HomeMy WebLinkAboutResolution - 4359 - CO #1 To Contract-Gilbert Texas Construction Comapany- Runway_Airfield, LIA - 01_13_1994Resolution No. 4359
January 13, 1994
Item #22
RESOLUTION
BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF LUBBOCK:
THAT the Mayor of the City of Lubbock BE and is hereby authorized and directed
to execute for and on behalf of the City of Lubbock Administrative Change Order No. 1 to
a contract previously entered into by and between said City and Gilbert Texas Construction
Company for runway and airfield improvements at the Lubbock International Airport,
attached hereto, which shall be spread upon the minutes of the Council and as spread upon
the minutes of this Council shall constitute and be a part of this Resolution as if fully
copied herein in detail.
Passed by the City Council this 13th
ATTEST:
&Et;- J-�- cy-,-Llr�
Betty M. Johnsonv City Secretary
APPROVED AS TO CONTENT:
J' ewsome, Acting Director of Aviation
APPROVED AS TO FORM:
Harold Willard, Assistant Attorney
HW:da/ccdoca/GII.BERT.ree
December 2, 1993
ADMINISTRATIVE
CHANGE ORDER NO. 1
City of Lubbock, Texas
Lubbock International Airport
Runway 17R-35L Shoulders and
Airfield Signage Improvements
AIP Project No. 3-48-0138-11
August 1992
November 29, 1993
To: Gilbert Texas Construction Co.
800 Paloma Drive, Suite 160
Round Rock, Texas 78764
General description of work included in the original Contract:
Construction of bituminous shoulder pavement on Runway 17R-35L and certain associated
taxiways, construction of airfield signage, lighting vault and emergency generator improvements and other
related items of work.
Original Amount of Contract ................................. $1,815,798.00
Quantity Adjustments ...............................(Deduct) ($ 69,025.38)
Administrative Change Order No. 1 .................(Add) $ 36,305.00
Total Adjusted Contract Amount ..............$1,783,077.62
Original Contract Construction Time ................... 180 Calendar Days
Change Order No. 1....................................... 0 Calendar Days
Total Adjusted Contract Time ........... 180 Calendar Days
WHEREAS, it is desirable to make certain changes in the work included under this project:
1. It is necessary to extend certain existing underground electrical ducts used for Federal
Aviation Administration control, power and communication circuits. This item of work will be
accomplished for the total lump sum price of Thirty -Five Thousand, One Hundred and Seventy -Five
Dollars and No Cents ($35,175.00).
2. It is necessary to provide taxiway intensity control circuits to certain taxiway regulators,
and wiring and mechanical modifications in the Electrical Vault. This item of work will be accomplished
for the total lump sum price of One Thousand, One Hundred, Thirty Dollars and No Cents ($1,130.00).
Administrative Change Order No.
Page 1 of 2
Lubbock International Airport
November 29, 1993
The aforementioned work will be added to scope of the improvements included in the original
Contract, and shall be subject to all original Contract stipulations and covenants, and shall be
accomplished in accordance with the technical specifications in the original Contract. The aforementioned
work will be accomplished for the total lump sum price of Thirty -Six Thousand. Three Hundred and
Five Dollars and No Cents ($36,305.00).
AND WHEREAS, the Owner and the Federal Aviation Administration desires to reconcil the final
constructed quantities to the estimated quantities included in the project Proposal. This results in a total
reduction of Sixty -Nine Thousand. Twenty -Five Dollars and Thirty -Eight Cents ($69 025. in the total
contract amount.
IN WITNESS THEREOF, the Owner and the Contractor have hereto set their hands this 13 th
day of January , 1994.
RECOMMENDED: PARKHILL, SMITH &OOPER, INC., Consulting Engineer
M
Lawrence J. (Larry) Valdiz, P.E., Project Engineer
RECOMMENDED: LUBBOCK INTERNATIONAL AIRPORT, Owner
APPROVED:
APPROVED:
ATTEST:
APPROVED AS TO CONTENT:
- Z S . 1993
��4�;� 12- -5
Bern E. Case, A.A.E., Director of Aviation
GILBERT TEXAS CONSTRUCTION CO., Contractor
1 - 41 C)a�
BettyOM.'Johnsdfi, City Secretary
Administrative Change Order No. 1
Page 2 of 2
APPROVED AS TO FORM:
1993
1993
19"
e some, A.A.E.
Tntarim Director of Aviation
Assistant City &Me-y-
Atto