HomeMy WebLinkAboutResolution - 2022-R0013 - Downtown Permittable Grant to Ramar CommunicationsResolution No. 2022-R0013
Item No. 7.21
January 11, 2022
RESOLUTION
WHEREAS, pursuant to Article IV, Section 5 of the Amended and Restated Bylaws of the
Market Lubbock Economic Development Corporation (the "Corporation"), the City Council
of the City of Lubbock (the "City Council"), as the Corporation's authorizing unit, has the
authority to approve all programs and expenditures of the Corporation; and
WHEREAS, the City Council finds that it is in the best interest of the public to approve the
program or expenditure, as proposed to the City Council by the Corporation, as set forth in
Exhibit "A" attached hereto and incorporated herein by reference; NOW THEREFORE:
BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF LUBBOCK:
THAT the Downtown Permittable Grant program or expenditure of the Corporation, in the
amount set forth in Exhibit "A" attached hereto and incorporated herein by reference, to be
provided to RAMAR Communications, Inc., is hereby approved pursuant to Section 5 of the
Amended and Restated Bylaws of the Corporation.
Passed by the City Council on January 11, 2022
�Jv
DANIEL M. POPE, MAYOR
AID
Rebecca Garza, City Secretary
T:D AS TO C
Brianna Gerardi, Busi css D velopment Director
l7:R9lIC�l�1C� I
r
K lli Leisure, Assistant City Attorney
ccdocs/RES. Market Lubbock DT Permutable Grant —RAMAR
12.16.21
Resolution No. 2022-R0013
RE 21-76
RESOLUTION APPROVING RAMAR COMMUNICATIONS, INC
612 AVENUE O
DOWNTOWN FACADE & PERMITTABLE GRANT
THE STATE OF TEXAS
COUNTY OF LUBBOCK
At a regular meeting of the Board of Directors of MARKET LUBBOCK ECONOMIC DEVELOPMENT
CORPORATION, INC., a Texas nonprofit corporation (MLI), on 'Wednesday, December 15, 2021, held in
conformity with the bylaws, after due notice as therein provided, a quorum being present and acting, the following
resolution was unanimously adopted:
WHEREAS, MLI presented to members of the Board the proposal of a possible Economic Development Grant and
Contract to RAMAR Communications, Inc., owned by Brad Moran and the RAMAR Family Trust, who is
renovating the interior and exterior of the property located at 612 Avenue O, located within the downtown TIF.
RAMAR Communications was founded in 1972 with the startup of radio station KTEZ-FM 101.1 by Ray Moran.
In 1986 RAMAR moved into the building at 98th and University under the helm of the founder's son, Brad
Moran. RAMAR Communications will move into its new studios in downtown Lubbock at 612 Avenue 4.
The scope of facade work will include landscaping, new fencing and gates totaling $79,250 in fagade expenses.
The scope of permittable work will include demolition, plumbing, HVAC, electrical and structural work
totaling $1,124,054. Total expenses for this project total $1,203,304. The terms and conditions of such Economic
Development Grant and Contract, other than the normal terms and conditions applicable to all such Economic
Development Grant and Contracts by the Corporation, are described generally as follows, to wit:
Grant RAMAR Communications, Inc. a Downtown Facade Grant of $25,000 and a Downtown Permittable
Grant totaling $100,000 for the project at 612 Avenue O, which is located within the Downtown TIF, once proof of
payment has been submitted.
WHEREAS, The Board of Directors of MLI finds that an Economic Development Grant and Contract
offering the incentive for providing assistance for renovations to their property, meet and comply with the
qualifications and purposes of the Corporation for the granting of such Economic Development Grants and
Contracts.
Upon Motion by Director, Mr. Barry Orr and Seconded by Director, Dr. John Opperman.
IT WAS RESOLVED that MLI offer and, if accepted by Recipient, enter into an Economic Grant and
Contract with RAMAR Communications, Inc., for improvements to the building at 612 Avenue O, Lubbock, Texas.
This Economic Development Grant and Contract will be on the normal terms and conditions of such Downtown
Grant Program and Contract offered by MLI to existing businesses and business prospects and authorize the CEO
to enter into and execute all documents related to the Economic Grant and Contract.
John Osborne, President & CEO
Linda Davis, Secretary
MARKET LUBBOCK, INC. - DOWNTOWN GRANT PROGRAM
612 Avenue 0
(RAMAR Communications, Inc.)
TOTAL SCOPE OF WORK = $1,203,304
TOTAL FACADE SCOPE OF WORK = $79,250
FACADE GRANT = $25,000
TOTAL PERMITTABLE SCOPE OF WORK = $1,124,054
PERMITTABLE GRANT = $100,000
M A R K E T
Downtown Grant Program
Presented to MLI Board
December 15, 2021
Project 612 Ave 0 (FaVade and Permittable)
RAMAR Communications, Inc. at 612 Ave 0 is making improvements to both the interior and exterior of
their property, located in the Downtown TIF.
RAMAR Communications was founded in 1972 with the startup of radio station KTEZ-FM 101.1 by Ray
Moran and was originally housed in the Plains National Bank Building. It was sold in 1983 to help fund
the startup of KJTV-TV, which was established in 1981 as an independent television station. The station's
success eventually gave way to the FOX network, founded in 1986. That same year, RAMAR moved into
its 33,000 sq. ft. building at 98th and University under the helm of the founder's son, Brad Moran. In
1993, two radio stations, AM 950 and FM 93.7, were added back into the operation and by the end of the
decade, RAMAR added FM stations 97.3, 106.5. 2016 and 107.7. RAMAR sold the TV business in 2020 but
retained its land and towers at 98th and University. RAMAR now operates Double T 97.3, Magic 106.5,
93.7 The Eagle,107.7 YES! FM,100.7 The Score, Oldies 97.7, 96.9 The Bull, 93.1 Texas FM and 92.3 The
Vibe. In 2022, RAMAR Communications will move into its new studios in downtown Lubbock at 620 Ave
0.
The scope of fagade work will include landscaping, new fencing and gates totaling $79,250 in facade
expenses. The scope of permittable work will include demolition, plumbing, HVAC, electrical and
structural work totaling $1,124,054. Total expenses for this project total $1,203,304.
The MLI Board is being asked to consider a Downtown Facade Grant for RAMAR Communications, Inc.
totaling $25,000 and a Downtown Permittable Grant of $100,000 at 612 Ave 0.
M A R K E T
LUBBOCK.
Downtown Grant - Application
The information requested on this form will be used by Market Lubbock, Inc. for analysis of your project.
MLI CONTACT INFORMATION
Jorge Quirino - Director of Downtown & Special Project. Phone: 806.749.4500
Market Lubbock, Inc.
1500 Broadway, Sixth Floor, Lubbock, TX 79401 Email: 'Lge(c)marketlubbock.orc
Date Initial Application Submitted (Due prior to start of construction or permits assigned) 07/14/21
Projected Project Start Date 08/01/21
Project Property Address
Property LCAD R#
GENERAL INFORMATION
Company Name
RAMAR Communications, Inc.
Contact
Brad Moran
Street Address
612 Ave O
Title
President
City, State, Zip
jLubbock, TX 79401
Phone
806-787-3434
ibmoranaramarcom.com
Email
INFORMATION ABOUT THE PROJECT
Property Ownership: Own ❑ Lease 0 Grant Type: Permittable ❑ Facade 0
(612 Ave 0, LLC)
Summary of Expenses (detailed bids attached)
Projected
I MLI Approved
Fagade
$79,250
$25,000
Permittable
$1,124,054
$100,000
TOTAL
$1,203,304
$125,000
Final bids will be used to calculate the project cost and grant amount.
COMPANY BACKGROUND
List any person or entity that has at least 5% ownership in the Applicant Company:
Is the firm registered with the Secretary of State's Office to do business in Texas? Yes
Are you in good standing with the State of Texas? Yes
If you answered "No" to either of the above two questions, please explain
Is the firm and/or principals delinquent on any federal, state or local tax obligations? No
Has the company or principals of the company had prior bankruptcies or lawsuits? No
answered "Yes" to either of the above two
Percent
MLI 3.8.21
APPLICANT'S CHECKLIST:
Initial application received by MLI prior to the start of construction and/or before permits are assigned ❑
All remaining documents must be received and an application packet presented to the MLI Board no ❑
more than three months after the initial application is received by MLI.
Contact Brianna Gerardi, City Director of Development bgerardi@mylubbock.us , to determine:
Does the scope of work meet downtown standards and guidelines? ❑
Are permits required for any aspect of the scope of work? ❑
Are public improvements required? ❑
Documents Required for Final Grant Application
Copies of City permits, if applicable
❑
Detailed/Itemized Bids
❑
Before Pictures
❑
Copy of building's current certificate of occupancy (request at
❑
orr@mylubbock.us)
Architectural Renderings (if applicable)
❑
Architectural Plans (if applicable)
❑
After Completion of Construction
Certificate of Occupancy or Similar City Document Approving ❑
Completion (Applicant responsible for final scope of work matching
approved scope)
Proof of Payment:
PAID Invoices (must reference the approved project) ❑
Processed Checks, Bank or Credit Card Statements ❑
matching PAID invoices (legible copies)
Signature (not required for electronic submittals): Brad Moran (per email)
Date: 7/15/2021
MLI 3.8.21
r;-EastE.K-n ffftildin-g--
612 Ave O — Lee Lewis Schedule of Values
Proj: Ramar Bldg Area: 11.500 st
Loc: Lubbock Site Area: 0 st 0 Acres Estimator:
Owner: Moran Schedule: 4 mo
Arch: CDA Subcontract
Date: 8/6/2021 Bond Rate: 1.50%
Elting. Permit
Survey
SWPPP
Construction Entrance
Contingency Allowance
119 Selective Site Demolition
Selective Interior Demo
Selective Building Demo
New Asphalt Paving
Paving Repair
StnpingrADA Signs
313 Portland Cement Concrete
000 Landscape Work Patch and Rf
Site Fencing
Gates
Cedar Utility Gate
042000
Unit Masonry Assemblies
047000
Adhered Stone Veneer Sy
047200
Cast Stone Masonry
CMU Fence
Concrete Grade Beam for
051200
Bollards
055000
Metal Fabrications
Prefab Parking Structure
3uyoutRamar
Retail Recap
2.875
2.500
(EXCLUDED
Allowance 2.000
SPECS 0
LLCI 10,500 43.200
LLCI w/tlemo wl demo
LLCI wl demo w/tlemo
Allowance
Pavecon
Pavecon
Moms
Allow, ance
Allowance
Allowance
Lonestar
Lonestar
Lonestar
Lonestar
Wall Allowance
South Plains Steel
LLCI
Allowance
5,600
6,8%
evi pav repair
48.528
20.000
41.250
15.000
3.000
107.350
w/ masonry
wl masonry
w/ masonry
20.545
1,900
5,000 1.200
0
1 of
37,233
3.24
0
0.00
2.875
025
2,500
0.22
0
0.00
2.000
0.17
0
0.00
0
000
0
0.00
0
0.00
53,700
4.67
0
000
0
0.00
0
0,00
5,600
0.49
6,856
0.60
0
0.00
46.528
422
0
0,00
20.000
1.74
0
0.00
41,250
3.59
15,000
1.30
3.000
0.26
0
0.00
0
0.00
0
0,00
107,350
9.33
0
0.00
0
0.00
0
0.00
20.545
179
0
0.00
1.900
0.17
6,200
0.54
0
0.00
0
Goo
9/21/2021 5:14 Phi
Loc: Lubbock
Owner Moran
Arch: CDA
Bldg Area:
Site Area:
Schedule.
Subcontract
0 sf
4 mo
Mall's
0 Acres
Estimator:
0
000
061053 Miscellaneous Carpentry
LLCI
17.250
17.250
1.50
0
000
Millwork
Hunter
23.483
23.483
2.04
0
0.00
71500 Firestopping
wl trades
24,000
24,000
2.09
0
0.00
7400 Stucco
T&S
68,750
66.750
5,98
Stucco Soffit
T&S
wl Stucco
0
0,00
0
0,00
7700 Roofing Sheet Metal
Schrader
12.888
12.888
1.12
0
0.00
079200 Joint Sealants
Monterey
8.200
8.200
0.71
0
0,00
081113 Steel Doors and Frames
WBS
32,082
6.900
38,982
3.39
087100 Door Hardware
WBS
wl doors
w1 doors
0
0.00
0
000
054000 Cold -Formed Metal Framing
Hamilton
w/ gyp
0
0.00
072100 Building Insulation
Hamilton
wl gyp
0
0,00
092216 Non -Load Bearing Steel Frami
Hamilton
W gyp
0
0.00
092900 Gypsum Board Sheathing
Hamilton
94.200
94.200
8.19
Exterior Framing and Sheamin
Hamilton
w/ gyp
D
0.00
D
0.00
9400 Carpet
Yates
99.245
99,245
8.63
Resilient
Yates
w/ carpet
0
000
Ceramic Tile
Yates
wl carpet
0
0-00
0
0.00
099100 Painting
Padgett
98,445
98.445
8.56
25% Wall VC Removal
Padgett
wl painting
0
0,00
0
0.00
10000 Toilet Accessories
WBS
4.859
500
5,359
0.47
Fire Exhgulsher
Allowance
1.000
w/ crew
1,000
0-09
0
0.00
224000 Plumbing
Earls
32,226
32.226
2,80
HVAC
Allowance
35.000
35,000
3.04
Concrete Patch @ Plumbing
Allowance
2.000
2.000
0.17
0
0.00
31.ryoutRamar Retail Recap
2013
912112021
5:14 PM
Prot' Ramar
Bldg Area:
11.500
sf
Loc: Lubbock
Site Area.
0
sf
0 Acres
Estimator:
Owner. Moran
Schedule:
4
mo
Arch: CDA
Subcontract
Date: 8/612021
Bond Rate.
1.50%
Code Description
SubcontractoriVendor
Subs
Mail's
Labor
Total
s1Sf
260000 Electrical
Larcon
78,500
78,500
6.83
Fire Alarm
EXCLUDED
0
0.00
0
0.00
Labor Crew
10.320
10.320
0.90
0
0.00
0
0.00
Fee/Mo.,
S13,233
AddCheck --
ok
869,691
70214
1 480
1,024.385
89.08
% General Conditions
3.35%
Percent Cost:
84.9°k
6.9%
8.2%
Approx Cost Beakdown
(Po11SC)
LAB BURDEN
22.00%
40. DO%
29,767
2,59
Bldrs. Risk
S295
Sales Tax
GRT
0.00%
0
0.00
Site S20BA79
S18-13
Gen. Liab.
S4.217
Sub Total
1,054.152
91.67
OPL
SO
B.R.lG.L.lOPL
4,512
0.39
Building S994,825
S86&51
P&P Bond
S14,616
Fee
5.0%
52,933
4.60
Total
1,111.597
96.66
Gross Reciepts Tax
91,707
Total With GRT
1,203,304
Bid Amount
1,203,304
RJOUND FLOOR DEMO .p
N
IEH.
MAUAM' DEMQ- PLAN, 02. 44
T—
OUND FL001 PIA
HASFMFN`r FLOOR
GENERAL NOTES SHEM NOTES
ui
E-
7.T:
t.j
C..
o
WALL TYPE LEGEND
M=13
ARMO I 15 PC
_t=*T_4CE8,' :1 QRY 'ZC UE V LE
kc
I—,
:Al�]O
GENERAL NC SeVEDUll
T 7
7
ga7 ;3 f.
I T
no
IEET NOTES
i -dam+4�
f- T,
:v
_Tl Ll
INTYRIOR 11NIS)f MA- VRJ,%t. SCIIF.DVU
t4
mz
V11TE ALL SEAL11:14� A�:(
T
T
SHE 'Et I.FrUND
0 0 0 o C-1
TWO
7�
6b IOU -
_A
lip
NJ L J
T
Tu Exp. JT, pcua,_o
Rpump FLOOR RCP RA.
rA -rAILQ— x
=CAL rnp QL 3
ARCHITsiql; Pq
C91; M
-0
AM
A2.0
or. Is
ri "MoRN-1m. I)XfcAL DETAIL 07
101 City of CITY OF LUBBOCK
Lubbock ALTERATIONS COMMERCIAL BUILDING
TEXAS
Thursday, October 14, 2021 9:35AM Page 1 of
Date Entered Date Expires
14-Oct-2021 12-Apr-2022
Parcel
PIN:
36104
Address:
620 AVE O
Zip:
79401
Units:
Subdivision:
MEMORIAL CENTER
Legal Detail:
MEMORIAL CENTER BLK 7 L 3A
Zone
Proposed Development
Permit Type/Number Project Number
COMM-125870-2021
of Construction Occupancy
11-B B
437 - COMMERCIAL ADDITIONS /ALTERATIONS
MIN. FINISHED FLOOR ELEV. Not Determined PER TABLE 403.1. 7.3, 2009 IRC AMENDMENTS.
FLOOD PLAIN?
MEMORIAL CENTER BLK 7 L 3A 11,029.0
DESCRIPTION:
COMMENTS:
COMMENTS:
DESCRIPTION:
CORRECTIVEACTION:
COMMENTS:
RECOMMENDATION:
TO REQUEST INSPECTIONS CALL (806)775-3159 OR (806)775-3174 FOR BUILDING INSPECTION AND
(806)775-2589 FOR WATER UTILITIES.
11830 SQ FT
3408 SF - Signed Electrical
3644 SF - Signed Mechanical
1319 SF - Engineered Plumbing
Valuation Square Footage C of O Required
$250,000.00 11,029.00 YES
r CITY OF LUBBOCK
City of
Lubbock ALTERATIONS COMMERCIAL BUILDING
Texas
Thursday, October 14, 2021 9:35AM Page 2 of 2
Date Entered Date Expires
14-Oct-2021 12-Apr-2022
Professional
LEE LEWIS CONSTRUCTION, INC.
LEWIS, LEE
PO BOX 65197
LUBBOCK, TX 79464
State License: ACTIVE
Professional License:
Required Inspections
Zoning Final
Building Final
Fire Final
Framing
Slab Building
Footing
Notice/Signature
Permit Type/Number
COMM-125870-2021
Protect Number
806-797-8400
I hereby certify that the above statements are true facts concerning the construction of the building or other work for
which this application is made. I also understand that the issuance of this permit does not relieve the permit holder from
the responsibility of complying with all applicable City of Lubbock regulations, codes and ordinances and that failure to
comply may subject the permit holder to criminal and/or civil liability.
Issuance of this city permit does not insure compliance with state or federal regulations, rules or laws. I understand that it
is the responsibility of the permit holder or his agents to meet applicable state and federal requirements. These
requirements may include, but are not limited to, those imposed by the Americans with Disabilities Act, the U. S.
Environmental Protection Agency, the Texas Architectural Barriers Act, the Texas Department of Licensing and
Regulation, the Texas Department of Health and the Texas Commission of Environmental Quality. This list is not
all-inclusive and other federal or state requirements may be applicable.
Customer Signature: Permit Issued By: 172984