THAT the Mayor of the City of Lubbock is hereby authorized and directed to execute for
and on behalf of the City of Lubbock, Change Order No.I to that certain Contract No. 11150 by
and between the City of Lubbock and Kimley-Horn and Associates, Inc., for 98th Street Paving
Improvements -University Avenue to US 87 -Supplemental Request per Bid #13 -11150 -TL, and
related documents. Said Change Order No. 1 is attached hereto and incorporated in this
resolution as if fully set forth herein and shall be included in the minutes of the City Council.
Passed by the City Council on February 26, 2015
GLg9/_/ROBtRTSON, MAYOR
ATTEST:
Garza, City
APPROVED AS TO CONTENT:
R.Keith Smith, P.E., Director of Public Works
APPROVED AS TO FORM:
RES.ChgOrd#I,Contract-Kimley-Hom and Assoc, Inc.
2.5.15
,
Apf5rL. /'
V
utyOtity.Atey
RES.ChgOrd#I,Contract-Kimley-Hom and Assoc, Inc.
2.5.15
Contract No: 11150
Change Order
BID/RFP No. 13 -11150 -TL
City of Lubbock
Purchasing and Contract Management
Change Order
Contractor: Kimley-Horn and Associates, Inc.
Contract Title: 98th Street Reconstruction - University Ave. to U.S. 87
Project Number. 92289
"Change Order" means a written order to a Contractor executed by the Owner in accordance with the contract authorizing an
addition to, deletion from, or adjustment or revision of the requirements of the contract documents, or an adjustment to the
compensation payable to Contractor, or to the time for performance of the contract and completion of the Project, or a
combination thereof, which does not alter the nature of the thing to be constructed and is an integral part of the project objective.
Adjustments to "Estimated Quantities" to a line item in a Unit Price contract do not require a Change Order. All work that alters
the nature of the thine to be constructed or that is not an integral part of the project obiective must be let out for public bid.
Description of change (alteration, deviation, addition, or deletion) caused by conditions encountered during construction
not covered by the specifications and drawings of the project (aaach additional pager ijnecessary):
Additional charges associated with acquiring Right-of-way for Drainage Easement. See
attached schedules.
2. Where the Change Order is negotiated, the Change Order must be fully documented and itemized as to costs, including material
quantities, material costs, taxes, insurance, employee benefits, other related costs, profit and overhead. Where certain unit prices
are contained in the initial contract no deviations are allowed in computing negotiated change order costs.
ITEMIZED COSTS MUST BE FULLY DOCUMENTED AND ATTACHED TO THIS FORM.
ITEM DESCRIPTION
A. ORIGINAL CONTRACT VALUE:
B. AMOUNT OF THIS CHANGE ORDER: Covecd approval required ijowr 325,000
COST CENTER: ACCOUNT:
C. PERCENT OF CONTRACT VALUE THIS CHANGE ORDER (B/A):
D. AMOUNT OF PREVIOUS CHANGE ORDERS:
E. TOTAL AMOUNT OF ALL CHANGE ORDERS (B+D):
F. PERCENT OF CONTRAC 7 OF ALL CHANGE ORDERS (E/A): 25% incmuae
or decor.
AMOUNT
$ 825,300
$17,1100
2.1 %
$0
$ 803,100
2.1 a/
G. NEW CONTRACT AMOUNT (A+E): $843,100
3. It is mutually agreed that the above dollar amount and the time extension, as applicable, as set forth in this Change Order constitutes
full compensation to the Contractor for all costs, expenses and damages to the Contractor, whether direct, consequential or otherwise,
in anyway incident to, or arising out of or resulting directly or indirectly; from the work performed or modified by the Contractor
under this Change Order.
This Change Order is not valid without the following signatures (please Bien in order and return 3 originals with Contract Cover Sheet to
Purchasing and Contract Management Department):
(1) CONTRACTOR Date (2) PROJECT ARCHI /ENGINEER Date
Approved as = Approved as to Form:
(3) WNER'S REPRESENTATIVE Date (4 f Y RN Date
s-u-js aLLX15
(5) CAPITAL PROJECTS MANAGER Date (6) PURL AS CONTRACT MANAGER Date
ange rde ov 515,000 require a Contra Cover Sheet and the jollowq t signal res:
CITY OF LUBBOCK A T
(7) MAYOR Date (8) CITY S CRFTARY Date
CouncA Date:ebruary 6, 2015 Agenda Item #: 6.6 Resolution #:2015-R 0057
Pl1R-45 (Rev 178012)
Kimley>Morn
January 16, 2015
Mr. Neil Welch, P.E.
City of Lubbock
1625 13'" Street
Lubbock, Texas 79401
RE: 98`x' Street Paving Improvements — University Avenue to US 87 — Supplemental Request
Dear Mr. Welch:
Our Design Team has almost completed the construction plans for Paving Improvements to 9811
Street, between University Avenue and US 87. However, there are a few items of new scope that
need to be added to the contract in order for us to complete the project. If these items can be added
to the contract, we expect the City of Lubbock Purchasing can advertised the project for bids within
the next two months. This timing is perfect for dovetailing the roadway improvements with the current
construction of the South Lubbock Sanitary Sewer Extension - Phase 1, which will soon be underway
along 98" Street between Avenue P and US 87.
Below is a description of the tasks needed for the new items of work
Additional Conveyance Documents: The original scope called for AMD to prepare three (3)
right-of-way conveyance documents and three (3) easement conveyance documents. After
the design was underway, and as more detailed design work was performed, we learned that
the roadway widening would require seven (7) additional conveyance documents to contain
the proposed improvements. Without these additional documents, the roadway cannot be
constructed. AMD requests $9,300 ($10,500 less $1,200 discount) to compensate them for
the additional work.
2. Additional Topographic Survey: After our topographic survey had been completed, a new
apartment complex began construction and built new curb and gutter improvements along the
south side of 981° Street east of Avenue U. This required us to perform an additional survey
along the new curb and gutter to determine if it would match our proposed design. AMD
requests $1,250 to compensate them for the additional work
3. Additional Property Coordination: The time required for coordinating with adjacent
landowners to obtain the necessary right-of-way and easement dedications was significantly
more time than original anticipated. IGmley-Horn respectfully requests $4,200 to compensate
us for the additional time required to coordinate with property owners related to the ten (10)
ROW dedications and three (3) easements. AMD requests $450 for their coordination efforts
to obtain ROW dedications from Betenbough Homes and Wooded Forest.
4. Additional Right -of -Way Stakina: We have performed all of the survey tasks contained within
our original scope of services. However, NTS Communications has requested for us to stake
the new right-of-way at the southeast comer of 981^ Street and Avenue P so that they can
7021 Kewanee Avenue, Suite 8-101, Lubbock, TX 79424 806 686 1080
Kimley»)Horn
Page 2
make their final utility relocation in advance of the construction. This will require a small
amount of fee to accomplish the staking. AMD requests $300 to compensate them for this
additional work.
5. New Conveyance Documents: The City of Lubbock recently requested for us to obtain a
"Storm Water Impoundment Easement" for the cut -fill plan proposed at the southwest corner
of 981 Street and Avenue P. This effort will require additional survey work, document
preparation, and coordination time to work with the property owner. AMD requests $1,250 to
compensate them for the survey work and document preparation. AMD also requests $450
for coordination time with Wooded Forest Kimley-Hom requests $600 to compensate us for
our coordination time with Wooded Forest.
The additional cost associated with this new scope is summarized in the table below:
Task
No.
Task Description
Kimley-Horn
AMD
Engineering
Total
1
Additional Conveyance Documents
(') $ 9,300
$ 9,300
2
Additional Topographic Surveying
$ 1,250
$ 1,250
3
Additional Property Owner Coordination
$ 4,200
$ 450
$ 4,650
4
Additional ROW Staking
$ 300
$ 300
5
1 New Conveyance Document & Coord.
$600
$ 1,700
$ 2,300
Sub -Totals
$ 4,800
$ 13,000
$17,800
(') AMD is providing a $1,200 discount for this task. A letter of request from AMD Engineering is
attached to this letter.
If you have any questions about our request, please call me at 806-686-1086, or email me at
kerry. m i I lerna. kimley-horn. com.
We appreciate your consideration, and we look forward to beginning construction of this important
City infrastructure project.
Sincerely,
Kerry C. Miller, P.E.
Project Manager
AMD ENGINEERING, LLC
January 9, 2015
Mr. Kerry Miller, P.E.
Kimley - Horn
7021 Kewanee Avenue, Suite 8-101
Lubbock, TX 79424
Re: Additional Surveying Services for 980' Street between University Avenue and US
Highway 87
Dear Mr. Kerry Miller:
I am writing this letter in response to your email dated December 09, 2014, and as a
continued discussion about invoicing for surveying services for the above mentioned
project. AMD Engineering had performed the services as outlined in the scope of work
for the 9801 Street project. We were requested to provide additional services outside
that scope which I have summarized below. The total billing for those additional
services was $11,000 and we are hereby requesting your consideration and payment for
those services. Thank you in advance for your consideration.
1.) Through direction provided by you during project scoping, you asked us to
provide fee and scope for 3 right-of-way conveyance documents and 3 easement
conveyance documents. Throughout the project we were asked to provide 7
right-of-way conveyance documents and 3 easement conveyance documents,
which we did. Using the lower contract price for easements of $1,500 each, 7
additional documents would total 7 @ $1,500 = $10,500.
2.) Per request by you, well after the initial survey was provided and during the
design phase of 98"i Street, we were asked to provide additional surveying
services to shoot topographic survey improvements on the curb and gutter on
the south side of 980i Street along the apartment complex located at the
southeast comer of 980i Street and Avenue U. This curb and gutter was
constructed with a new project that did not exist during our initial topo of 98'
Street. The additional effort incurred for this was $1,250.
3.) Per request by you, we performed coordination with Betenbough Homes and
Wooded Forest for right-of-way dedication. The additional effort incurred for
this was $450.
In summary, we are requesting $11,000 in additional services and have discounted
$1,200. Thank you for your consideration.
2807 740' Street, Suite 8 TBPE Reg. # F-9197 Office: (806) 771-5976
Lubbock, Texas 79423 www.amdeng.com Fax: (806) 771-7625
In addition to the items above, you have requested that I provide you with a fee
proposal for providing additional services. The following scope of services and
associated fees should summarize your request. If I have misunderstood your request,
please feel free to give me a call and I can revise any scope and fee as necessary.
1.) Flag up or reset ROW monuments at the southeast corner of 98"' Street and
Avenue P. It is our understanding that only the chamfer comers are needed.
The proposed fee for this task is $300 lump sum.
2.) We will prepare an exhibit drawing with legal description for a Stormwater
Drainage Easement or "Impoundment Easement" titled as you desire and as the
sample that you have provided to me. We are currently waiting to hear back
from you regarding the desired size of this item. It is my understanding that
Cory Dulin spoke to you about the lack of plans on part of the current
landowner/developer and the desire to not hinder anything that they would be
able to do in the future regarding playa lake reclamation. The proposed fee for
this effort is $1,250 lump sum.
3.) Services for coordination with Wooded Forest in an effort to assist you with
developing the size of these easements will cost $450. This is estimating 3
hours of work and if we have less time involved in this effort, we will bill the
time involved.
Thank you for the opportunity to work with you and the City of Lubbock on this
project.
IIS =zinc.•
Brandon Autrey, '
98th Street Improvements Project Page 2 of 2
City of Lubbock, TX
Capital Project
Project Cost Detail
February 26, 2015
Capital Project Number:
Capital Project Name:
Encumbered/Expended
City Staff
Kimley-Horn and Associates
Agenda Item February 26, 2015
Kimley-Horn and Associates
EncumberedlExpended To Date
92289
98th Street University to US 87
Estimated Costs for Remaining Appropriation
City Staff
Contingency
Remaining Appropriation
Total Appropriation
Budget
$ 93,811
825,300
17,800
936,911
40,000
9,398,389
9,438,389