HomeMy WebLinkAboutResolution - 062366C - Street Improvements - Kerr Construction Co - 53Rd Street - 06_23_1966 RESOLUTION
RESOLUTION ACCEPTING IMPROVEMENTS ON A PORTION OF A STREET AS LISTED BELOW:
WHEREAS, the City of Lubbock passed a resolution on April 14, 1966 author-
izing the construction of street improvements by Kerr Construction Company on a
portion of the following street:
53rd Street from its intersection with a line 16 feet West of the West Property
Line of Quaker Avenue to its intersection with a line 13 feet East of the East
Property Line of Raleigh Avenue known and designated as Unit Number 2156.
AND WHEREAS, the improvements upon the said portion of the abovementioned
street have been inspected and found to have been constructed according to the
approved plans and specifications.
THEREFORE$ BE IT RESOLVED BY THE CITY OF LUBBOCK, TEXAS
I.
That the improvements on said portion of the abovementioned street be,
and the same are hereby accepted and the City Engineer be and he is hereby
authorized to direct the payment of the City' s share and release escrow money.
—� II.
This resolution shall take effect and be in force after its passage.
PASSED AND APPROVED THIS 23RD D 966.
bF;
W. D. Rog Jr. , or
ATTES .:
L Xenia Lowe; Cit , Seczetary
APPRO
ue1 W.,,Wahli~-C t Etiginee
A�ppunvFn': .. ., ., ��'
Fred O. Senter, Jr. , Cit torney
i
H
. '211
POrter 2-6411
P. O. Box 2000
LUBBOCK . TEXAS 79408
June 23, 1966
Honorable Mayor and City Council
Lubbock, Texas
Gentlemen:
I have examined the paving improvements constructed by Kerr
Construction Company, paving contractor, as authorized by a resolution
passed on April 14, 1966 and find the improvements on 53rd Street
from Quaker Avenue to Raleigh Avenue as listed on the final estimate
sheet to have been completed in accordance with the plans and specifica-
tions and recommend that you accept the improvements on said street
authorizing payment to the contractor the amount shown on the attached
consolidated final estimate sheet as due them by the City of Lubbock.
Yo very V
amuel W. ahl
City Engineer
t
s
CONSOLIDATED FINAL ESTIMATE
GWO 2897
Accepted June 23, 1966
QUANTITIES
S.Y.
Unit & Paving L.F.
Sub-Unit Location 6" Base C & G
2156 53rd Street from 13' E. of the 1976.89 1112,00
EPL of Raleigh Avenue to 16' W.
of the WPL of Quaker Avenue
COST'ESTIMATE
1976.89 S.Y. Paving 6" Base @ $1.65 $ 3,261.87
1112.00 L.F. Curb & Gutter @ $1.55 1,723.60
CONTRACT COST $ 4,985.47
COST DISTRIBUTION
Property City to
Unit & Contract Owner Contr4ptor
Sub-Unit Cost Cost NOW
2156 4,985.47 4,711.27 274.20