, made arrange-
ments with Kerr Construction Company for the construction of paving improvements
on certain streets dedicated in said subdivision under the provisions of said Ordi-
nance prior to the recording of the subdivision plat of Horizon West Addition, Lots
1-113 including the following streets:
West 1/2 of North Dover Avenue from its intersection with the South
\ Raw Edge of Erskine Street to its intersection with a line 7.00
feet South of the South Property Line of Alley South of Emory Street
known and designated as New Subdivision Sub -Unit Number 100 of Unit
Number 2019.
Emory Street from its intersection with the East Raw Edge of Frankford
Avenue to its intersection with the West Lip Line of North Englewood
Avenue known and designated as New Subdivision Sub -Unit Number 0 of
Unit Number 2020.
Emory Street from its intersection with the East Lip Line of North
Englewood Avenue to its intersection with the West Lip Line of
North Dover Avenue known and designated as New Subdivision Sub -Unit
Number 1 of Unit Number 2020.
North Englewood Avenue from its intersection with the South Raw
Edge of Erskine Street to its intersection with a line 7.00 feet
South of the South Property Line of the alley South of Emory Street
known and designated as New Subdivision Sub=Unit Number 2 of Unit
Number 2020.
North Elmwood Avenue from its intersection with the South Lip Line
of Erskine Street to its intersection with the North Lip Line of
Emory Street known and designated as New Subdivision Sub -Unit Number
3 of Unit Number 2020.
North Elkhart Avenue from its intersection with the South Lip Line
of Erskine Street to its intersection with the North Lip Line of
Emory Street known and designated as New Subdivision Sub -Unit Number
4 of Unit Number 2020.
North Durham Avenue from its intersection with the South Lip Line
of Erskine Street to its intersection with the North Lip Line of
Emory Street known and designated as New Subdivision Sub -Unit Number
5 of 'Unit Number 2020.
South 1/2 of Erskine Street from its intersection with a line 7.00
feet West of the West Property Line of Alley West of North Englewood
Avenue to its intersection with the centerline of North Dover Avenue
known and designated as New Subdivision Sub -Unit Number 12 of Unit
Number 2020.
AND WHEREAS, the construction of the above improvements on the above
mentioned streets was performed under the supervisionof the City Engineer, and
said improvements have been completed and have been inspected and found to have
been constructed in accordance with City specifications and in accordance with the
provisions of City Ordinance 1331.
THEREFORE, BE IT RESOLVED BY THE CITY OF LUBBOCK, TEXAS.
I.
That the improvements on said portions of the abovementioned streets be
and the same are hereby accepted and the City Engineer be and he is hereby author-
ized to direct the payment of the City's portion of the cost.
II.
This resolution shall take effect and be in force from and after its
passage.
PASSED AND APPROVED THIS 23RD DAY OF-JUNE, 1977.
:'...y Roy Bass, Mayor
AT�,ESTe
revs Phillips, Ci Secretary
APPROVED:
Wilf d . Watson, City Engineer
APPROV D:
wd:0. Senter, Jr., C- Attorney
CONSOLIDATED FINAL ESTIMATE
HORIZON WEST ADDITION, LOT 1-113
Accepted June 23, 1977
QUANTITIES
S.Y.
S.Y.
S.Y.
Unit &
Paving
L.F. Alley
Valley
Sub -Unit
Location
6" Base
C & G Return
Gutter
NS 2019-100
West 1/2 of North Dover
Avenue from the South Raw
Edge of Erskine Street to
7.00 feet South of the
S.P.L. of the alley South
of Emory Street.
1,715.99
639.76 20.20
28.49
NS 2020-0
Emory Street from the
East Raw Edge of Frank -
ford Avenue to the West
Lip Line of N. Engle-
wood Avenue.
3,316.71
1,626.49
34.76
NS 2020-1 Emory Street from the
East Lip Line of N.
Englewood Avenue to the
West Lip Line of N.
Dover Avenue.
NS 2020-2 N. Englewood Avenue from
the South Raw .Edge of
Erskine Street to 7.00
feet South of the S.P.L.
of the alley South of
Emory Street.
NS 2020-3 N. Elmwood Avenue from
the South Lip Line of
Erskine Street to the
North Lip Line of Emory
Street.
NS 2024-4 N. Elkhart Avenue from
the South Lip Line of
Erskine Street to the
North Lip Line of Emory
Street.
4,382.47 2,260.79 20.20
3,230.79 1,461.38 40.40
1,911.80 1,138.36 40.40
1,911.80 1,143.52
87.31
88.10
52.54
52.54
S.Y. S.Y. S.Y.
Unit :& Paving L.F. Alley Valley
Sub -Unit Location 6" Base C & G Return Gutter
NS 2020-5 N. Durham Avenue from the
South Lip Line of Erskine
Street to the North Lip
Line of Emory Street. 1,911.80 1,138.36
NS 2020-12 South 1/2 of Erskine
Street from 7.00 feet
West of the W.P.L. of
the alley West of N.
Englewood Avenue to the
centerline of N. Dover
Avenue. 1,278.22
TOTAL QUANTITIES 18,381.36 10,686.88
40.40
52.54
273.71 396.28
CONSOLIDATED FINAL ESTIMATE
HORIZON WEST ADDITION, LOT 1-113
Accepted June 23, 1977
COST DISTRIBUTION
Unit &
Contract
Developer
Sub -Unit
Cost
Cost
NS 2019-100
6,968.55
6,968.55
NS 2020-0
14,093.54
14,093.54
NS 2020-1
19,185.58
19,185.58
NS 2020-2
13,881.26
13,881.26
NS 2020-3
9,138.78
9,138.78
NS 2020-4
8,718.57
8,718.57
NS 2020-5
9,138.78
9,138.78
NS 2020-12
4,694.72
4,694.72
TOTAL
85,819.78
85,819.78
COST ESTIMATE
18,381.36 S.Y. Paving 6" Base
10,686.88 L.F. Curb & Gutter
273.71 S.Y. Alley Return
396.28 S.Y. Valley Gutter
@ $ 2.90 $53,305.94
@ $ 2.73 $29,175.18
@ $10.75 $ 2,942.38
@ $ 1.00 $ 396.28
CONTRACT COST $85,819.78