RES OLUT ION
RESOLUTION ACCEPTING IMPROVEMENTS ON PORTIONS OF STREETS, AND/OR
AVENUES AS LISTED BELOW.
WHEREAS, the City of Lubbock heretofore passed various street improve-
ment ordinances and resolutions and entered into contract with Kerr Paving
Company, Inc. (G.W.O. 2660) for the making and construction of street improve-
ments on portions of numerous streets and/or avenues in said City including
among others the following:
Paving adjustment in 3rd Street from 8 feet east of the east property line of
Elgin Avenue to 198 feet west of the west property line of Elgin Avenue, known
and designated as Sub-Unit 1 of Unit 2085.
Paving adjustment required in the intersection of 3rd Street and Detroit Avenue
for the closing of 3rd Street between Detroit and Elgin Avenues, known and
designated as Sub-Unit 2 of Unit 2085.
AND WHEREAS, the improvements upon the said portions of the above-
mentioned streets and/or avenues, have been inspected and found to have been
constructed in accordance with terms of said contract (G.W.O. 2660) .
THEREFORE, BE IT RESOLVED BY THE CITY OF LUBBOCK, TEXAS:
I.
That the improvements on said portions of the abovementioned streets,
and/or avenues be and the same are hereby accepted, and the City Engineer be
and he is hereby authorized to direct payment of the City's portion of the cost
II.
This resolution shall take effect and be in force from and after its
passage.
1
PASSED AND APPROVED THIS 9TH Y AUGUST, 19�r2-
/ ack F. Strong, Mayor
ATTES / ...
)
Lave a Lowe, Ci Secretary
APP OVED:
z k) '
T. Hickerson, City Engineer
APPROVED:
w
Fred 0. Senter, Jr., C' Attorney
0(0� CITY OF LUBBOCK
t� y
CK.'�
TEXAS
August 9, 1962
Honorable Mayor and City Commission
Lubbock, Texas
Gentlemen:
I have examined the paving improvements constructed by Kerr
Paving Company, Inc., paving contractor, under their contract with
the developer of Blocks 10 & 11 of Maddox Addition and find the
improvements on 3rd Street and Elgin Avenue intersection as listed on
the final estimate sheet to have been completed in accordance with the
plans and specifications and recommend that you accept the improvements
on said streets and/or avenues, authorizing payment to the contractor ,
the amount shown on the attached consolidated final estimate sheet as
due them by the City of Lubbock.
Y urs very truly,
ohn T. Hickerson
City Engineer
g CONSOLIDATED FINAL ESTIMATE
ADJUSTMENTS ON 3RD STREET FOR THE CLOSING OF 3RD STREET
ACCEPTED AS PART OF G.W.O. 2660
ACCEPTED AUGUST 9, 1962
QUANTITIES REMOVAL(NOT CONSTRUCTED)
S.Y. S.Y. 4" S.Y.
Unit & S.Y. L.F. Valley Concrete S.Y. L.F. Valley
Sub-Unit Location Paving C & G Gutter Driveway Paving C & G Gutter
2085-1 Paving adjustment in 3rd 497.03 270.43 23.76 8.33 73.78 47.12 15,45
St. from 81 E. of the
E.P.L. of Elgin Ave. to
198' W. of the W.P.L. of
Elgin Ave.
2085-2 Paving adjustment re- 18.67 56.00 75.31 31,42
quired in the intersec-
tion of 3rd St. and
Detroit Ave. for closing
3rd St. between Detroit
& Elgin Avenues
TOTALS 515.70 326.43 23.76 8.33 149.09 78.54 15.45
COST DISTRIBUTION
Property
Unit & Contract Owner
Sub-Unit Cost Cost
2085-1 $ 1,781.56 $ 1, 781.56
2085-2 193.63 193.63
TOTALS $ 1,975.19 $ 1, 975.19
COST ESTIMATE
515.70 S.Y. Paving @ 1.90 979.83
326.43 L.F. Curb & Gutter @ 2.00 652.86
23.76 S.Y. Valley Gutter @ 7.00 166.32
8.33 S.Y. 4" Concrete Drives @ 5.00 41.65
QUANTITIES REMOVED
149.09 S.Y. Paving @ 0.30 44.73
78.54 L.F. Curb & Gutter @ 0.75 58.90
15.45 S.Y. Valley Gutter @ 2.00 30.90 oe
CONTRACT COST $ 1,975.19 '
4�
a�
�o