RESOLUTION
BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF LUBBOCK:
THAT the MAYOR of the CITY OF LUBBOCK, BE and is hereby
authorized and directed to execute for and on behalf of the CITY OF
LUBBOCK, CHANGE ORDER #3 to the AGREEMENT between the CITY OF
LUBBOCK and KERR CONSTRUCTION COMPANY at LUBBOCK REGIONAL
AIR TERMINAL, covering extension of time for completion of terminal
parking and roadway construction, attached herewith which shall be spread
upon the Minutes of the COUNCIL and as spread upon the Minutes of this
COUNCIL shall constitute and be a part of this Resolution as if fully copied
herein in detail.
Passed by the City Council this 26th day of February , 1976.
q/U"&SS
ROY IrASS, MAYOR
JATTEST:
Treva Phil ips, ty Secretary -Treasurer
JAPPROVED AS TO FORM:
Fred O. Senter, Jr. amity Attorney
xRib _7
A. ,t
r
CHANGE ORDER NO. 3
Terminal Parking and
Roadway Construction
Lubbock Regional Airport
Lubbock, Texas
ADAP Project No. 8-48-0138-02
Contract No. 2
TO: KERR CONSTRUCTION COMPANY
P.O. Box 888
Lubbock, Texas 79408
General description of work ,included in contract: The construction
of approximately 42,000 square yards of flexible pavement on entrance and
service roads to the terminal building, construction of approximately
35,000 square yards of flexible pavement in the terminal parking area,
construction of approximately 6,200 square yards of flexible pavement in
the auto -rental storage areas, construction of approximately 15,000 linear
feet of curb and gutter on the service roads, construction of approximately
3,400 linear feet of curb and gutter in the parking area, construction of
two attendant's buildings in the parking area, construction of area light-
ing on the service roads and in the parking area, installation of parking
control equipment, construction of drainage structures, construction of
concrete slabs, removal of existing pavement, painting of roads and park-
ing areas, and other related items of work.
Original amount of contract. . . . . . . . . .$ 992,464.85
Change Order.No. 1 . . . . . . . . .Deduct j 320.-00]
Change Order No. 2 . . . . . . . . . Add 97,679.10
Change Order No. 3 . . . . . . . . . . . . . None -0-
Adjusted Contract Price . . . . . . . . $1,08% 823.95
Adjustment in Construction Time:
Original Date of Completion September 15, 1975
Change Order No. 1 . . . . . . None _0_ Days
Change Order No. 2 ... . . . . . Add 49 Days
Change Order No. 3. . . . . . . . Add 105 Days
Adjusted Date of Completion . . . February 16, 1916
WHEREAS, during the construction time provided by the contract, the
weather was unseasonal in that more rain occurred than was normal resulting
in the loss of working time due to the rain and wet, unworkable conditions
at the job site;
AND WHEREAS, during the construction time provided by the contract,
other contractors were performing work for the Owner at the job site; the
work of those contractors in certain instances conflicted with the work of
this project resulting in the loss of working time on this project;
CHANGE ORDER 140. 3
Page 1 of 2
AND WHEREAS, during the construction time providee the contract,
a labor strike stopped work by union craftsmen resultis,7 I= the loss of
working time on this project;
AND WHEREAS, during the construction of this project, delays were
encountered in the delivery of luminaires required for the erection of
outside lighting on the project resulting in the loss of working time;
AND WHEREAS, near .completion of the project additional work was
added to the project requiring additional time for delivery and installa-
tion of these added items of work:
THIS AGREEMENT WITNESSETH: In consideration of the mutual advantages
gained, the Owner and Contractor agree that the time allowed for completion
of the project shall be extended 105 days from November 3, 1975, to
February 16, 1976, and further agree that there shall not be an adjustment
to the contract price for the extension of time.
IN WITNESS WHEREOF, the Owner and the Contractor have hereto set their
hands this the day of ,.1976.
RECO)MNDED: PARKHILL, SNITH & COOPER, INC., Consulting Engineers
BY z r f, Q , +, ,-, 1976
APPROVED: KERR CONS RUCTION COMPANY, Contractor
By � � � Z117, 1976
APPROVED: CITY 0 LUBB CK, TEXAS, Owner
By�i1i�,_ MAYOR FBRUARY � 2 6, 19!'6 -
ATTEST:
City . Se,4retary
CHANGE ORDER NO. 3
Page 2 of 2