HomeMy WebLinkAboutResolution - 102661H - Street Improvements - Pioneer Pavers Inc - GWO 10199 - 10_26_1961 • RESOLUTION
a
RESOLUTIONS ACCEPTING MPROVE111EAiTS ON PORTIONS OF ALLEYS, STREETS, AND/
OR ;AVENUES AS LISTED BELOW AND ORDERING THE ISSUANCE OF CERTIFICATES IN EVI _
DENCE OF ASSESSMENTS LEVIED.
WHEREAS, the City of Lubbock heretofore passed various street improve-
ment ordinances and resolutions and. entered into contract with Pioneer Pavers
Inc. (G.W.O. 10199) for the making and conttruction of street and/or alley im-
provements on portions of numerous alleys, streets, and/or avenues in said
City including among others the following:
The South-2 of 53rd Street from its intersection with the west line of lot 254
Oakwood Addition to its intersection with the east line of lot 251 Oakwood
Addition known and designated as part of Sub--unit Number 4 Of Unit Number
2017.
AND WHIEREAS, the improvements upon the said portions of the abovemention
ed alleys, streets and/or avenues, have been inspected and found to have been
donstruc-ted.in accordance with terms of said contract (G.W.O. 10199).
THEREFORE, BE IT RESOLVED BY THE CITY OF LUBBOCK, TEKAS:
I.
That the improvements on said portions of the abovementioned alleys,
streets, and/or avenues be and the same are hereby accepted, and the City
Engineer be and he is hereby authorized to direct payment; of the Cityts por-
tion of the cost.
II.
This resolution shall take effect and be in force from and after its
passage.
PASSED AND APPROVED THIS 26th DAY OF October 1961.
David C. Casey, Mayors
ATTE �!
Lakenia Lowe, C' y Secretary
R E
D:/'7
�
Z
ohn T. Hickerson, City Enginee
V
Fred 0. Senter, Jr. , City rney
. � CITY OF LUBB13CK
TEXAS
October 26, 1961
Honorable Mayor and City Commission
Lubbock, Texas
Gentlemen:
I have examined the paving improvements constructed by Pioneer
Pavers, Inc., paving contractor, under their contract dated April 28, 1960,
designated as G. T.O. 10199 and find the improvements on South one-half of
53rd Street as listed on the final estimate sheet to have been completed
in accordance with the plans and specifications and recommend that you
accept the improvements on said streets and/or avenues, authorizing payment
to the contractor the amount shown on the attached consolidated final
estimate sheet as due them by the City of Lubbock.
Yours very
truly,
14John T. Hickerson
City Engineer
V
4
CONSOLIDATED FINAL ESTIMATE
Oakwood Addition
Accepted October 26, 1961
QUANTITIES
Unit & S.Y
Sub-Unit Location Paving
Part of
2017-4 S/2 53rd St. from W. lot line 390.04
of Lot 254 to E. lot line of
Lot 251 Oakwood Addition.
Total 390.04
COST ESTIHATE
390.04 S.Y. Paving 1.67 $651.37
CONTRACT COST $651.37
COST DISTRIBUTION
Escrow
Unit & Contract To be
Sub-Unit Cost Released
Part of 2017-4 $651.37 $651.37
Total $651.37 $651.37
i
I