HomeMy WebLinkAboutResolution - 122073E - Agreement - URA - Memorial Civic Center - 12_20_1973��. /moo 73 E
RESOLUTION
BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF LUBBOCK:
THAT the Mayor of the City of Lubbock BE and is hereby authorized and
directed to execute for and on behalf of the City of Lubbock an agreement between
the City, of Lubbock and the Urban Renewal Agency of the City of Lubbock covering
the construction of certain water and sewer lines within the Memorial Civic Centel
Complek'Urban Renewal Area, Project No. Tex. R-138(C), attached herewith
which shall be spread upon the minutes of the Council and as spread upon the
minutes, of this Council zhall constitute and be a part of this Resolution as if fully
copied herein in detail.
Passed by the City Council this 20th day of December 1973.
-. ORRIS W. TURNER, MAYOR
TTEST:
, City Secretary -Treasurer
AS TO FORM:
t
CONTRACT
PART I - AGREEMENT
THIS AGREEMENT, entered into as of this 13th day of December ,
1973, by and between the Urban Renewal Agency of the City of Lubbock, State of
Texas (hereinafter referred to as the "Local Public Agency"), and the City of
Lubbock, (hereinafter referred to as the "Contractor").
WITNESSETH:
WHEREAS, the Local Public Agency has heretofore entered into a contract
for Loan and Grant with the United States of America for the Memorial Center
Urban Renewal Project, Number TEX. R-138(C), the same being dated June 16, 1971,
as amended on June 9, 1972, and June 22, 1973, said contract and amendments
thereto providing for financial aid to the Local Public Agency under Title I of
the Housing Act of 1949, as amended; and
WHEREAS, pursuant to such Contract, the Local Public Agency is undertaking
certain activities necessary for the execution of said project, within the
Memorial Center Complex Urban Renewal Area, Project Number TEX. R-138(C), including
certain project site improvements work; and
WHEREAS, the Local Public Agency desires to engage the Contractor to under-
take and carry out the performance of certain project improvements designated
as Item I project improvements in connection with such undertakings of the Local
Public Agency; and
WHEREAS, by waiver dated December 13 , 1973, a copy of which is
attached to this Contract, the Local Public Agency has obtained the approval
of the Secretary of Housing and Urban Development to enter into a contract
with the City of Lubbock to perform certain project improvement work relating
to the construction of water and sewer lines which have been designated as Item
I Project Improvements on an actual cost basis to the extent such project
improvements are eligible to be charged to and paid out of Item I of Gross
Project Costs, and has obtained a waiver of Section 107E of the Loan and Capital
Grant Contract Number TEX. R-138(C) to the extent necessary to permit the Local
Public Agency to enter into such contract with the City of Lubbock.
NOW THEREFORE, the parties hereto do mutually agree as follows:
1. Scope of Services: The Contractor shall perform all the necessary services
provided under this Contract in connection with the Memorial Center Complex
Urban Renewal Area, Project Number TEX. R-138(C), and shall do perform and
carry out in a satisfactory and proper manner, as determined by the Local
Public Agency, the following: Provide the following improvements in the
Project Area, in accordance with the attached specification and schedule,
attached as Exhibit A.
2. Time of Performance: The services of the Contractors are to commence on
the 26th day of December, 1973, and shall be undertaken and completed in
such sequence as to assure their expeditious completion, but in any event
all of the services required hereunder shall be completed within 60 days
from the date hereof.
3. For and in consideration of the services to be perforried by the Contractor,
the Local Public Agency will pay to the Contractor such portion of the
Contractor's actual costs as are eligible to be designated as Item
Project Cost for this Project. Final payment shall be made on the basis
of actual costs incurred by the contractor in the performance of the work
authorized. Estimated cost to be incurred are as follows:
A. Water System $10,706.00
B. Sewer System 13,168.00
$23,874.00
The total compensation to be paid shall be the actual cost of the Contractor
for labor, material, and equipment (rental rate of equipment shown on
Exhibit "B" attached hereto); provided that in no event will the maximum
compensation paid to the Contractor exceed $23,874.00.
4. Method of Payment: Payment will be made upon completion of all work provided
for under this contract, subject to the approval and concurrence of the
Department of Housing and Urban Development of the cost and expenses
claimed by the Contractor.
IN WITNESS WHEREOF, the Local Public Agency and the Contractor have
executed this Agreement as of the date first above written.
ATTEST:
SECRETARY
ATTEST:
URBAN RENEWAL AGENCY OF THE
CITY OF LUBBOCK, TEXAS
BY
CHAIRMAN
THE CITY OF LUBBOCK
MORRIS W. TURNER, MAYOR
t
ity-Secretary - Tre surer, Lavenia Lowe
ity Attorney
ESTIMATE OF COST FOR WATER AND SEWER
TO SERVE LA QUINTA MOTOR INN
UNIT UNIT TOTAL COST
ITEM NO. DESCRIPTION QUANTITY OF
. MEASURE PRICE IN PLACE
A. WATER SYSTEM
1. 6" asbestos cement (AC)
2. 8" asbestos cement (AC)
3. 6" cast iron (CI)
4. Fire hydrant w/6" gate valve
5. 8" valve with 30" tap
6. 6" valve with 6" tap
B. SEWER SYSTEM
1. 6"VC pipe (0'-6' depth)
standard strength
2. 8" VC pipe (0'-6' depth)
standard strength
3. 8" VC pipe (0'-8' depth)
standard strength
4. 8" VC pipe (8'-10' depth)
standard strength
5. Sanitary sewer manhole type A
10' deep
6. Sanitary sewer manhole type B
5' deep
7. Sanitary sewer manhole type B
6'deep
8. Clean outs
1135
L.F.
5.20
5,902.00
163
L.F.
6..50
1,059.50
14
L.F.
7.75—
94.50
2
Ea.
700
1, 0�+ 0.00
1
Ea.
1,2067
1,200.00
3
Ea.
350
1,050.00
412
L.F.
5.00
2,060.00
277
L.F.
6.00
1,662.00
242
L.F.
8.00
1,936.00
526
L.F.
10.00
5,26o.00
1
Ea.
500
500.00
3
Ea.
400
1,200.00
1
Ea.
450
450.00
1
Ea.
100
100.00
$23,874.00
(1) The total estimated cost includes: materials, labor and equipment for construction,
surveying, construction staking and construction supervision.