RESOLUTION
RESOLUTION ACCEPTING IMPROVEMENTS ON PORTIONS OF STREETS AND/OR AVENUES
AS LISTED BELOW:
WHEREAS, in conformance with the paving requirement provisions of City
Ordinance 1331, the subdivider of Quaker Heights Addition Lots 241-354 and
Tract "D", made arrangements with Kerr Construction Company for the construc-
tion of paving improvements on certain streets dedicated in said subdivision
under the provisions of said Ordinance prior to the recording of the sub-
division plat of Quaker Heights Addition Lots 241-354 and Tract "D" including
the following streets:
78th Street from its intersection with a line 12.72 feet East of the East
property line of Richmond Avenue to its intersection with a line 8.50 feet
East of the West property line of Quaker Avenue, known and designated as
New Subdivision Unit Number 2015-87.
79th Street from its intersection with the East Lip Line of Toledo Avenue
to its intersection with a line 8.50 feet East of the West property line of
Quaker Avenue, known and designated as New Subdivision Unit Number 2015-88.
80th Street from its intersection with a line 16.00 feet West of the -West
property line of Toledo Avenue to its intersection with the West raw edge
of Quaker Avenue, known and designated as New Subdivision Unit Number
2015-89.
Part of the West 1/2 of Quaker Avenue
3.00 feet South of the South property
to its intersection with a line 15.00
of 80th Street (concrete only), known
Unit Number 2015-90.
from its intersection with a line
line of the alley south of 77th Stree
feet South of the South property line
and designated as New Subdivision
Quinton Avenue from its intersection with the North Lip Line of 78th Street
to its intersection with a line 3.00 feet South of the South property line
of the alley south of 77th Street and from its intersection with the
North Lip Line of 79th Street to its intersection with the South Lip Line
of 78th Street, known and designated as New Subdivision Unit Number 2015-91
Toledo Avenue from its intersection with the North Lip Line of 80th Street
to its intersection with a line 16.00 feet South of the South property line
of 78th Street, known and designated as New Subdivision Unit Number 2015-92
Richmond Avenue from its intersection with the Northeast Lip Line of 80th
Street to its intersection with the Southwest Lip Line of 79th Street,
known and designated as New Subdivision Unit Number 2015-93.
AND WHEREAS, the construction of the above improvements on the abovemention d
streets was performed under the supervision of the City Engineer, and said im-
provements have been completed and have been inspected and found to have been
constructed in accordance with City specifications and in accordance with the
provisions of City Ordinance 1331.
THEREFORE, BE IT RESOLVED BY THE CITY OF LUBBOCK, TEXAS:
I -
That the improvements on said .portions of the abovementioned streets BE
and the same are hereby accepted and the City Engineer BE and he is hereby au-
thorized to direct the payment of the City's portion of the cost.
II.
This resolution shall take effect and be in force from and after its passage.
PASSED AND APPROVED THIS 24th DAY OF JANUARY, 1974.
MORRIS W. TURNER, MAYOR
ATTEST:
Treva Phillips, City cretary
rAillyrE—D. Watson, Cfty Engineer
PPRD:
i
Fred 0. Senter, Jr., g1ty Attorney
CONSOLIDATED FINAL ESTIMATE
Quaker Heights Addition
Lots 241-354 and Tract D
Accepted January 24, 1974
UANTITIES
S.Y. Alley
S.Y.
S.Y.
Returns &
S.Y.
Unit &
Paving
Paving
L.F.
Drainage
Valley
Sub -Unit
Location
9" Base
6" Base
C & G
Channels
Gutter
NS2015-87.
78th Street from 12.72' East of
5133.48
2663.90
12.00
.the E.P.L. of Richmond Avenue to
8.5' East of the W.P.L. of Quaker
Avenue
NS2015-88
79th Street from the E.L.L. of
6603.20
3524.99
346.24
Toledo Avenue to 8.5' East of the
W.P.L.. of Quaker Avenue
NS201.5-89
80th Street from 16.0' West of
271.25•
8066.67
4037.01
52.54
the W.P.L. of Toledo Avenue to the
West raw edge of Quaker Avenue
Part of
NS2015-90
The West 1/2 of Quaker Avenue from
the 3.0' South of the S.P.L. of the
alley South of 77th Street to 15.0'
South of the S.P.L. of 80th Street
.(concrete only)
Developer's Quantities
542.84
40.40
S.W.P.S. Quantities
146.00
NS2015-91
Quinton Avenue from the N.L.L.
1487.40
846.46
40.40
of 78th Street to 3.0' South of
the S.P.L. of the alley South of
77th Street and from the N.L.L. of
79th Street to the S.L.L. of 78th
Street
NS2015-92 Toledo Avenue from the N.L.L. of 80th 2312.88 1001.38 40.40
Street to 16.0' South of the S.P.L. of
78th Street
NS2015-93 Richmond Avenue from the Northeast Lip 1022.42 579.92 40.'40
Line of 80th Street to the Southwest
Lip Line of 79th Street
Total Developer's Quantities 271.25 24,626.05-13,196.50 519.84 52.54
Total S.W.P.S. Quantities 146.00
COST DISTRIBUTION
-
Property
S.W.P.S.
Unit &
Contract
Owner
Company
Sub -Unit
Cost
Cost
Cost
NS 2015-87
$15,720.09
$15,720.09
NS 2015-88
23,035.87
23,035.87.
NS 2015-89
25,354.64
25,354.64'
NS 2015-90
1,731.28
1,431.98
$299.30
NS 2015-91
4,999.45
4,999.45
NS 2015-92
6,951.49
6,951.49
NS 2015-93
3:532.39
3,532.39
TOTAL
$81,325.21
$81,025.91
$299.30
COST ESTIMATE
24,626.05 S.Y.
Paving 6" Base
@ $1.98
$48,759.58
271.25 S.Y.
Paving 9" Base
@ $2.55
$ 691.69
13,342.50 L.F.
Curb & Gutter
@ $2.05
$27`,352.13
519.84 S.Y.
Alley Return
& Drainage Channel
@ $7.90
$ 4,106.74
52.54 S.Y.
Valley Gutter
@ $7.90
$ 415.07
CONTRACT COST
$81,325.21