Loading...
HomeMy WebLinkAboutResolution - 2022-R0219 - Change Order No. 3 Contract 15325 with Red River Construction 5.10.19Resolution No. 2022-RO219 Item No. 7.11 May 10, 2022 RESOLUTION BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF LUBBOCK: THAT the Mayor of the City of Lubbock is hereby authorized and directed to execute for and on behalf of the City of Lubbock, Change Order No. 03 to that certain Contract No. 15325 by and between the City of Lubbock and Red River Construction for the Southeast Water Reclamation Project — Plant 3 Improvements, and related documents. Said Change Order No. 03 is attached hereto and incorporated in this resolution as if fully set forth herein and shall be included in the minutes of the City Council. Passed by the City Council on May 10, 2022 DANIEL M. POPE, MAYOR ATTEST: Reb a Garza, City Secre APPROVED AS TO CONTENT: Jesica achern, ASsis ity Manager APPROVED AS TO FORM: & h-"& K lli Leisure, Assistant City Attorney ccdocs/RES.Contract 15325 CO#3 - SEWRP Plant 3 04.21.22 Office of Purchasing and Contract Management Change Order Contract No: 15325 Contractor: Red River Construction Change Order No: 3 Contract Title: SEWRP — Plant 3 Improvements Project Bid/RFP No: 20-15325-CM Project No: 92444.9242.30000 "Change Order" means a written order to a Contractor, executed by the Owner, in accordance with the Contract authorizing an addition to, deletion from or adjustment or revision of the requirements of the Contract documents, or an adjustment to the compensation payable to the Contractor, or to the time for performance of the Contract and completion of the project, or a combination thereof; which does not alter the nature of project and is an integral part of the project objective. Adjustments to "Estimated Quantities" to a line time in a Unit Price Contract do not require a Change Order. All work that alters the nature of the construction or that is not an integral part of the project objective must be let out for public bid. Description of Change (alteration, deviation, addition, or deletion) caused by conditions encountered during conatrnetian net mvprpA t,., rt.p specifications and drawings of the project attached additional pages is necessary: Per attached backup material, this Change Order #2 includes the following items: Item 1) Coating of the 30-inch aeration basin influent pipe in the piping gallery at a cost of+$23,715.53. Item 2) Replacement of existing WAS check valve at a cost of+$10,208.33 and 2 additional days of construction time. Item 3) Pulling two new RAS pumps to unclog the impellers of unexpected material five times at a cost of+$28,060.82 and 7 additional days of construction time. Item 4) Additional pumping and cleaning of the two Plant 3 primary clarifiers at a cost of+$98,373.59 and 30 additional days of construction time. Item 5) Transport of two RAS pumps to Smith Pump Co. for examination, and subsequent repair at a cost of+$42,666.67. Item injection credit of -$100,000.00. Where the Change Order is negotiated, the Change Order must be f dly documented and itemized as to costs, including material quantities, material costs, taxes, insurance, employee benefits, other related costs, profit and overhead. Where certain unit prices are contained in the initial Contract, no deviations are allowed in computing negotiated change order costs. ITEMIZED COSTS MUST BE FULLY DOCUMENTED AND ATTACHED TO THIS FORM. ITEM DESCRIPTION AMOUNT A. ORIGINAL CONTRACT VALUE: $7,257,052.00 B. AMOUNT OF THIS CHANGE ORDER: Note: Council approval required if (+/-) $50,000 $103,024.94 COST CENTER 92444 1 ACCOUNT: 9242.30000 C. PERCENT OF CONTRACT VALUE THIS CHANGE ORDER /A 1.42% D. AMOUNT OF PREVIOUS CHANGE ORDERS: $699,977.03 E. TOTAL AMOUNT OF ALL CHANGE ORDERS +D $803,001.97 F. PERCENT OF CONTRACT OF ALL CHANGE ORDERS A : 25%maximum) 11.07% G. NEW CONTRACT AMOUNT A+E : $g 060 053.97 It is mutually agreed that the above dollar amount and the time extension, as applicable, as set forth in this Change Order constitutes full compensation to the Contractor for all costs, expenses and damages to the Contractor, whether direct, consequential or otherwise, in anyway incident to, or arising out of or resulting directly or indirectly, from the work performed or modified by the Contractor under this Change Order. This Change Order is not valid without the following signatures (please sign in order and rewrn 3 originals with the Contrad Cover Sheet to Pu mlra—s= and Contract MM ement d OM08/22 (1) Contractor Date ( Project Architect/Engineer Date (3) er's ntative *D&— (5) Capital Pro' t Manager Date 5/ 10/2022 Date Council Date: May 10, 2022 Agenda Item #: (8) C) Date Date —� Date 7.11 Resolution #: 2022-RO219 PUR-45 (Rev 08/2018) Engineers... Working Wonders With Water® April 8, 2022 Mr. Zoltan Fekete, P.E. Senior Engineer City of Lubbock, Texas 1314 Avenue K Lubbock, TX 79401 Subject: SEWRP Plant 3 Improvements Project Change Order #3 Dear Mr. Fekete: Attached with this letter is documentation for Change Order #3. Time Item Description Cost Impact Impact Status 1 Coating of the 30-inch aeration basin influent pipe in +$23,715.53 No Time Recommended by the piping gallery Carollo 2 Replacement of existing WAS check valve +$10,208.33 2 days Recommended by Carollo Pulling two new RAS pumps to unclog the impellers 3 of unexpected material five times, plus additional +$28,060.82 7 days Recommended by budget to pull the two pumps two more times (if Carollo needed) 4 Additional pumping and cleaning of the two Plant 3 +$g8,373.59 30 days Recommended by primary clarifiers Carollo 5 Transport of two RAS pumps to Smith Pump Co. for +$42 No Time Recommended as examination, and subsequent repair ,666.67 modified by Carollo 6 Credit for not epoxy injecting interior concrete -$100,000.00 No Time Recommended by surfaces of the existing secondary clarifiers Carollo Total Contract Impacts from CO #1 PCOs: +$103,024.94 +39 days Items recommended for inclusion with Change Order #3 are described in more detail as follows: Item 1 TCEQ 217 Subchapter M, §217.329 lists required color -coding for pipes in a wastewater treatment facility. The exposed 30-inch influent pipe for the three Plant 3 aeration basins is not painted the required color, and the WWTP has been cited by TCEQ for this in the past. WWTP staff has requested the pipe be painted the required color to meet the requirements of TCEQ 217, and to avoid future citations. 8900B.30I22-04-08_Fekete.d= 8911 Capital of Texas Highway North, Suite 2200, Austin, Texas 78759 P. 512.453, 5383 F. 512, 453, 0101 carollo.com Mr. Zoltan Fekete, P.E. Senior Engineer City of Lubbock, Texas April 8, 2022 Page 2 Red River Construction (RRC) has proposed $23,715.53 for their coatings subcontractor to coat the 30-inch diameter pipe. The Engineer and RPR have reviewed the request, and have found the cost to be in line with what would be expected. The following documents are attached to support Item 1: 1. Potential Change Order (PCO) #016 dated November 24, 2021 from Health Staffeld of RRC with the proposal and cost backup for the additional work. 2. PCO #016 Response from Jason Anderson of Carollo Engineers with the Engineer's response to the proposal. Item 2 During construction an existing WAS discharge line check valve was relocated from the east end of the aeration basin piping gallery to the west end of the gallery, along with an existing WAS pump. The check valve was later determined by WWTP staff to be in need of replacement. RRC proposed a cost of $10,208.33 and an additional 2 days of contract time to replace the check valve. The Engineer and RPR have reviewed the proposal, and have found the cost and effort to be in line with what would be expected, and also agree with the request for a 2-day contract time extension associated with this additional work. The following documents are attached to support Item 2: 1. PCO #017 dated February 17, 2022 from Health Staffeld of RRC with the proposal and cost backup for the additional work. 2. PCO #017 Response from Jason Anderson of Carollo Engineers with the Engineer's response to the proposal. Item 3 The Plant 3 Improvements Project includes new a pair of new return activated sludge (RAS) pumps associated with each secondary clarifier. The arrangement of the secondary clarifiers and RAS piping, along with the site constraints required the use of vertical turbine solids handling (VTSH) pumps. The new pumps are capable of passing a 3.6-inch spherical object. The pumps ran perfectly for approximately two months, but then began to experience issues with reduced flow, and ultimately one of the two pumps installed in Phase 1 construction experienced a stoppage. The pump was pulled and found to be completely clogged with long stringy fibrous material and trash, none of which should be found in RAS. It was later determined that the fine screens at the Headworks had not been functioning for some time, and flow was being bypassed to the coarse screen, allowing material that would not normally make it past the Headworks to end up in the primary clarifiers, aeration basins, secondary clarifiers, and ultimately, the RAS pump suction headers. RAS Pumps 3 and 4, as installed for Phase 1 construction, were pulled and sent to Smith Pump Company in Waco for disassembly and 8900B.30122-04-08_Fekete.dom carollo.com Mr. Zoltan Fekete, P.E. Senior Engineer City of Lubbock, Texas April 8, 2022 Page 3 evaluation. RAS Pumps 1 and 2 were installed in place of Pumps 3 and 4. In the weeks following, Pumps 1 and 2 continued to experience reduced flow, but now that it was understood what was the cause of the flow reduction the pumps would be pulled and cleaned, then reinstalled. This has been done a total of five times to date. RRC proposed a cost of $28,060.82 and an additional 7 days of contract time for pulling the pumps five times. RRC also provided a quote of $4,485.94 for each additional instance of pulling the pumps, which would be included in a future Change Order if needed. The Engineer and RPR have reviewed the proposal, and have found the cost and effort to be in line with what would be expected (with corrections to the totals as made by the Engineer), and also agree with the request for a 7-day contract time extension associated with this additional work. The following documents are attached to support Item 3: PCO #019 dated March 8 from Health Staffeld of RRC, and corrected by Carollo Engineers, with the proposal and cost backup for the additional work. 2. PCO #019 Response from Jason Anderson of Carollo Engineers with the Engineer's response to the proposal. Item 4 In relation to the issues experienced with trash and rags plugging the new RAS pumps, the Contractor was requested to prepare a proposal to dewater and clean out the existing Plant 3 primary clarifier distribution box, and the two primary clarifiers. Restoring the full capacity of the two primary clarifiers will help to prevent the problematic material from being passed on from the primary clarifiers, and creating further problems in the downstream systems. RRC proposed a cost of $98,373.59 and an additional 30 days of contract time for the additional work associated with cleaning the primary clarifiers and related structures. The Engineer and RPR have reviewed the proposal, and have found the cost and effort to be in line with what would be expected, and also agree with the request for a 30-day contract time extension associated with this additional work. The following documents are attached to support Item 4: 1. PCO #020 dated March 25, 2022 from Health Staffeld of RRC with the proposal and cost backup for the additional work. 2. PCO #020 Response from Jason Anderson of Carollo Engineers with the Engineer's response to the proposal. Item 5 As described in Item 3, RAS Pumps 3 and 4 were pulled and transported to Smith Pump Company in Waco. Smith Pump Company disassembled both pumps, and produced a condition assessment report, including recommendations for repair of the pumps. The motors were 8900B.30 122-04-08_Fekete.docx carollo.com Mr. Zoltan Fekete, P.E. Senior Engineer City of Lubbock, Texas April 8, 2022 Page 4 shipped separately from Waco to the Smith Pump Company motor shop in Dallas. The cost for shipping, examination, and repair quoted by Smith Pump Company is $36,020.83. RRC proposed a cost of $42,666.67 for the transportation, examination, repair work and reinstallation associated with RAS pumps 3 and 4. The proposal also requested a 30-day extension to the contract time. The Engineer and RPR have reviewed the proposal, and have found the cost and effort to be in line with what would be expected, but do not find a basis for requesting a 30-day contract time extension associated with this additional work. The following documents are attached to support Item 5: 1. PCO #021 dated March 6, 2022 from Health Staffeld of RRC with the proposal and cost backup for the additional work. 2. PCO #021 Response from Jason Anderson of Carollo Engineers with the Engineer's response to the proposal. Item 6 The Plant 3 Improvements Project specified the interior concrete surfaces of the existing concrete basins would require repair of cracks with epoxy injection. After dewatering the existing basins, the concrete was found to be in excellent condition. Because of the condition of the concrete, epoxy injection has been reconsidered, and a credit for epoxy injection was requested by the Owner. RRC proposes a credit of $100,000.00 for not performing epoxy injection of cracks on the interior concrete surfaces of the existing concrete basins. The Engineer and RPR have reviewed the proposal, and have found the credit to be in line with what would be expected. The following documents are attached to support Item 6: 1. PCO #022 dated March 6, 2022 from Health Staffeld of RRC with the proposal and cost backup for the additional work. 2. PCO #022 Response from Jason Anderson of Carollo Engineers with the Engineer's response to the proposal. 8900B.30122-04-OB_Fekete.docu carollo.com Mr. Zoltan Fekete, P.E. Senior Engineer City of Lubbock, Texas April 8, 2022 Page 5 The change in contract price associated with items 1 through 11 is summarized below: • Original contract price : $7,257,052.00 • Net increase in price of this change order: +$103,024.94 • Contract price with all approved change orders: $8,060,053.97 • Original contract time: 600 Days to Final Completion • Net increase of time with this change order: +39 days • Contract time with all approved change orders: 849 days to Final Completion After you have had a chance to review this information, we are available to discuss any questions or comments, at your convenience. Please contact, Jason Anderson, or myself with any questions. Thank you for the opportunity to provide construction phase services for the City of Lubbock. We look forward to continuing to work with you and City staff on this project through its successful completion. Sincerely, CAROLLO ENGINEERS, INC. W'. �. �1' Hani E. Michel, P.E. Project Manager JEAJea cc: Josh Kristinek, P.E. Mary Gonzales Mark Aaron Carpenter Jason Anderson, P.E. 8900B.30122.044 Fekete.docu carollo.com