RESOLUTION
RESOLUTION 1495 - 9/22/83
See: Reso. 923, 9124/81; Bid 641
BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF LUBBOCK:
THAT the Mayor of the City of Lubbock BE and is hereby authorized and
directed to execute for and on behalf of the City of Lubbock Change Order
No. 7 to a contract previously entered into by and between said City and
Jack Cooper Construction Co., Inc. relating to improvements to Municipal
Water Treatment Plant and Pump Station No. 9, attached herewith which shall
be spread upon the minutes of the Council and as spread upon the minutes of
this Council shall constitute and be a part of this Resolution as if fully
copied herein in detail.
Passed by the City Council this 22nd day of September , 1983.
ALAN HENRY.4 OR
' ATTEST:
'velyn Ga fga, City gecftt y-Treasurer
APPROVED AS TO CONTENT:
tlol-
Guy Wil on, Water Utilities Engineer
APPROVED A TO FORM:
dZ
J. WortV FjbIlingimp Assistant City Att10
19
RESOLUTION 1495 - 9/22/83
�N y^cFrPFTP,Ry- R .;IcI
�%19�3 CHANGE ORDER #7
Improvements to Municipal
Water Treatment Plant and -
Pump Station No. 9
Lubbock, Texas
September 8, 1983
TO: Jack Cooper Construction Co., Inc.
P.O. Box 1153
Temple, Texas 76503-1153
General description of work included in original contract: The
construction of six rapid sand filters and a 15 mgd pump station at the
Municipal Water Treatment Plant, construction of 25 mgd Pump Station No. 9
and chlorination and electrical control building, and other related items.
Original Amount of Contract . . . . . $3,118,176:00
Change Order No. 1 . . . . . . . . . . . -0-
Change Order No. 2 . . . . . 4,739.00
Change Order No. 3 . . . . . . . 15,140.00
Change Order No. 4 . . . . . . . . . . 2,600.00
Change Order No. 5 . . . . . . . . . . . 9,436.00
Change Order No. 6 . . . . . 14,140.00
Change Order No. 7 . . . . . o 3,512.34
Adjusted Contrace Amount . . $3,167,743.34
Adjustment in Construction Time . . . None
WHEREAS, it is desirable to make changes in the work to be constructed
under this project.
THIS AGREEMENT WITNESSETH: In consideration of the mutual advantage
gained, the Owner and the Contractor agree to the changes indicated below
and further agree that the amount of the contract shall be adjusted by the
amount shown above.
1. Modify software for filter control
system to provide hard copy output
of all output shown on the.CRT
screen during the backwash
sequence exclusive of timer count-
d owns .
Add. . . . . . . . . . . . . . . .
CHANGE ORDER NO. 7
Page 1 of 2
$ 456.00
2. Install pushbutton switches, pilot
lights and appurtenances in,the
motor control centers in the Pump
Station No. 9 control room to
control four (4) motor operated cone
valves on pump discharges at Pump
Station No. ' 9.
Add .. . . . . . . . . . . . . . . . 2,007.54
3. Install analog flow indicators for
each of the four (4) pumps at Pump
Station No. 9 in the existing sum-
mator cabinet.
Add. . . . . . . . . . . . . . . . 1,048.80
The aforementioned changes and work affected thereby, are subject to
all contract stipulations and covenants.
The Owner and the Contractor agree that there will not be an adjust-
ment to the time allowed for completion of the project for the above listed
changes.
IN WITNESS THEREOF, the Owner and the Contractor have hereto set their
hand this the 22nd day of September , 1983.
RECOMMENDED: PARKHILL, SMITH & COOPER, INC., Consulting Engineers
By� Proj. Engineer, 9 P 1983
APPROVED: JACK COOPER CONSTRUCTION CO., INC., Contractor
By _1983
APPROVED: CITY OF LUBBOCK, TEXAS, Owner
ATTEST:
CHANGE ORDER NO. 7
Page 2 of 2
9/22/ 1983