HomeMy WebLinkAboutResolution - 111055J - Resolution Missing. Paving Improvements. West Texas Construction. - 11/10/1955CITY OF LUBBOCK 1110.95f
TEXAS
November 10, 1955
Honorable Mayor and City Ccmmdesion
Labbock, Texas
Gentlemen:
I have examined the paving improvements constructed by Kest Texas
Construction, Incorporated, Paving Contractors, under their contract
with the subdivider of McCulloch Addition No. 9 in accordance with
New Subdivision Ordinance No. 1331 and find the improvements on the
West one—half of Quaker Avenue designated as New $ubdivision Unit
No. 195, as listed on the attached final estimate sheet to have been
completed in accordance with plans and specifications and recomend
the payment to the contractor the amount shown on the attached
consolidated final estimate sheet as being due him from the City, of
Lubbbak.
EVPswm
Very truy yours,
John T. Hickerson
City Engineer
UAgT
Unit Not Location S.Y. S.Y. L.F. S.Y.
Paving Subg.Prep Curb.& Grutt. Conc.Alley
Slab
N-S 195 wj Quaker Ave. - 16 ft. S.of
SPL„42nd St. to 2.5 ft. S. of
Alley S. of 42nd Street
Totals 292.22 347.92 149.50 14.,17
CAST ESTIiTE
292,22 S.Y. Paving (Surf & Base) a $1.15 $336.05
347.92 S.Y. Subgrade Preparation 0 0;20 = 69.58
1.49.50 L.F, Concrete Curb & Gutter 0 1.50 - 224.25
14.17 S.Y. Concrete Alley Return 0.3.75 = 53,
Total Contract Cast 683.02
1.0% Engineering
Total Cost
751.32
COST DISTRIBUTION
Subdividers City to Contract Credit Engr.
Unit No. Total C2g& C28t Total CLtZ Cost Contractor- Coal D
N-S 195 6 8 8 8 8
Totals $751.32 $544.94 $206.38 $138.08 683.02 68.30