HomeMy WebLinkAboutResolution - 1719 - Accept Water & Sewer Improvements- Panhandle Construction- Tract F, KG Addition - 06_14_1984RESOLUTION 1719 - 6/14/84
PPROT.UTTON
RESOLUTION ACCEPTING WATER AND SEWER SYSTEM IMPROVEMENTS FOR TRACT
F, KING'S GATE ADDITION.
WHEREAS, the developer of Tract F, King's Gate Addition have complied
with the provision of the City of Lubbock Code, Chapter 28, Article IV,
by providing the water and sewer improvements for said addition in accor-
dance with paragraph 156 of said Chapter 28, and
WHEREAS, the total utility cost to the developer is $15,622.81 with the
improvements constructed by Panhandle Construction Co. having a value of
$14,690.70 as determined by the unit prices established by said Chapter 28,
and $932.11 cash paid to the City, with H. A. Sessions, the developer to
receive a refund of $15,622.81 in accordance with Chapter 28 of the Code
of the City of Lubbock and
WHEREAS, the construction of the said water and sewer improvements was
performed under the supervision of the Water Utilities Engineer and completed
in accordance with the City of Lubbock's plans and specifications,
NOW THEREFORE BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF,LUBBOCK:
1. That the improvements be and the same are hereby accepted as an
integral part of the water and sewer system of the City of Lubbock.
2. That the refundable cost in the amount of $15,622.81 be made in
accordance with said Chapter 28.
3. This resolution shall take effect and be in force from and after
its passage.
PASSED AND APPROVED THIS 14th
AT ST:
Evelyn Gaf ga, tity S r r
APPROVED AS CONTENT.
Wi or D. Watson, Chief Water
Util ies Engineer
APPROVED AS TO FORM:
ZGL+,.
ty Attorney
DAY Jwre84.
�r