HomeMy WebLinkAboutResolution - 071163F - Street Improvements - Kerr Construction Co - Mackenzie Terrace Addition - 07_11_1963 ` 4
t
RESOLUTION Q
RESOLUTION ACCEPTING IMPROVEMENTS ON PORTIONS OF STREETS AND/OR
AVENUES AS LISTED BELOW:
WHEREAS, in conformance with the paving requirement provisions of
City Ordinance 1331, the subdivider of Mackenzie Terrace Addition, made
3 arrangements with Kerr Construction Company 'for the construction of paving
improvements on certain streets dedicated in said subdivision under 6e
provisions of said Ordinance prior to the recording of the subdivision plat of
Mackenzie Terrace, Lot 4, Tract D, including the following streets:
East 5th Street from its intersection with the East Lip Line of Quirt:Avenue
to its intersection with a line 38 feet West of the West Property Line of
Redbud Avenue, known and designated as New Subdivision Unit Number 1245.
Redbud Avenue from its intersection with a line 3 feet South of the South
Property Line of the alley North of 5th Street to its intersection with a line
38 feet West of the West Property Line of Redbud Avenue, known and designated a
New Subdivision Unit Number 1246.
East one-half of Quirt Avenue (curb and gutter only) from its intersection
with a line 3 feet South of the South Property Line of the alley south of 4th
Street to its intersection with a line 13 feet South of the South Property Line
of East 5th Street, known and designated as New Subdivision Unit Number 1251.
AND WHEREAS, the construction of the above improvements on the above
mentioned streets was performed under the supervision of the City Engineer, and
said improvements have been completed and have been inspected and found to have
been constructed in accordance with city specifications and in accordance with
the provisions of City Ordinance 1331.
THEREFORE, BE IT RESOLVED BY THE CITY OF LUBBOCK, TEXAS.
I.
That the improvements on said portions of the abovementionedlstreets
be and the same are hereby accepted and the City Engineer be and he is hereby
authorized to direct the payment of the city's portion of the cost.
II.
This resolution shall take effect and be in force from and after its
passage.
PASSED AND APPROVED THIS 11TH DAY OF JULY, 1963.
ck F. Strong, Mayor
ATTEST
Wu
Cl
Lavgfiia Lowe, City Secretary
APPROVED:
t J hn T. Hickerson, City Engineer
APPROVED.-
Fred O. Senter, Jr., Cit torney
r
City of Lubbock
POrter 3-3491
,v
916 Texas Avenue
Lubbock, Texas
July 11, 1963
Honorable Mayor and City Commission
Lubbock, Texas
Gentlemen:
I have examined the paving improvements constructed by Kerr
Construction Company, paving contractor, under their contract with the
subdividers of Mackenzie Terrace Addition, Lot 4, Tract D, and find the
improvements on East 5th Street and Redbud Avenue as listed on the final
estimate sheet to have been completed in accordance with the plans and
specifications and recommend that you accept the improvements on said
streets and/or avenues, authorizing payment to the contractor the amount
shown on the attached consolidated final estimate sheet as due them by
the City of Lubbock.
Yours very truly,
ohm
kT. Hickerson
o
CONSOLIMTED FINAL ESTIMATE
MACXENZIE TERRACE ADDITION
Accepted July 11, 1963
QUANTITIES
S.Y.
Unit & S.Y. L.F. Alley
Sub-Unit Location Paving C.& G Return
N.S. 1245 E. 5th St. from the ELL of Quirt Ave.
to 38' West of the W.P,L. of Redbud
Ave. 1,302.60 737.70
N.S. 1246 Redbud Ave. from 3 t South of the
alley North of 5th St. to 38' West
of the WPL of Redbud Ave. 701.01 394.33
N.S. 1251 E. 1/2 of Quirt Ave. (curb and gutter
only) from 31 South of the alley South
of 4th St, to 131 South of the SPL of
E. 5th St. 141.29 9,86
TOTALS 20003,61 1*273.32 9.86
COST ESTIMATE
2,003.61 S.Y. Paving @ $1.45 $ 2,905.23
1,273.32 L.F. Curb& Gutter @ $1.45 1,846.31
9.86 S.Y. Alley Return @ $5.00 49.30
CONTRACT COST $ 4,800.84
COST DISTRIBUTION
Unit & Contract Property
Sub-Unit Cost Owner Cost
N.S. 1245 $ 2,958.44 2,958.44
N.S. 1246 1,588.24 1,588:24
N.S. 1251 254.16 254.16
$ 4,800.84 4,800.84