HomeMy WebLinkAboutResolution - 3760 - Supplemental Agreement #1- HDR Engineering Inc- E-W Freeway Railroad Relocation - 11_21_1991i
Resolution #3/6u
November 21, 1991
it Item #9
iI
JWF:dw
BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF LUBBOCK:
l THAT the Mayor of the City of Lubbock is hereby authorized and
directed to execute for and on behalf of said City Supplementary Agreement
No. 1 to the Agreement dated July 8, 1991, between said City (as Owner) and
HDR Engineering, Inc. (as Engineer) for professional engineering services
for the Railroad Relocation for East-West Freeway Project in Lubbock,
attached herewith, which shall be spread upon the minutes of the Council and
as spread upon the minutes of the Council shall constitute and be a part of
.I
this Resolution as if fully copied herein in detail.
Passed by the City Council this 21st day of November 1991.
C
B. C. McMINW, MAYOR
_ATTE,ST :
y ,)ecretary
APPROVED AS TO CONTENT:
J
-Zf VN1 LJ
James Bertram, Assistant City
Managgt for Development Services
APPROVED AS TO FORM:
J.Xotth Fullingim, Assistant
C' y Attorney
Resolution #3760
SUPPLEMENTAL AGREEMENT NO. 1
TO THE
AGREEMENT DATED JULY 8, 1991
BETWEEN
CITY OF LUBBOCK, TEXAS
OWNER
AND
HDR ENGINEERING, INC.
ENGINEER
FOR
PROFESSIONAL ENGINEERING SERVICES
FOR THE
RAILROAD RELOCATION FOR EAST -WEST FREEWAY IN LUBBOCK
PROJECT
NOVEMBER 21, 1991
SUPPLEMENTAL AGREEMENT NO. 1
TO THE
AGREEMENT DATED JULY 8, 1991
BETWEEN
CITY OF LUBBOCK, TEXAS
AND
HDR ENGINEERING, INC.
FOR
PROFESSIONAL ENGINEERING SERVICES
FOR THE RAILROAD RELOCATION FOR EAST -WEST FREEWAY
THIS IS SUPPLEMENTAL AGREEMENT NO. 1 made as of November 21, 1991, between
the City of Lubbock, Texas and HDR Engineering, Inc. for modifications to the
AGREEMENT BETWEEN CITY OF LUBBOCK, TEXAS AND HDR ENGINEERING, INC.
FOR PROFESSIONAL ENGINEERING SERVICES dated July 8, 1991.
OWNER and ENGINEER, in consideration of the mutual covenants contained herein,
agree to modifications to the Agreement as follows:
1. Change the Agreement Section 2.1.2 to read:
2.1.2 Provide Environmental Studies: Environmental Assessment Coordination
Document, Draft Environmental Impact Statement (DEIS) and Final Environmental
Impact Statement (FEIS) as related to the PROJECT.
2. Change the Agreement Section 2.1.3 to read:
2.1.3 Provide Public Involvement/Public Hearing assistance related to the
PROJECT and participate in three (3) public involvement meetings and one (1)
public hearing.
3. Change the Agreement Section 4.2.2 to read:
4.2.2 Final Design Phase - 210 calendar days.
4. Change the Agreement Section 4.3.1 to read:
4.3.1 Route Location Analysis, Environmental Studies and Public Involvement 700
calendar days.
5. Change the Agreement Section 5.3.1 to read:
5.3.1 For Additional Services as described in Paragraph 2.1 and Appendix,
Exhibit A, payment shall be on the basis of Cost Plus Fixed Fee. The Fixed Fee
shall be thirty-six thousand seventy-eight dollars and eighty-three cents
IPZ
($36,078.83). The maximum amount payable for Additional Services as described
in Appendix, Exhibit A, is six hundred twenty-nine thousand six hundred ninety-one
dollars and forty-four cents ($629,691.44). Estimated Costs are itemized in the
Appendix, Exhibit D. The maximum amount payable will be revised in the event
of change in scope, increased scope, complexity or character of PROJECT or
periods of service which exceed those periods defined in Section 4 as mutually
agreed in writing by OWNER and ENGINEER.
6. Change the APPENDIX, EXHIBIT A, Section I.A.1.a. to read:
a. Four alternative routes shall be evaluated.
7. Delete the APPENDIX, EXHIBIT A, Section B and replace with the following:
B. ENVIRONMENTAL STUDIES AND PUBLIC INVOLVEMENT (Additional
Services, SDHPT Function Code 120)
1. Environmental Reports
a. An Environmental Assessment Coordination Document
containing the following shall be prepared, anticipating the
need for a Draft Environmental Impact Statement.
1. Description of the Proposed Project - Describe the
location, length, termini and proposed improvements.
2. Need - Identify and describe the problem which the
proposed project is designed to correct.
3. Alternatives Considered - Discuss all reasonable
alternatives to the proposed actions which were
considered.
4. Impacts - Discuss the social, economic and
environmental impacts of the alternatives considered
and describe whether or not impacts are considered to
be significant.
5. Comments and Coordination - Describe coordination
efforts and comments received from government
agencies and the public: Formal coordination and
communication with government agencies and the
public shall be provided by SDHPT.
If it is believed that the proposed project requires a
Section 4(f) evaluation, the ENGINEER shall notify the
OWNER. The ENGINEER shall proceed with
development of technical data for a Section 4(f)
evaluation after agreement between the OWNER and
ENGINEER on additional scope and additional
compensation and after receipt of written notice to
proceed from OWNER.
-3-
0
0
6. Appendices (if any) - Include only analytical information
that substantiates an analysis which is important to the
document. Other information should be incorporated
by reference only.
A Draft Environmental Impact Statement (DEIS) containing the
following shall be prepared in accordance with applicable
Texas Department of Transportation (TxDOT), Federal
Highway Administration (FHWA), Interstate Commerce
Commission (ICC) and National Environmental Policy Act
(NEPA) requirements.
1. Title Page
2. EIS Identification Number
3. Summary
4. Table of Contents
5. Purpose and Need for Action
6. Discussion of Alternatives including the preferred
alternative, all reasonable alternatives and other
alternatives considered but dropped from detailed
study.
7. Affected Environment
8. Environmental Consequences as identified in the Texas
DOT (TxDOT) Operations and Procedures Manual, Part
II-B, Environmental and Public Involvement Procedures
During Project Specific Planning and Development
9. List of Preparers
10. List of Agencies, Organizations and Persons to Whom
Copies of the Statement are Sent
11. Comments and Coordination
12. Index
13. Appendices
C. A Final Environmental Impact Statement (FEIS) shall be
prepared after appropriate interagency review within time limits
prescribed by the Code of Federal Regulations, Title 23, Part
771.
Public Involvement
a. All public involvement procedures shall be in accordance with
TxDOT Administrative Order 23-82.
b. Three public involvement meetings and one public hearing
held in conjunction with TxDOT's East-West Freeway public
hearing shall be scheduled, coordinated and conducted.
C. Technical assistance, meeting/hearing preparation,
maintenance of contact lists, minutes of meeting(s), and
i'a
exhibit preparation shall be provided by the ENGINEER.
Texas Department of Transportation (TxDOT) shall conduct
the public hearing.
d. Public Relations - TxDOT shall provide any required fact
sheets and public relations or public notifications.
3. Hazardous Materials Investigations - the ENGINEER shall perform a
Level 1 Hazardous Materials Investigation for the old and new
railroad right-of-way.
a. Task 1: A record search to determine past ownership and
historical uses of "high risk" properties located within the
project corridor.
b. Task 2: Conduct a "windshield" survey to investigate sites for
potential environmental contamination or hazardous materials
storage violations.
C. Task 3: A review of applicable local, state and federal records
to determine possible permit violation or clean-up
requirements within the project corridor.
d. Task 4: An analysis of historical aerial photographs to
determine prior land uses in the project vicinity.
e. Task 5: A written Hazardous Materials Evaluation Report
summarizing the results of the Investigation.
Recommendations for a Level 2 Investigation will be made
based on findings of the preliminary study.
4. General Guidelines for Preparation of Environmental Documents
a. The environmental documents prepared shall be provided on
paper and on a 3 1/2" IBM 1.44 MB diskette(s).
b. Fifteen draft copies and fifteen final copies of the
Environmental Documents shall be provided. One copy with
the camera-ready artwork shall be provided for TxDOT's
attachment to the East-West Freeway environmental
documents, to be prepared by TxDOT.
C. The environmental document shall be prepared in accordance
with the content and format of FHWA Technical Advisory
T6640.8A.
d. Exhibits in the environmental document shall be limited to 11"
by 17" where possible.
8. Delete APPENDIX, EXHIBIT D, SUMMARY OF COMPENSATION and replace with
the following:
-5-
EXHIBIT D
SUMMARY OF COMPENSATION
This exhibit expands the Basis and Amount of Compensation described in SECTION 5 -
PAYMENTS OF ENGINEER of the Agreement for the PROJECT known as Railroad
Relocation for East-West Freeway in Lubbock.
N.
HDR ENGINEERING, INC.
Seagraves, Whiteface &
Lubbock Railroad
HOURS AND LABOR COST
SUMMARY
Relocation for
East-West Freeway
-------
- - ------
- --- ---- - --- -------------------------
--------------------- MANHOURS
---------------------------
--------------------------------------------
- - - -
DIRECT
- - -
DIRECT
LABOR
LABOR +
FUNCTION HDR LABOR CATEGORY
A
B
C
D
E
F
TOTAL
COST
ON COST
CODE
HRS
(DLC)
(DLCx2.616)
110 ROUTE AND DESIGN STUDIES
64
404
920
0
608
168
2,164
49,144.00
128,560.70
120 ENVIRONMENTAL STUDIES AND PUBLIC
INVOLVEMENT
138
622
260
64
380
328
1,792
42,800.00
111,964.80
------------------------------------------------------------------------------------------------------------------------------------------------------------------
PROJECT TOTALS - HDR ENGINEERING
202
1,026
1,180
64
988
496
3,956
$91,944.00
$240,525.50
HDR ENGINEERING - TOTAL LABOR COSTS ---------------------------
$240,525.50
LABOR
CATEGORIES:
A = Principal
HDR ENGINEERING - DIRECT COSTS--------------------------------
B = Project Manager
C = Design Engineer
Printing and Reproduction
10,000.00
D = Design Tech
Travel
20,000.00
E = Drafter
Computer at $10.00/hour
2,000.00
F = Clerical
CADD at S15.00/hour
3,600.00
Telephone, Postage, Misc.
-----------------------------------------------------
11,500.00
TOTAL DIRECT COSTS - HDR
47,100.00
SUBCONTRACTS
Hicks 214,216.11
PSC 91,771.00
-------------------------------------------
TOTAL SUBCONTRACTS 305,987.11
NOR ENGINEERING - TOTAL COSTS $593,612.61
FIXED FEE 36,078.83
TOTAL --------------
TOTAL 629,691.44
HDR ENGINEERING - WORK ESTIMATE DETAIL SHEET
FUNCTION CODE 110 ROUTE AND DESIGN STUDIES
---------------------MANHOURS
-------------------
DIRECT
DIRECT
LABOR
LABOR +
LABOR
CATEGORY
A
B
C
D E
F
TOTAL
COST
OH COST
FUNCTION PLAN
HRS
(DLC)
(DLCx2.616)
SUB -CODE SHTS
WORK DESCRIPTION
Project Management - 4 months
8
128
32
168
4,816.00
12,598.66
Kick -Off Meeting
8
16
32
24
16
96
2,176.00
5,692.42
Develop Study Plan and Scope
8
16
80
24
16
144
3,376.00
8,831.62
Data Collection
SW&LR Operations
4
24
4
32
776.00
2,030.02
AT&SF Operations
4
24
4
32
776.00
2,030.02
Existing Conditions
2
24
4
30
712.00
1,862.59
Piggyback Research
1
8
2
11
256.00
669.70
Maintenance / Dinner Train
1
8
2
11
256.00
669.70
Identification of Alternatives
8
40
120
80
16
264
5,928.00
15,507.65
Evaluation of Alternatives
4
24
80
8
116
3,032.00
7,931.71
Determine Preferred Route
4
16
40
60
1,680.00
4,394.88
15
Design Schematic
8
64
200
200
472
10,184.00
26,641.34
Preliminary ROW
2
24
40
40
106
2,412.00
6,309.79
Traffic Analysis
2
16
80
16
114
2,788.00
7,293.41
Report
8
40
120
240
40
448
8,456.00
22,120.90
Quality Control
4
8
40
8
60
1,520.00
3,976.32
15
FUNCTION CODE 110 TOTALS
64
404
920
0 608
168
2,164 $49,144.00
$128,560.70
LABOR CATEGORIES: A=Principal, B=Project Manager,
C=Design
Engr,
D=Design
Tech,
E=Drafter, F=Clerical
HDR ENGINEERING - DIRECT COSTS
Printing and Reproduction
$5,000.00
Travel
$10,000.00
Computer at S10.00/hour
$1,200.00
CADD at S15.00/hour
S3,000.00
Telephone, Postage, Misc.
-------------------------------------------
$1,500.00
TOTAL DIRECT COSTS
S20,700.00
SUBCONTRACTS
Parkhill, Smith & Cooper $29,912.00
-------------------------------------------
TOTAL SUBCONTRACTS $29,912.00
HDR ENGINEERING - TOTAL COSTS $179,172.70
FIXED FEE $19,284.11
--------------
TOTAL $198,456.81
--------------
--------------
HDR ENGINEERING - WORK ESTIMATE DETAIL SHEET
FUNCTION CODE 120 ENVIRONMENTAL STUDIES AND PUBLIC INVOLVEMENT
------------------- MANHOURS ------------------------ DIRECT DIRECT
LABOR LABOR +
LABOR CATEGORY A B C D E F TOTAL COST ON COST
FUNCTION PLAN HRS (DLC) (DLCx2.616)
SUB -CODE SHTS WORK DESCRIPTION
Project Management - 23 months 24 368 184 576 14,992.00 39,219.07
Hazardous Materials investigation * 10 260 64 180 40 554 11,264.00 29,466.62
Review/Coordinate EA Report
4
20
4
28
856.00
2,239.30
Review/Coordinate DEIS
16
60
16
92
2,784.00
7,282.94
Review/Coordinate FEIS
8
30
8
46
1,392.00
3,641.47
Coordinate with TxDOT/FHWA
8
40
8
56
1,712.00
4,478.59
Public Meetings (3)
48
48
80 40
216
5,152.00
13,477.63
Public Hearing (1)
16
16
80 8
120
2,400.00
6,278.40
Incorporate Comments
4
40
40 20
104
2,248.00
5,880.77
----------------------------------------------------------------------------------------------------------------------------------
0 FUNCTION CODE 120 TOTALS 138 622 260 64 380 328 1792 S42,800.00 S111,964.80
LABOR CATEGORIES: A=Principal, B=Project Manager, C=Design Engr, D=Design Tech, E=Drafter, F=Clerical
HDR ENGINEERING - DIRECT COSTS
Printing and Reproduction $5,000.00 * Hazardous Materials investigation
Travel S10,000.00 covers only Level I analysis of the
Computer at S10.00/hour $800.00 existing railroad right-of-way and
CADD at $15.00/hour $600.00 alternative routes.
Telephone, Postage, Misc. S5,000.00
Haz. Materials Investigat $5,000.00
---------------------------------------
TOTAL DIRECT COSTS $26,400.00
SUBCONTRACTS
Hicks $214,216.11
PSC $61,859.00
---------------------------------------
TOTAL SUBCONTRACTS $276,075.11
HDR ENGINEERING - TOTAL COSTS S414,439.91
FIXED FEE $16,794.72
TOTAL $431,234.63
9. Delete APPENDIX, EXHIBIT E, PROJECT SCHEDULE and replace with the
following:
-10-
EXHIBIT E
PROJECT SCHEDULE
-11-
a n.adReiucatconfor
..,t West Freeway
Prorkned Protect Schedule
EXHIBIT E
Months from Notice to Proceed
1991 j
1992 1 1993 199� 1993
__
fart and Deacriptiae l A S 0 NjD
1 P M AWN I l A S iO H D 1 F MI ANII JI DAIS �O�N D 1 P N A M 1 J A S O N D J F N A N 1 1 iA
ROUTE LOCATION ANALYSIS, ENVIRONMENTAL STUDIES AND PUBLIC INVOLVEMENT
Prnjeq Msaagement A Aderinlstratice
Route Loaatiae Analyst
A. Identify Alternatives
i
B. Evaluate Alterestives
C. Select Preferred Route
>
Esviroamental Studies tad Public Involvement
A. Public involvement Program
B. Develop Eaviroon»ntal Basellne(EA)
C. Identify Impacts, Mitigation (EA)
D. Public Meetings
•
•
•
E. Submit Draft Coordination EA to COIJDistrkt
•
F. Review A Revin Cuordinatioo EA
G. District Submits EA to D-9
•
H. D-1 Review; Revise, Resubmit Coordination EA
L D—g Submits EA to FHWA. Other Ageacles:
30 Day Comment Period
J. Dstria Drafts NO], Submits to D—g
•
K. District, D —9 Notify At". State Clearinghouses
L. FHWA/IYDOT Publish NOI
•
M. Prepare DEIS Review Draft
.1. COL/District Reviser; Ravin, Resubmit DEIS
O. D—fi Review; Ravin, Resubmit DEIS
P. FHWA Reviews; Ravin. Resubmit DEIS
NONE
O. FHWA Adopts DEIS for Circulation
•
R. D-1. District Circulate DEIS for Comment
•
S. EPA/raDOT Publish Notice of DEIS Availability
•
T. 0—Day Comment Period
U. Respond to Comments
V. District Publishes Notice of Public Hearing
•
W. Public Hearing on DEIS
•
X. Prepare FEIS
Y. D—i Review; Ravin, Resubmit
Z. FHWAReviewand Approval
ONO
AA. D-1 Dlwributes FEIS
•
BB. D—S Nottlles Are.,
'
State Clearinghouses
•
CC. EPAfrxD(Yr Publish Notice of FEIS Availability
•
DD. FHWA Regional Office Completes and Si t ROD
PRELIMINARY DESIGN. FINAL DESIGN A BIDDING PHASES - -
Projecs Management A Administration
NTP — Preliminary Design Piave
>
A. Ground Control -- Aerisl Mapping
B. Coordinate with Geaech Consultant A Surveyor
C. Prelimmary Design. Plans A Cost Estimates
D. Right—of—Wa Acquisition Utility Relocation
F'unl Design Phase
A. Prepare Plans, Specifications A Estimates
B. ReviewbyCity. SDHPTASWRLR
C. Incorporate Review Comments
D. Tack Materiels Procurement
Biddi.Phase
CONSTRUCTION PHASE — ADMINISTRATION OF THE CONSTRUCTION CONTRACT
Coestraction Engineering A Inspoctlossf[ProjJect N mt
Shop Drawiffix Review
Final Inspection
Acceptance by Railroad
Aa—Built Drawin
ICC Accoantin a Estimates
Demolition and Sal"Se Railroad
Redroed ROW Clear for F Constreaios
�.JA
1�0
l A
S O
N D
1 F
N A
N D
1 P
MAN
1
J A
S O
N D
1 P
M A
M 1
S A S O N D J P;UJAJl
1 A
19
1992
1993
1 199S
Months from Notice to Proceed
Except as modified herein, all other provisions of the Agreement remain unchanged.
IN WITNESS WHEREOF, the parties have executed this Supplemental Agreement as of
the day and year first written above.
Approved As To Content:
Name. \James E. Bertram
Title: Assistant City Manager for
Development Services
Approved As To Form:
By: J-Afit�t�
Name: J. Worth Fullingim
Title: Assistant City Attorney
Approved:
Steil
"OWNER"
CITY OF LUBBOCK, TEXAS
a
By:
A�k —
Name: B.C. VcMinn
Title: Mayor
Address: 1625 13th Street
Lubbock, Texas 79457
est:
B
Name: Ranette Bo d
Title: City Secretary
"ENGINEER"
HDR ENGINEERING, INC.
By: �JAAl / � —
Name: William B. a od, P.E.
Title: Senior Vice President
Address: 12700 Hillcrest Road
Suite 125
Dallas, Texas 75230-2096