RESOLUTION
RESOLUTION ACCEPTING IMPROVEMENTS AS LISTED BELOW:
WHEREAS, in conformance with the paving requirement provisions of City
Ordinance 1331, the subdivider of Lots 4 & 5, Methodist Hospital Addition made
arrangements with Hub City Pavers, Inc. for the construction of improvements
in said subdivision under the provisions of said Ordinance prior to the re-
cording of the subdivision plat of the above -mentioned Addition including the
following:
Alley paving between 21st and 22nd Streets from Knoxville Avenue West to the
East side of Lot 4, then South to 22nd Street known as Unit No. A-461-07.
WHEREAS, the construction of the above improvements was performed under
the supervision of the City Engineer, and said improvements have been com-
pleted and have been inspected and found to have been constructed in
accordance with City specifications and in accordance with the provisions of
City Ordinance 1331; NOW THEREFORE:
BE IT RESOLVED THE CITY COUNCIL OF THE CITY OF LUBBOCK:
SECTION 1. THAT the improvements BE and the same are hereby accepted
and the City Engineer BE and he is hereby authorized to notify the owner of
acceptance by the Lubbock City Council.
SECTION 2. THAT this Resolution shall take effect and be in force from
and after its passage.
Passed by the City Council this 14th day of November 1991.
B. C. McMIN , MAYOR
APPROVED AS TO FORM:
Wort u ingim, Assistant Pty
A. orney
CONSOLIDATED FINAL COST
METHODIST HOSPITAL ADDITION
LOTS 4 & 5
UNIT A-461-07
496.7 S.Y. Concrete Alley Paving @ $ 30.00/ S.Y. $14,901.00
15 L.F. of Curb and Gutter @ $ 6.00/L.F. 90.00
29.3 S.Y. Alley Return @ $ 30.00/S.Y. 879.00
392 S.Y. Concrete Removal @ $ 13.50/S.Y. 5,292.00
25 L.F. Curb and Gutter Removal @ $ 6.00/L.F. 150.00
TOTAL CONTRACT COST $21,312.00
The quantities and cost were submitted by Hugo Reed and Associates, Inc.