HomeMy WebLinkAboutResolution - 5690 - Amendment #1 To Agreement - Delta Airport Consultants Inc - Rehabilitate Runway - 10_23_1997RESOLUTION NO.5690
Item #21
October 23, 1997
KESOLUTION
BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF LUBBOCK:
THAT the Mayor of the City of Lubbock BE and is hereby authorized and directed to
execute for and on behalf of the City of Lubbock Amendment No. One to an Agreement between
the City of Lubbock and Delta Airport Consultants, Inc. for runway reconstruction, attached
hereto, which Amendment shall be spread upon the minutes of the Council and as spread upon the
minutes of this Council shall constitute and be a part of this Resolution as if fully copied herein in
detail.
Passed by the City Council this 23rd day of . . October , 1997.
ATTEST:
Ka Darnell, City Secretary
APP OVED AS TO CONTENT:
Earle, Aviation
VED AS TO FORM:
arold Willard, Assistant City Attorney
14W : gs/ccd ocs'D e1taAC. res
October 13, 1997
RESOLUTION NO. 5690
Item #21
October 23, 1997
PROJECT BUDGET SUMMARY
RahabttRate Runway 17R45L Keel (11.5W x 60
Lubbock kftmatlonal Airport
Lubbock. Texas
AP Project No. U"138-19-9T
Dena Project NO..T?c 97053
Dale. September 19.1997
Grant Amount AtP-19 Total
FAA i5,998.361A0 $5.998.361AO
Local IM.484.60 SSt36,484.60
Total $11AN.848.00 $6.664A46.00
LOM
LATEST
BUDGET
ESTIMATE
AP-19
BUDGET
ESTMATE
AIP-10
COST
TO DATE
%
COMP
a.
Adadnfstrttlon
10,000.00
10.000.00
0.00
subtotat
$10.000.00
$10,000.00
=OM
0%
b.
Preamir ary
0650 Ground Surveys (High -Tech)
23.000.00
33AMM
28.190.00
Design Ceotechnlcal (Raba-l(fstner)
46.000.00
46A=.00
0.00
Design Concrete Specialists (APTech)
18,331.00
18.331.00
11.588.18
Subtotal:
$99.331.00
$99.331.00
MXIBAS
40%
d.
Englneedng Bash SeMatas
Design thru Bidding Phase (Della-tump Sum)
323.060.00
323Ae0A0
316.598.80
Construction Phase Services (Delta#ect Cost) (eat)
163.746.W
183,M.00
0A0
Subtotal
5488.608.00
$486.806.00
$316.598.80
65%
a. Other Engrg
CIA Tes" (Terra)
75.000.00
75.00D.00
0.00
Construction Surveys(est)
10.000.00
10,000.00
0.00
Direct Nonsalery Expenses - Design
12AW.00
12AMOD
9207A3
Direct Nonsalary Expenses - Construction (eat)
771.650.00
77,650.00
OAO
Wed Fee - Design
11213.00
11213.00
5.494.37
Wed Fee - Construction (est)
09,033.00
89.033.00
0.00
Cost Allowance - Design
11.213.00
11213.00
OAO
Cost Allowance -Constmctonlost)
51.444.00
51A".00
0A0
Subtotal:
$318.353.00
:318,353.00
$14.701.80
5%
f. Project Mapecttlon
Resident Project ReKesentaWe (est)
188.039.00
188.039AD
0.00
Subtotal:
$188A39.00
$188,039.00
$0.00
0%
L Construction
Contractor
5,362,317.00
5A62.317.00
OAO
P-501 PCC Bonus
20OAOOAO
200A00.00
OAO
subtotal
$5,562.317.00
=5,56Z.317.00.
$0.00
0%
Total•
$6,664,846.00
$6.664,846.00
$371.078.78
6%
Total Amount
6,664,846.00
6.664A46.00
371.078.78
6%
AMENDMENT NO. ONE (1)
TO THE
ENGINEERING AGREEMENT
BETWEEN
CITY OF LUBBOCK, TEXAS
THE OWNER
AND
DELTA AIRPORT CONSULTANTS, INC.
THE ENGINEER
DATE: SEPTEMBER 19, 1997
DELTA PROJECT NO. TX 97053
TASK 2 - RECONSTRUCT RUNWAY 17R-35L KEEL (CONSTRUCTION PHASE)
3115
AMENDMENT NO. ONE (1)
TO THE AGREEMENT
BETWEEN OWNER AND ENGINEER
FOR PROFESSIONAL SERVICES
SEPTEMBER 19, 1997
This AMENDM 14T NO. ONE (1) dated September 19, 1997 is made part of the Engineering
Agreement dated May 22, 1997 between the City of Lubbock, Texas, the OWNER, and Delta Airport
Consultants, Inc., the ENGINEER, for work at the Lubbock International Airport, Lubbock, Texas.
The following revisions and/or additions are made to the original Engineering Agreement.
The scope of work to be covered by Amendment No. One (1) shall be as follows:
TASK 2: RECONSTRUCT RUNWAY 17R 35L IXEL (CONSTRUCTION PHASE)
ADD the following paragraphs to ARTICLE 7:
7.8 Task 2: Reconstruct Runway 17R-35L Keel (Construction Phase). Basic services for
construction phase services shall be compensated on a unit cost plus fixed fee basis.
Compensation for these services shall be limited to a budget amount of $583,176 unless
written authorization has been received from the OWNER. The budget amount is based
on an estimated cost budget of $518,889 and a fixed fee of $64,287.
Except as so modified, supplemented, and amended, the terms and conditions of the Agreement
for Engineering Services dated May 22, 1997 shall remain in full force and effect.
The following attachments are made part of this amendment:
Attachment "AMD 1-1" Estimated Workhours and Summary of Fees (Task 2)
Attachment "AMD 1-2" Subcontractor Proposals (Task 2)
Attachment "AMD 1-3" 1998 Fee Schedule
70533115.AM1 - 1 -
AMENDMENT NO. ONE (1)
All other provisions of the original agreement remain unchanged.
OWNER:
City of Lubbock
1625 13th Street, Suite L-04
Lubbock. Texas 79401
Windy Sitton
Mayor
10-23-97
Date
ATTEST:
ENGINEER:
Delta Airport Consultants, Inc.
9101 Southern Pine Blvd., Suite 140
Charlotte, North Carolina 28273
ken�eth W. Moody-,'
Vice President
Date
ND X Kaythi a Darnell, City Secretary Notary: Kristen D. Richardson
I�,c���s��pz�zxxxxxxxxxxxxxx
APPROVED AS TO CONTENT:
Mark rle, Director of Aviation
70533115.AM1 - 2 -
My Commission Expires: 7/18/2001
APPROVED AS TO FORM:
arold Wi ard, Asst. City Attorney
ATTACHMENT " AMD 1-1"
ESTIMATED WORKHOURS AND SUMMARY OF FEES (TASK 2)
ATTACHMENT'AMD 1-1'
Estimated Workhours - Article 7.6
Reconstruct Runway 17R-35L Keel (Construction Phase)
Lubbock International Airport
Lubbock, Texas
AIP Project No. 3-48-0138-19-97
Delta Project No. TX 97053
Date: September 19,1997
SENIOR PM
PM
PE
TECH
FLD REP
CLERICAL
Description
No.
(hr)
(hr)
(hr)
(Frc)
(hr)
(ho
CONSTRUCTION OBSERVATION
360 Calendar Days
BASIC SERVICES
Coordinate Award
8
0
4
0
0
0
Coordinate Contract Documents
16
0
8
0
0
4
Prepare Released for Construction Plans
16
24
24
48
0
16
Preconstruction Conference
1
24
0
8
0
0
8
Review Contractor OC Program
8
16
0
0
0
0
Review Contractor SWPPP
8
16
0
0
0
0
Prapaving Conference
1
24
0
8
0
0
4
Coordinate Testing
24
8
24
0
0
16
Review Test Results
72
24
60
0
0
16
Construction Visits
30
200
60
40
0
0
32
Coordinate Res. Prof. Rep.
160
80
96
0
0
24
Shop Drawing Review
48
16
32
_
0
0
8
Review Contr. Pay Request
14
16
8
16
0
0
16
Construction Coor+esponderce
120
160
96
0
0
48 `
Punch List Inspection
1
10
0
0
0
0
4
Anallnspedon
1
24
0
10
0
0
4
Final tituantity Review
8
4
16
8
0
0
• Basic Services Hours Subtotal:
786
416
442
56
0
200
ADDITIONAL SERVICES
FAA Pay Request/Budget Summary
13
8
0
16
_
0
0
4
Coordination with Airlines
24
16
16
0
0
2
- Rekxxd Drawings
8
16
16
`_ 64
0
0
Final Project Report
6
4
16
0
0
8
Independent Fee Review Package
4
8
0
0
0
4
Resident Project Rep.
0
0
0
0
4373
0
Construction Additional Services Subtotal:
52
44
64
64
4.373
18
File: 7053FE02.WK4
ATTACHMENT'AMD 1-1"
Estimated Workhours - Article 7.8
Reconstruct Runway 17R-35L Keel (Construction Phase)
Lubbock International Airport _
Lubbock,Texas
AIP Project No. 3-48-0138-19-97
Delta Project No. TX 97053
Date: September 19,1997
Field Representative Summry (360 Calendar DM
Preoonstruction Conference 8 Hrs
360 Calendar Days 9 Hrs/Calendar Day 3240 Hrs
120 Calendar Days 9 Hrs/Calendar Day 1080 Hrs
5 Pre/Post Calendar Days @ 9 Hrs/Calendar Day 45 Hrs
Total: 4373 Hrs
Per Diem/Housing Allowance
1 RPR @ 120 :Catendar Days 120 Calendar Days
1 RPR @ 12 months 12 Months
Mileage
. Mobilization & Demobilization 500 Miles
Job Related Mileage
360 Calendar Days @ 20 Miles/Calendar Day 7200 Miles
120 Calendar Days @ 20 Miles/Calendar Day 2400 Miles
5 Pre/Post Calendar Days @ 20 Mites/Calendar Day 100 Miles
Total: 10200 Miles
File: 7053FE02.WK4
ATTACHMENT •AMD 1-1'
Estimated Workhouts - Artide 7.8
Reconstruct Runway 17R-35L Keel (Construction Phase)
Lubbock International Airport
Lubbock, Texas
AIP Project No. 348-0138-1"7
Delta Project No. TX 97053
Date: September 19,1997
Est
Hourly
Est
Est
Description
Hm
Rate
Cost
Fee Totals
1) Work Hour Cost OmIgnthead)
a) Basic Services
Senior Project Manager
786
$99
77,814
11,672
Project Manager
416
$75
31,200
4,680
Project Engineer
442
$48
21.216
3,182
Tedmidan
56
$39
2,184
328
Clerical & Administrative
200
$36
7,200
1,080
Subtotal:
1900
$139,614
$20,942 $160,556
16%
b) Additional Services
Senior Project Manager
52
Project Manager
44
Project Engineer
64
Technician
64
Field Representative
4373
Clerical & Administrative
18
Subtotal: 4615
2) Direct Nonsala y ExMnses
Travel
Printing
Housing - RPR ($1250/Month)
Per Diem - RPR ($80/CD)
Subtotal:
3) Subcontracted Services
O!A Testing (Terra)
Constr & Record Surveys (est)
Subtotal:
4) Estimate Cost & Flied Fee
5) Cost Allowance
Article 7.8 Budget Amount:
$99
5,148
772
$76
3,300
495
$a
3,072
461
$39
2,496
374
$43
188,039
26,206
$36
648
97
$202,703
$30,405 $233,108
15%
30,000
3,000
4,000
400
12 $1.250 15,000
1,500
120 $80 9,600
960
$58,600
$5,860 $64,460
10%
60,800 6,080
10,000 1,000
$701800 $7,080 $77,880
10%
$471,717 $64,287 $536,004
10% $47,172 $0 $47,172
$518,889 $64,287 $583,176
$583,176
File: 7053FE02. WK4
ATTACIMENT "AMID 1-2"
SUBCONTRACTOR PROPOSALS (TASK 2)
TERRA ENGINEERS, INC.
5208 - 34TH STREET
P.O. BOX 16605 - LUBBOCK, TEXAS 79490-6605 - (806) 793-4767 - FAX (806) 793-4768
August 28, 1997
Delta Airport Consultants, Inc. _
9101 Southern Pine Boulevard, Suite 140
Charlotte, North Carolina 28273
Attn.: Mr. Tracy J. Saunders, P.E.
RE: Proposal for Acceptance Testing for the Lubbock International Airport -
Reconstruct Runway 17R-35L Keel
Dear Mr. Saunders:
As per letter dated August 14, 1997, Terra Engineers, Inc. is pleased to submit a
proposal for Acceptance Testing for the Lubbock Intemational Airport -Reconstruct
Runway 17R-35L Keel. -
We are very proud to inform you that Terra Engineers, Inc. is accredited by
American Association for Laboratory Accreditation (A2LA) in the field of Geotechnical
and Construction. Material Testing, therefore our firm meets the requirements of ASTM
D-3666 for testing bituminous concrete and ASTM C-1077 for Portland Cement Concrete
testing. Terra is also certified as Disadvantaged Business Enterprise, Minority Woman -
owned Business Enterprise and Historically Under-utilized Business (see the enclosed
copies of the certificates). We maintain Professional liability, General liability and
Workmens' compensation insurance policies.
Our technicians are NICET and TxDOT certified and have more than 5 years of
experience on construction material testing for highway and airport paving projects. We
also have a Professional engineer on board. We have had the opportunity to provide
Geotechnical and Constructibn Material Testing services for almost all the airports in
West Texas area for the last 2O years.
Terra Engineers, Inc. -appreciates the opportunity to be of service to you on this
project. Please do not hesitate to call me if you should have any questions concerning this
proposal.
Sincerely,
TERRA ENGINEERS, INC.
Ali Behpour, B
Manager, Material Testing
Encls.: as above
SOIL INVESTIGATION - MATERIAL TESTING - ENVIRONMENTAL SERVICES - PROFESSIONAL ENGINEERING SERVICES - NDT
Mr. Moody
August 28, 1997
Page 2 of 11
Lubbock International Airport: Reconstruct Runway 17R-35L Keel
. Alternate 1
NO.
ITEM
DESCRIPTION OF TEST
STANDARD
QTY
UNIT
TOTAL
NO.
1.0
P-152
Excavation and Embankment
1.1
P-152
Moisture Density Relation
ASTM D-698
1
80.00
80.00
1.2
P-152
Sand Cone Density Test
ASTM D-1556
5
45.00
225.00
1.3
P-152
Liquid Limit, Plastic. Limit and
ASTM D-4318
1
45.00
45.00
Plasticity Index of Soil
Mobilization, Mileage, & Tech Time
4
35.00
140.00
Total
490.00
2.0
P-209
Crushed Aggregate Base Course
2.1
P-209
Unit Weight of Aggregate
ASTM C-29
1
45.00
45.00
2.2
P-209
Soundness
ASTM C-88
1
175.00
175.00
2.3
P-209
Material Finer Than # 200 Sieve
ASTM C-117
1
25.00
25.00
2.4
P-209
Los Angeles Abrasion
ASTM C-131
1
150.00
150.00
2.5
P-209
Sieve Analysis
ASTM C-136
5
35.00
175.00
2.6
P-209
Moisture Densities
ASTM D-698
1
80.00
80.00
2.7
- P-209
Density of Soil and Soil Aggregate In-
ASTM D-2922
5
22.00
110.00
Place by Nuclear Method
2.8
P-209
Liquid Limit, Plastic Limit and
ASTM D-4318
1
45.00
45.00
Plasticity Index of Soil
Mobilization, Mileage, & Tech Time
-
6
35.00
210.00
Total
1015.00
3.0
P-210
Caliche Base Course
3.1
. P-210
Sieve Analysis
ASTM C-136
1
35.00
35.00
3.2
P-210
Moisture Density Relations
ASTM D-698
1
80.00
80.00
3.3
. P-210
Density of Soil by Sand Cone Method
ASTM D-1556
2
45.00
90.00
3.4
P-210
Liquid Limit, Plasticity Index
ASTM D-4318
1
45.00
45.00
Mobilization, Mileage, & Tech Time
4
35.00
140.00
Total
390.00
4.0
P-501
Portland Cement Concrete
Pavement
4.1
P-501
Making Curing Concrete Test
ASTM C-31
800
20.00
16,000.00
Specimen
4.2
P-501
Testing for Flexural Strength of
ASTM C-78
800
5.00
4,000.00
Concrete
4.3
P-501
Los Angeles Abrasion
ASTM C-131
1
150.00
150.00
4.4
P-501
Sieve Analysis
ASTM C-136
1
35.00
35.00
4.5
P-501
Unit Weight of Concrete
ASTM C-138
1
40.00
40.00
4.6
P-501
Test for Slump of Portland Cement
ASTM C-143
400
10.00
4,000.00
Mr. Moody
August 28, 1997
Page 3 of 11
Lubbock International Airport: Reconstruct Runway 17R-35L Keel
Alternate 1
NO. ITEM
DESCRIPTION OF TEST
STANDARD QTY
UNIT
TOTAL
NO.
4.7 P-501
Test for Air Content of Freshly Mix
ASTM C-231 400
15.00
6,000.00
Concrete by the Pressure
4.8 P-501
Test Method for Flat or Elongated
ASTM D-4791 1
40.00
40.00
Particles in Coarse Aggregate
Mobilization, Mileage, & Tech Time
400
35.00
14,000.00
Total
44,265.00
5.0
TxDOT Hot Mix Asphaltic Concrete
TxDOT Tyne
5.1
TxDOT Compacting Test Specimens Tex 206F
9
30.00
270.00
5.2
TxDOT Sieve Analysis Tex 201F
12
35.00
420.00
5.3
TxDOT Theoretical Maximum Specific Tex 227F
12
50.00
600.00
Gravity of Bituminous
5.4
TxDOT Vacuum Extraction Tex 21OF
12
65.00
780.00
5.5
TxDOT Bulk Specific Gravity of Compacted Tex 207F
9
30.00
270.00
Bituminous
5.6
TxDOT Stability and Flow
9
30.00
270.00
Mobilization, Mileage, & Tech Time
8
35.00
280.00
Total
2,890.00
6.0
Miscellaneous
6.1
Mileage Charge
N/C
6.2
Technician Time _
150
35.00
5,250.00
6.3
Engineer _
100
65.00
6,500.00
Total
_11,750.00
Sub Total
60,800.00
Note:
The number of test quoted above is estimated based on the project specification. The total
number of tests actually performed may vary during construction
phase and
shall be prorated
accordingly.
TERRA ENGINEERS, INC.
Mr. Moody
August 28, 1997
Page 4 of 11
Lubbock International Airport: Reconstruct Runway 17R-35L Keel
Alternate 2
NO. ITEM DESCRIPTION OF TEST STANDARD QTY UNIT TOTAL
NO.
1.0
P-152
Excavation and Embankment
1.1
P-152
Moisture Density Relation ASTM D-698
1
80.00
80.00
1.2
P-152
Sand Cone Density Test ASTM D-1556
5
45.00
225.00
1.3
P-152
Liquid Limit, Plastic Limit and ASTM D-4318
1
45.00
45.00
Plasticity Index of Soil
Mobilization, Mileage, & Tech Time
4
35.00
140.00
2.0
2.1
2.2
2.3
2.4
2.5
2.6
2.7
P-209
P-209
P-209
P-209
P-209
P-209
P-209
P-209
2.8 P-209
3.0 P-210
3.1 P-210
3.2 P-210
3.3 P-210
3.4 P-210
Crushed Aeareeate Base Course
Unit Weight of Aggregate
Soundness
Material Finer Than # 200 Sieve
Los Angeles Abrasion
Sieve Analysis
Moisture Densities
Density of Soil and Soil Aggregate In -
Place by Nuclear Method (min of 3)
Liquid Limit, Plastic Limit and
Plasticity Index of Soil
Mobilization, Mileage, & Tech Time
Caliche Base Course
Sieve Analysis
Moisture Density Relations
Density of Soil by Sand Cone Method
Liquid Limit, Plasticity Index
Mobilization, Mileage, & Tech Time
Total 490.00
ASTM C-29
1
45.00
45.00
ASTM C-88
1
175.00
175.00
ASTM C-117
1
25.00
25.00
ASTM C-131
1
-_ 150.00
150.00
ASTM C-136
5
35.00
175.00
ASTM D-698
1
80.00
80.00
ASTM D-2922
5
22.00
110.00
ASTM D-4318
1
45.00
45.00
Total 1,015.00
ASTM C-136
1
35.00
35.00
ASTM D-698
1
80.00
80.00
ASTM D-1556
2
45.00
90.00
ASTM D-4318
1
45.00
45.00
4
35.00
140.00
Total
390.00
4.0
P-501
Portland Cement Concrete
Pavement
4.1
P-501
Making Curing Concrete Test
ASTM C-31
512
20.00
10,240.00
Specimen
4.2
P-501
Testing for Flexural Strength of
ASTM C-78
512
5.00
2,560.00
Concrete
4.3
P-501
Los Angeles Abrasion
ASTM C-131
1
150.00
150.00
4.4
P-501
Sieve Analysis
ASTM C-136
1
35.00
35.00
4.5
P-501
Unit Weight of Concrete
ASTM C-138
1
40.00
40.00
4.6
P-501
Test for Slump of Portland Cement
ASTM C-143
300
10.00
3,000.00
Mr. Moody
August 28, 1997
Page 5 of 11
Lubbock International Airport: Reconstruct Runway 17R-35L Keel
Alternate 2
NO. ITEM
DESCRIPTION OF TEST
STANDARD QTY
UNIT
TOTAL
NO.
4.7 P-501
Test for Air Content of Freshly Mix
ASTM C-231 300
- 15.00
4,500.00
Concrete by the Pressure
4.8 P-501
Test Method for Flat or Elongated
ASTM D-4791 1
40.00
40.00
Particles in Coarse Aggregate
Mobilization, Mileage, & Tech Time
300
35.00
10,500.00
Total
31,065.00
5.0
TxDOT
Hot Mix Asphaltic Concrete
TxDOT Tvae
5.1
TxDOT
Compacting Test Specimens
Tex 206F
6
30.00
180.00
5.2
TxDOT
Sieve Analysis
Tex 201F
8-
35.00
280.00
5.3
TxDOT
Theoretical Maximum Specific
Tex 227F
8
50.00
400.00
Gravity of Bituminous
5.4
TxDOT
Vacuum Extraction
Tex 21OF,
8
65.00
520.00
5.5
TxDOT
Bulk Specific Gravity of Compacted
Tex 207F
6
30.00
180.00
Bituminous
5.6
TxDOT
Stability and Flow
6
30.00
180.00
Mobilization, Mileage, & Tech Time
6
35.00
210.00
'
Total
1,950.00
6.0
Miscellaneous
6.1
Mileage Charge
N/C
6.2
Technician Time
125
35.00.
4,375.00
6.3
Engineer
80=
65.00
5,200.00
Total
9,575.00
Sub Total
44,485.00
Note: The number of test quoted above is estimated based on the project specification. The total
number of tests actually performed may vary during construction phase and shall be prorated
accordingly.
TERRA ENGINEERS, INC.
Mr. Moody
August 28, 1997
Page 6 of 11
Lubbock International Airport: Reconstruct Runway 17R-35L Keel
Alternate 3
NO. ITEM DESCRIPTION OF TEST STANDARD QTY UNIT TOTAL
NO.
1.0 P-152
Excavation and Embankment
1.1 P-152
Moisture Density Relation ASTM D-698
1
80.00
80.00
1.2 P-152
Sand Cone Density Test ASTM D-1556
5
45.00
225.00
1.3 P-152
Liquid Limit, Plastic Limit and ASTM D-4318
1
45.00
45.00
Plasticity Index of Soil
Mobilization, Mileage, & Tech Time
4
35.00
141.00
2.0
2.1
2.2
2.3
2.4
2.5
2.6
2.7
P-209
P-209
P-209 -
P-209
P-209
P-209
P-209
P-209
2.8 P-209
Crushed Aggregate Base Course
Unit Weight of Aggregate
Soundness
Material Finer Than # 200 Sieve
Los Angeles Abrasion
Sieve Analysis
Moisture Densities
Density of Soil and Soil Aggregate In -
Place by Nuclear Method (min of 3)
Liquid Limit, Plastic Limit and
Plasticity Index of Soil
Mobilization, Mileage, & Tech Time
Total 490.00
ASTM C-29
1
45.00
45.00
ASTM C-88
1
175.00
175.00
ASTM C-117
1
25.00
25.00
ASTM C-131
1
150.00
150.00
ASTM C-136
5
35.00
175.00
ASTM D-698
1
80.00
80.00
ASTM D-2922
5
22.00
110.00
ASTM D-4318
1
45.00
45.00
6
35.00
210.00
Total
1,015.04
3.0
P-210 _
Caliche Base Course
3.1
P-210 -
Sieve Analysis
ASTM C-136
1
35.00
35.00
3.2
P-210
Moisture Density Relations
ASTM D-698
1
80.00
80.00
3.3
P-210
Density of Soil by Sand Cone Method
ASTM D-1556
2
45.00
90.00
3.4
P-210
Liquid Limit, Plasticity Index
ASTM D-4318
1
45.00
45.00
Mobilization, Mileage, & Tech Time
4
35.00
140.00
Total
390.00
4.0
P-501
Portland Cement Concrete
Pavement
4.1
P-501
Making Curing Concrete Test
ASTM C-31 &
420
20.00
8,400.00
Specimen
-
4.2
P-501
Testing for Flexural Strength of
ASTM C-78
420
5.00
2,100.00
Concrete
4.3
P-501
Los Angeles Abrasion
ASTM C-131
1
150.00
150.00
4.4
P-501
Sieve Analysis
ASTM C-136
1
35.00
35.00
4.5
P-501
Unit Weight of Concrete
ASTM C-138
1
40.00
40.00
4.6
P-501
Test for Slump of Portland Cement
ASTM C-143
250
10.00
2,500.00
F
Mr. Moody
August 28, 1997
Page 7 of 11
Lubbock International Airport: Reconstruct Runway 17R-35L Keel
Alternate 3 -
NO. ITEM
NO.
DESCRIPTION OF TEST
STANDARD QTY
UNIT
TOTAL
4.7 P-501
Test for Air Content of Freshly Mix
ASTM C-231 250
15.00
3,750.00
Concrete by the Pressure
4.8 P-501
Test Method for Flat or Elongated
ASTM D-4791 1
40.00
40.00
Particles in Coarse Aggregate
Mobilization, Mileage, & Tech Time
250
35.00
8,750.00
5.0 TxDOT Hot Mix Asphaltic Concrete
TxDOT Type
5.1 TxDOT
Compacting Test Specimens
5.2 TxDOT
Sieve Analysis
5.3 TxDOT
Theoretical Maximum Specific
Gravity of Bituminous
5.4 TxDOT
Vacuum Extraction
5.5 TxDOT
Bulk Specific Gravity of Compacted
Bituminous
5.6 TxDOT
Stability and Flow
Mobilization, Mileage, & Tech Time
6.0
Miscellaneous
6.1
Mileage Charge
6.2
Technician Time
6.3
Engineer
Total
25,765
Tex 206F
6
30.00
180.00
Tex 201F
8
35.00
280.00
Tex 227F
8
50.00
400.00
Tex 21OF
8
65.00.
520.00
Tex 207F
6
30.00
180.00
6
30.00
180.00
6
35.00
210.00
Total
1,950.00
N/C
100 35.00 3,500.00
65 65.00 4,225.00
Total 7,725.00
Sub Total 37,335.00
Note: The number of test quoted above is estimated based on the project specification. The total
number of tests actually performed may vary during construction phase and shall be prorated
accordingly.
TERRA ENGINEERS, INC.
Mr. Moody
August 28, 1997
Page 8 of 11
Lubbock International Airport: Reconstruct Runway 17R-35L Keel
Alternate 4
NO.
ITEM
NO.
DESCRIPTION OF TEST
STANDARD
QTY
UNIT
TOTAL
1.0
P-152
Excavation and Embankment
1.1
P-152
Moisture Density Relation
ASTM D-698
1
80.00
80.00
1.2
P-152
Sand Cone Density Test
ASTM D-1556
5
45.00
225.00
1.3
P-152
Liquid Limit, Plastic Limit and
ASTM D-4318
1
45.00
45.00
Plasticity Index of Soil
Mobilization, Mileage, & Tech Time
4
35.00
140.00
Total
490.00
2.0
P-210
Caliche Base Course
2.1
P-210
Sieve Analysis
ASTM C-136
1
35.00
35.00
2.2
P-210
Moisture Density Relations
ASTM D-698
1
80.00
80.00
2.3
P-210
Density of Soil by Sand Cone Method
ASTM D-1556
2
45.00
90.00
2.4
P-210
Liquid Limit, Plasticity Index
ASTM D-4318
1
45.00
45.00
Mobilization, Mileage, & Tech Time
4 "
35.00
140.00
Total
390.00
3.0
P-501
Portland Cement Concrete
Pavement
3.1
P-501
Making Curing Concrete Test &
ASTM C-31 &
320
20.00
6,400.00
Testing for Flexural Strength of
ASTM C-78
320
5.00
1,600.00
Concrete
3.2
P-501
Los Angeles Abrasion
ASTM C-131
1
150.00
150.00
3.3
P-501
Sieve Analysis
ASTM C-136
1
35.00
35.00
3.4
P-501
Unit Weight of Concrete
ASTM C-138
1
40.00
40.00
3.5
P-501
Test for Slump of Portland Cement
ASTM C-143
200
10.00
2,000.00
3.6
P-501
Test for Air Content of Freshly Mix
ASTM C-231
200
15.00
3,000.00
Concrete by the Pressure
3.7
P-501
Test Method for Flat or Elongated
ASTM D-4791
1
40.00
40.00
Particles in Coarse Aggregate
Mobilization, Mileage, & Tech Time
200
35.00
7,000.00
Total
20,265.00
4.0
TxDOT
Hot Mix Asnhaltic Concrete
TxDOT Tvne
4.1
TxDOT
Compacting Test Specimens
Tex 206F
6
30.00
180.00
4.2
TxDOT
Sieve Analysis
Tex 201F
8
35.00
280.00
4.3
TxDOT
Theoretical Maximum Specific
Tex 227F
8
50.00
400.00
Gravity of Bituminous
4.4
TxDOT
Vacuum Extraction
Tex 21OF
8
65.00
520.00
Mr. Moody
August 28, 1997
Page 9 of 11 _
Lubbock International Airport: Reconstruct Runway 17R-35L Keel
Alternate 4
NO. ITEM
DESCRIPTION OF TEST
STANDARD QTY
UNIT
TOTAL
NO.
4.5 TxDOT
Bulk Specific Gravity of Compacted
Tex 207F 6
30.00
180.00
Bituminous
4.6 TxDOT
Stability and Flow
6
30.00
180.00
Mobilization, Mileage, & Tech Time
6
35.00
210.00
Total
1,950.00
5.0
Miscellaneous
5.1
Mileage Charge
N/C
5.2
Technician Time
90 35.00
3,150.00
5.3
Engineer
55 65.00
3,575.00
Total
6,725.00
Sub Total
29,820.00
Note: The number of test quoted above is estimated based on the project specification. The total
number of tests actually performed may vary during construction phase and shall be prorated
accordingly.
TERRA ENGINEERS, INC.
Mr. Moody
August 28, 1997
Page 10 of 11
Lubbock International Airport: Reconstruct Runway 1711-35L Keel
Alternate 5
NO. ITEM DESCRIPTION OF TEST STANDARD QTY UNIT TOTAL
NO.
1.0
P-152
Excavation and Embankment
1.1
P-152
Moisture Density Relation ASTM D-698
1 80.00
80.00
1.2
P-152
Sand Cone Density Test ASTM D-1556
5 45.00
225.00
1.3
P-152
Liquid Limit, Plastic Limit and ASTM D-4318
1 45.00
45.00
Plasticity Index of Soil
Mobilization, Mileage, & Tech Time
4 35.00
140.00
Total
490.00
2.0
P-209
Crushed Aggregate Base Course
2.1
P-209
Unit Weight of Aggregate
ASTM C-29
1
45.00
45.00
2.2
P-209
Soundness
ASTM C-88
1
175.00
175.00
2.3
P-209
Material Finer Than # 200 Sieve
ASTM C-117
1
25.00
25.00
2.4
P-209
Los Angeles Abrasion
ASTM C-131
1.
150.00
150.00
2.5
P-209
Sieve Analysis
ASTM C-136
5
35.00
175.00
2.6
P-209
Moisture Densities
ASTM D-698
1.
80.00
80.00
2.7
P-209
Density of Soil and Soil Aggregate In-
ASTM D-2922
3
22.00
66.00
Place by Nuclear Method (min of 3)
2.8
P-209
Liquid Limit, Plastic Limit and
ASTM D4318
1
45.00
45.00
•
Plasticity Index of Soil
Mobilization, Mileage, & Tech Time
6
35.00
210.00
Total
971.00
3.0
P-210
Caliche Base Course
3.1
P-210
Sieve Analysis
ASTM C-136
1
35.00
35.00
3.2
P-210
Moisture Density Relations
ASTM D-698
1
80.00
80.00
3.3
P-210
Density of Soil by Sand Cone Method
ASTM D-1556
2
45.00
90.00
3.4
P-210
Liquid Limit, Plasticity Index
ASTM D-4318
1
45.00
45.00
Mobilization, Mileage, & Tech Time
4
35.00
140.00
Total
390.00
4.0
P-501
Portland Cement Concrete
Pavement
4.1
P-501
Making Curing Concrete Test
ASTM C-31
280
20.00
5,600.00
Specimen
4.2
P-501
Testing for Flexural Strength of
ASTM C-78
280
5.00
1,400.00
Concrete
4.3
P-501
Los Angeles Abrasion
ASTM C-131
1
150.00
150.00
4.4
P-501
Sieve Analysis
ASTM C-136
1
35.00
35.00
4.5
P-501
Unit Weight of Concrete
ASTM C-138
1
40.00
40.00
4.6
P-501
Test for Slump of Portland Cement
ASTM C-143
160
10.00
1,600.00
Mr. Moody
August 28, 1997
Page 11 of 11
Lubbock International Airport: Reconstruct Runway 17R-35L Keel
Alternate 5
NO. ITEM DESCRIPTION OF TEST STANDARD QTY UNIT TOTAL
NO.
4.7 P-501 Test for Air Content of Freshly Mix ASTM C-231 160 15.00 2,400.00
Concrete by the Pressure
4.8 P-501 Test Method for Flat or Elongated ASTM D-4791 1 40.00 40.00
Particles in Coarse Aggregate
Mobilization, Mileage, & Tech Time 160 35.00 5,600.00
Total 16,865.00
5.0
TxDOT
Hot Mix Asphaltic Concrete
TxDOT Tyne
5.1
TxDOT
Compacting Test Specimens
Tex 206F
6
30.00
180.00
5.2
TxDOT
Sieve Analysis
Tex 201F
8
35.00
280.00
5.3
TxDOT
Theoretical Maximum Specific
Tex 227F
8
50.00
400.00
Gravity of Bituminous
5.4
TxDOT
Vacuum Extraction
Tex 21 OF
8
65.00
520.00
5.5
TxDOT
Bulk Specific Gravity of Compacted
Tex 207F
6
30.00
180.00
Bituminous
5.6
TxDOT
Stability and Flow
6
30.00
180.00
Mobilization, Mileage, & Tech Time
6
35.00
210.00
'
Total
1,950.00
6.0
Miscellaneous -
6.1
Mileage Charge
N/C
6.2
Technician Time
80
35.00
2,800.00
6.3
Engineer
40
65.00
2,600.00
Total
5,400.00
Sub Total
26,066.00
Note:. The number of test quoted above is estimated based on the project specification. The total
number of tests actually performed may vary during construction phase and shall be prorated
accordingly.
TERRA ENGINEERS, INC.
ATTACHMENT "AMD 1-V
1998 FEE SCHEDULE
1998 FEE SCHEDULE
Delta Airport Consultants, Inc.
Date: July 15, 1997
1998
Billing
Item — -, Rate
Work Hours Billing Rates (with overhead)
Senior Project Manager
$99
Project Manager
$75
Project Engineer or Planner
$48
Technician
$39
Field Representative
$43
Clerical
$36
Direct Nonsalary Expenses
Automobile (per mile) $0.30
Piper Aztec (per flight hour) $70
Cessna 206 (per flight hour) $55
Cessna 172 (per flight hour) $25
Per Diem - Res Project Rep Federal Gov. guidelines
Long term - meals & lodging (per cal day)
Airline, Rental Car, Charter, etc. Direct
• Printing Direct
Advertisement Direct
Meals, Lodging, etc. (short term) _ Direct
Miscellaneous Direct
Subcontracted Services Direct
Delta Profit Fixed Fee
Notes:
1. Billing rates for future years will be increased by 4 % annually.
2. Work hours rates include three (3) year average labor overhead and general and administrative
overhead per FAA AC 150/5100-14C, paragraph 4-8 at 170.8 %.
3. Billing rates based on estimated 1998 salaries (i.e. 1997 salaries plus inflation).
FEESCHED.098