RESOLUTION
�.
RESOLUTION ACCEPTING IMPROVEMENTS ON A PORTION OF A STREET AS LISTED BELOW:
WHEREAS, in conformance with the paving requirement provisions of City
Ordinance 1331, the subdivider of Lot 1, Block 5, Burlington Industrial Addition #2
made arrangements with Kerr Construction Company for the construction of paving
improvements on certain street dedicated in said subdivision under the provisions of
said Ordinance prior to the recording of the subdivision plat of Lot 1, Block 5,
Burlington Industrial Addition including the following street:
East 46th Street from the East line of Lot 1, Block 40, Suburban Homes Addition to
275 feet East of the East Property Line of Lot 1, Block 40, Suburban Homes Addition
known and designated as New Subdivision Unit Number 1571
AND WHEREAS, the construction of the above improvements on the above-
mentioned street was performed under the supervision of the City Engineer, and said
improvements have been completed and have been inspected and found to have been
constructed in accordance with City specifications and in accordance with the
provisions of City Ordinance 1331.
THEREFORE, BE IT RESOLVED BY THE CITY OF LUBBOCK, TEXAS.
I.
That the improvements on said portions of the abovementioned street be and
the same are hereby accepted and the City Engineer be and he is hereby authorized to
,r- direct the payment of the City' s portion of the cost and to release escrow money.
II.
This resolution shall take effect and be in force from and after its
passage.
PASSED AND APPROVED THIS 12TH DAY OF AUG ST, 1965.
W. E'. Ail d'drson,�,Mayor==Pro Tem
ATTEST•
Lav nia Lowe, Ci Secretary
AP OVED:^^
/J✓
J hn T. H//////ickerson, "City Engineer
APPR VED:
Fred 0. Senter,Jr. , Ci ttorftey
�,gg6
1
CONSOLIDATED FINAL ESTIMATE
BURLINGTON INDUSTRIAL ADD. #2
LOT 1, BLOCK 5
Accepted August 12, 1965
QUANTITIES
S.Y.
Unit & Paving L.F.
Sub-Unit Location 6" Base C & G
NS 1571 E. 46th St. from the E. Line of Lot 1, 1466.67 550.00
Block 40, Suburban Homes Add. to
275' E. of the E. Line of said Lot 1
COST ESTIMATE
1466.67 S.Y. Paving @ $1.65 $ 2,420.01
550.00 L.F. C & G @ $1.55 852.50
$ 3,272.51
COST DISTRIBUTION
Escrow
Unit & Contract to be
Sub-Unit Cost Released
NS 1571 $ 3,272.51 $ 3,272.51
City of Lubbock
POrter 3-3491
916 Texas Avenue
Lubbock, Texas
August 12, 1965
Honorable Mayor and City Council
Lubbock, Texas
Gentlemen:
I have examined the paving improvements constructed by Kerr
Construction Company, paving contractor, under their contract with the
subdividers of Lot 1, Block 5, Burlington Industrial Addition #2,
and find the improvements on East 46th Street from 660' West of Globe
Avenue to 385' West of Globe Avenue as listed on the final estimate
sheet to have been completed in accordance with the plans and
specifications and recommend that you accept the improvements on said
streets and/or avenues, authorizing payment to the contractor the amount
shown on the attached consolidated final estimate sheet as due them by
the City of Lubbock.
Yours very truly,
ohn T. Hickerson
City Engineer