HomeMy WebLinkAboutResolution - 080973G - Pavement Improvements - Roehr Construction Inc - Newman Addition - 08/09/1973a
RESOLUTION
RESOLUTION ACCEPTING IMPROVEMENTS ON PORTIONS OF STREETS AND/OR AVENUES
AS LISTED BELOW:
WHEREAS= in conformance with the paving requirement provisions of City
Ordinance 1331, the subdivider of Newman Addition Tract A, made arrangements
with Roehr Construction, Inc. for the construction of paving improvements on
certain streets dedicated in said subdivision under the provisions of said
Ordinance prior to the recording of the subdivision plat of Newman Addition
including the following streets:
53rd Street from its intersection with the East lip line of Chicago Avenue
to its intersection with the West lip line of Bangor Avenue known and
designated as New Subdivision Unit Number 2014-43. Part of curb and gutter
on North side plus stub at Bangor.
Bangor Avenue from its intersection with the South lip line of 50th Street
to its intersection with a line 16.00 feet South of the South property line
of 53rd Street known and designated as New Subdivision Unit Number 2014-45.
AND WHEREAS, the construction of the above improvements on the above-
mentioned streets was performed under the supervision of the City Engineer,
and said improvements have been completed and have been inspected and found
to have been constructed in accordance with City specifications and in
accordance with the provisions of City Ordinance 1331.
THEREFORE$ BE IT RESOLVED BY THE CITY OF LUBBOCK$ TEXAS.
That the improvements on said portions of the above-mentioned streets
be and the same are hereby accepted and the City Engineer be and he is hereby
authorized to direct the payment of the City's portion of the cost.
This resolution shall take effect and be in force from and after its
passage,
PASSED'AND APPROVED THIS 9TH DAY OF AUGUST, 1973
ATTEST: _
-- - orris W. Turner, Mayor
Lave 'a Lowe, City' Secretary
APPROVED APPROVED:
CONSOLIDATED FINAL ESTIMATE
NEWMAN ADDITION - TRACT A
Accepted August 9, 1973
_ QUANTITIES
S.Y. L.F. S.Y. L.F.
Unit & Paving Curb & Alley Curb':& -Gutter L.F.
Sub -Unit Location 6" Base Gutter Return Removal Re -surfacing
NS 2014-43 53rd Street from 148.76 568.54
the ELL of Chicago
Avenue to the WLL
of Bangor Avenue.
Part of curb and
gutter on North
side plus stub at
Bangor Avenue.
NS 2014-46 Bangor Avenue from 3,628.86 1,559.08 12.22 92.00 92.00
the SLL of 50th St.
to 16.00 feet South
of the SPL of 53rd
Street.
:- TOTAL QUANTITITES 3,77:'x.62 2,127.62 12.22 92.00 92.00
COST ESTIMATE
3,777.62 S.Y. Paving 6" Base
2,127.62 L.F. Curb & Gutter
12.22 S.Y. Alley Return
92.00 L.F. Re -surface
92.00 L.F. Curb & Gutter Removal
COST DISTRIBUTION
Lump Sum Contract Cost $12,000.00
Property
Unit & Contract Owner
Xub-Unit Cost Cost
NS 2014-43 Lump Sum
NS 2014-45 Lump Sum
Total Lump Sum Contract 12,000.00<:•.: