HomeMy WebLinkAboutResolution - 1873 - Authorize Services - Wilson Surveying Company - Quirt Ave Overpass Project - 11_15_1984M
Resolution #1873
November 15, 1984
Agenda Item #11
JWF:rm
RESOLUTION
BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF LUBBOCK:
Section 1. That the City of Lubbock has received a proposal addressed
to its Mayor and City Council for professional engineering services in the
form of engineering land surveying services to be done by Wilson Surveying
Co., Inca in connection with the 34th street and Quirt Avenue Overpass
Construction Project, to be accomplished for an approximate estimated total
cost of $13,023.00 adjusted to the actual cost for the work in line with
the rates for services as set forth in said proposal, a copy of which
proposal is attached hereto and made a part hereof as Exhibit A.
Section 2. The City Engineer, at his sole discretion, may allow the
Resident Project Representative to notify and request engineering land
survey services from Wilson Surveying Co., Inc. as the need of such service
is required to serve the best interest of the City of Lubbock.
Passed this 15th day of November 9 19 84
ATTESTr
Ranet Boyd, City Secretary
APPROVED AS TO CONTENT:
APPROVED AS TO FORM:
V op� .
J. W r h Fullingim, Assistant City
Attor ey
No Text
PARKHILL, SMITH & COOPER, INC.
�S� - ENGINEERS • ARCHITECTS PLANNERS
LUBBOCK ELPASO
October 12, 1984
Mr. Jim Bertram
Assistant City Manager
City of Lubbock
P.O. Box 2000
Lubbock, Texas 79457
Re: City of Lubbock
Quirt Avenue Overpass
Dear Mr. Bertram: .
We are pleased to advise you that the resident project representative we
are planning to assign to the referenced project is Mr. Robert J. Field.
Mr. Field has been involved in the heavy construction industry for more
than thirty years. Mr. Field has served as resident project represen-
tative, survey party chief, estimator and construction superintendent on
numerous construction projects involving the construction of bridges, high-
ways, streets, drains, sewers, reservoirs, water and wastewater improve-
ments, airports and dams. Mr. Field's experience includes work in
Massachusetts, Maine, New York, Illinois and Texas. Mr. Field was employed
by Parkhill, Smith & Cooper, Inc. in April, 1982 and has served as resi-
dent project representative on various water, wastewater, street and air-
port construction projects in Lubbock and the surrounding area. Mr.
Field's experience in construction of highway bridges and other heavy
construction projects qualifies him to serve in the capacity of resident
project representative on the Quirt Avenue Overpass, coupled with periodic
site visits by a representative of the bridge design division of
Henningson, Durham & Richardson.
We also wish to advise you that we plan to use Wilson Surveying Co. for
construction surveying needs. The construction contract requires the
Contractor to furnish all surveys necessary to provide horizontal and ver-
tical lines and grades to construct the work. Any construction period sur-
veys performed by Wilson Surveying Co. for the City will be authorized
through our office, only for "spot-checking" the accuracy of staking and
construction performed by the Contractor.
The testing laboratory we plan to use is Terra Testing, Inc. The lab will
only test materials delivered to the site and report results of material
tests required to insure compliance with the project specifications. The
construction contract provides for payment for all required preconstruction
tests and all failing construction tests by the Contractor.
4010 AVENUE R • LUBBOCK, TEXAS 29412 • PHONE 806-747-016I
ATCHESON. CARTWRIGHT 1-1 ASSOCIATES - MEMBERS A.I.A. . AFFILIATES
Mr. Jim Bertram
Page 2
October 12, 1984
We have worked with both Wilson Surveying Co. and Terra Testing, Inc. on
numerous construction projects for several years and it is our opinion that
they have the resources to adequately perform the work required.
We trust we have adequately addressed your needs and we stand available to
provide any additional information you may require.
Sincerely,
PARKHILL, SMITH & COOPER, INC.
By .�li•r.�s. /S G�,��.� j_.,�
TerryiG. Bilderback, F.E.
TGB/djb
me: Mr. Larry Hertel
Mr. Eduardo Ugarte