HomeMy WebLinkAboutOrdinance - 2018-O0057 Budget Amendment 13 - Amending The FY 2017-18 Budget - 05/10/2018First Reading
May 10, 2018
Item No. 6.2
ORDINANCE NO.
Second Reading
May 24, 2018
Item No. 5.1
AN ORDINANCE AMENDING THE FY 2017-18 BUDGET FOR MUNICIPAL PURPOSES
RESPECTING THE CAPITAL PROGRAM TO AMEND CAPITAL IMPROVEMENT
PROJECT (CIP) 92470, SUBSTATION REBUILD — OLIVER; AMEND CIP 92484,
SUBSTATION UPGRADES; ESTABLISH CIP 92560, 115 kV LINE CONSTRUCTION —
RED RAIDER TAP; ESTABLISH CIP 92561, 345 kV TRANSMISSION LINE; AMEND
FULL-TIME EQUIVALENT (FTE) POSITIONS IN CUSTOMER SERVICE AND
INCREASE APPROPRIATION; AMEND FTE POSITIONS IN PRODUCTION REGIONAL
MARKET ADMINISTRATION AND COMPLIANCE AND DECREASE APPROPRIATION;
AMEND FTE POSITIONS IN DISTRIBUTION LOAD DISPATCHING AND DECREASE
APPROPRIATION; PROVIDING FOR FILING; AND PROVIDING FOR A SAVINGS
CLAUSE.
WHEREAS, Section 102.010 of the Local Government Code of the State of Texas
authorizes the City Council to make changes in the budget for municipal purposes; and
WHEREAS, in accordance with the City Budget Ordinance the City Council shall
approve all transfers between funds and departments; and
WHEREAS, the City Council deems it advisable to change the FY 2017-18 Budget for
municipal purposes and reallocate funds as follows; NOW, THEREFORE,
BE IT ORDAINED BY THE CITY COUNCIL OF THE CITY OF LUBBOCK:
SECTION 1. THAT the City Council of the City of Lubbock hereby approves changes
to the City of Lubbock Budget FY 2017-18 (Budget Amendment #13) for municipal purposes,
as follows:
I. Amend Capital Improvement Project 92470, Substation Rebuild — Oliver, by
decreasing the appropriation by $2,000,000, from $2,155,000 to $155,000;
decreasing the FY 2018 30-year LP&L Revenue Bonds by $1,555,000; and
decreasing the FY 2017 LP&L 30-year Revenue Bonds by $445,000.
II. Amend Capital Improvement Project 92484, Substation Upgrades — by
decreasing the appropriation by $2,400,000, from $4,125,000 to $1,725,000, and
decreasing FY 2018 30-year LP&L Revenue Bonds by $2,400,000.
III. Establish Capital Improvement Project 92560, 115kV Line Construction - Red
Raider Tap, and appropriate funding in the amount of $400,000. The funding will
be FY 2018 30-year LP&L Revenue Bonds. The project scope and justification
is as follows:
Project Scope: LP&L requires a new substation, Red Raider, to be built. This
scope addresses the new 115kV transmission line tap between the new substation
Red Raider and the existing Vicksburg to Brandon 115kV transmission line. The
new transmission tap will be built to 115kV specifications. It will tap off of the
existing Vicksburg to Brandon 115kV transmission line, which will be rebuilt
from the tap to Vicksburg. This scope of work only addresses the tap between
Red Raider substation and Vicksburg to Brandon I I5kV transmission line.
The new Red Raider substation is to be located off of Quaker Avenue (FM 2000),
to the Northwest of the intersection of 4th Street. It is located next to Texas Tech
University's agriculture research center. The Vicksburg to Brandon transmission
line runs north — south paralleling Quaker Avenue. The transmission line
conductor is planned to be 959.6 aluminum conductor steel supported thermal
wire (ACSS/TW) with an optical ground wire (OPGW) static neutral wire.
However, the final determination of the conductor is subject to change based on
the engineering analyses of the physical construction. The primary factor to
consider is the percent loading of the line and the effective sag it has on the line.
The transmission line total cost per mile will be approximately $1.6 million. The
project includes the estimated engineering, ROW acquisition, material, and
construction cost associated with constructing the transmission line.
Project Justification: Red Raider Tap is a project required to be completed in
order for the new Red Raider Substation to be connected to LP&L's current 69
kV Transmission System. The project is not as close to the sub as originally
planned and this project is needed to connect the substation to the existing
transmission system.
IV. Establish Capital Improvement Project 92561, 345kV Transmission Line, and
appropriate funding in the amount of $4,000,000. The funding will be $3,555,000
FY 2018 30-year LP&L Revenue Bonds and $445,000 FY 2017 30-year LP&L
Revenue Bonds from Capital Improvement Project 92470, Substation Rebuild —
Oliver. The project scope and justification is as follows:
Project Scope: The configuration for the incremental facilities required to
transition the portion of load moving from SPP to ERCOT assumes that the four
230 kV interconnections with SPS will be eliminated and replaced with three 345
kV interconnection points within the ERCOT system. The Wadsworth
interconnection (also see #92475) will be converted to a 345/115 kV
interconnection, and the station will be fed from the Abernathy —Wadsworth —
Oliver —Farmland 345kV line. The interconnection at McDonald will be
eliminated and replaced by a 345/115 kV interconnection at a proposed LP&L
North 115 kV station (also see #92474). This interconnection will be fed from the
Abernathy —North 345 kV line. To the south, the LP&L system will no longer be
fed from the Southeast station. Instead, two new 115 kV lines will be sourced
from the new Oliver 345 kV station (also see #92473) and will feed the LP&L
Chalker and LP&L Oliver stations. These lines will be constructed by a third
party, and LP&L will reimburse the third party for related expenses.
Project Justification: Through its studies, ERCOT has concluded that the
proposed integration facilities plan (Option 4ow) aligns well with the 2014
Panhandle Roadmap Stage 2 upgrade from Ogallala to Long Draw and that it
integrates LP&L load into ERCOT while meeting applicable reliability criteria,
has the lowest societal cost when considering capital cost and production costs,
provides for the largest Panhandle export increase, and provides greater
opportunities for ERCOT expansion.
V. Amend the Customer Service cost center 7515 by adding seven full time Utility
Service Operator positions and one Utility Operations Coordinator position.
VI. Amend the Customer Service cost center 7515 by increasing the appropriation for
eight full-time positions by $390,209.
VII. Amend the Customer Service cost center 7515 by increasing the appropriation for
computer/telephone equipment and professional services by $33,131.
VIII. Amend the Production Regional Market Administration & Compliance cost
center 7317 by eliminating three full time Power Plant Control Room Operator
positions.
IX. Amend the Production Regional Market Administration & Compliance cost
center 7317 by decreasing the appropriation for three full-time positions by
$269,448.
X. Amend the Distribution Load Dispatching cost center 7414 by eliminating two
full time SCADA Operator/Dispatcher positions.
XI. Amend the Distribution Load Dispatching cost center 7414 by decreasing the
appropriation for two full-time positions by $153,892.
SECTION 2. THAT a copy of the changes made to the City of Lubbock Budget
pursuant to this Ordinance shall be filed with the City Secretary and County Clerk of Lubbock
as required by law.
SECTION 3. THAT should any section, paragraph, sentence, clause, phrase or word of
this Ordinance be declared unconstitutional or invalid for any reason, the remainder of this
Ordinance shall not be affected thereby.
AND IT IS SO ORDERED
Passed by the City Council on first reading on May 10, 2018
Passed by the City Council on second reading on May 24, 2018
r
JEFF GRI FITH, MAYOR PRO TEM
ATTEST:
t*YN fv
Rebecca Garza
City Secretary
APPROVED AS TO CONTENT:
D. u Kostelich
Chief Financial Officer
APPROVED AS TO FORM:
Amy -
AssfAt C' Attorney
ccdocsBudgetFY 1718.Amend I lord
4/27/ 18