HomeMy WebLinkAboutResolution - 050968D - Water/Sewer Improvements - Hemphill Contracting Co - Quail Ridge Addition - 05/09/1968RESOLUTION
Resolution accepting water and sewer system improvements for Lots 1
thru 75 and Lot A, Quail Ridge Addition.
WHEREAS, the developer of Lots 1 thru 75 and Lot A, Quail Ridge Additi
have complied with the provisions of the City of Lubbock Code, Chapter 34, Article
2, by providing the water and sewer improvements for said addition in accordance
with paragraph 61 of said Chapter 34, and,
WHEREAS, the total utility cost to the developer is $24,556.88 with the
improvements constructed by Hemphill Contracting Company having a value of.
$20,488.35 as determined by the unit prices established by said Chapter 34, and
$1,358.00 cash (engineering, wet tie-ins, paving repair, difference in Pro Rata
and actual cost) paid to the City, with Kenneth Flagg, the developer, to receive a
refund of $3,280.65,in accordance with Chapter 34 of the Code of the City of
Lubbock.
WHEREAS, the construction of the said water and sewer improvements
was performed under the supervision of the City Engineer and said improvements
have been completed in accordance with the City of Lubbock's plans and
specifications,
NOW THEREFORE BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF
1. That the improvements be and the same are hereby accepted
as an integral part of the water and sewage system of the
City of Lubbock.
2. That refund of the refundable cost in the amount of
$3,280.65 be made in accordance with said Chapter 34.
3. This resolution shall take effect and be in force from
and after its passage.
PASSED AND APPROVED THIS 9TH DAY
ATTES
Lalfenia Lowe, City -Secretary
AP VED:
muel W. Wahl, 6ity Engineer
APPROVED:
Fred 0. Senter, Jr., Attorney