HomeMy WebLinkAboutResolution - 128 - CO#5 To Contract - HB Zachry Co - ADAP Project #6-48-0138-12, LIA - 04/12/1979JCR:cl RESO #128 - 4/12/79
RESOLUTION
BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF LUBBOCK:
THAT the Mayor of the City of Lubbock BE and is hereby authorized and
directed to execute for and on behalf of the City of Lubbock a Change Order #5
for taxiway J extension, A.D.A.P. Project X66-48-0138-12, attached herewith
which shall be spread upon the minutes of the Council and as spread upon the
minutes of this Council shall constitute and be a part of this Resolution as if
fully copied herein in detail.
Passed by the City Council this 12th day of April ,1979.
a-1Mr3+0678
ATTEST:
=Evelyn Gaffga,'_City SecietarVTreasurer
APPROVED AS TO CONTENT:
Marvin Coffee, DirO oir of Aviation
APPROVED AS TO FORM:
ohn 4C6q.-„�+�
C. -Ross, Jr., City Attor ey
w
A
V
RESO #128 - 4/12/79
CHANGE ORDER NO. 5
Runway 17R -35L Improvements and
Taxiway J Extension
Lubbock International Airport
Lubbock, Texas
ADAP Project No. 6-48-0138-08,09,10 & 11
and ADAP Project No. 6-48-0138-12
TO: H. B. ZACHRY COMPANY.
P.O. Box 21130
San Antonio, Texas 78285
General description of work included in contract: The construction of
approximately 148,000 square yards of rigid overlay pavement with level up
course on existing runway, construction of approximately 81,000 square yards
of rigid pavement on the extension of Runway 17R and the parallel Taxiway M,
construction of taxiway connections, modifications to existing airport light-
ing system, installation of new high intensity lights on the extension of Run-
way 17R and new taxiway lights on the extension of Taxiway M, removal of exist-
ing paving, construction of drainage structures, marking runways and taxiways,
construction of blast pads for Runway 17R -35L, excavation work, seeding shoulders,
and other related items of work. Work on Taxiway J Extension was added by
Change Order No. 3/Supplemental Agreement.
Original amount of contract . . . . . . . . . . . .
Alternate Bid/Change Order No. 1 . . . . . . (Add)
Total Amount Bid
Change Order No. 2 . . . . . . . . . . . . . (Add)
Change Order No. 3/Supplemental Agreement . . (Add)
Change Order No. 4 . . . . . . . . . . . . .(None)
Change Order No. 5 . . . . . . . . . . . . .(None)
Adjusted Contract Amount
Adjustment in Construction Time:
Original Date of Completion . . . . . . . .
Change Order No. 1 . . . . . . . . . . . . . .
Change Order No. 2 . . . . . . . . . . . . . .
Change Order No. 4 . . . . . . . . . . . 0 . .
Adjusted Date of Completion for Runway 17R -35L
Improvements . . . . . . . . . . . . . . . .
Change Order No. 3 - Time for Completion of
Taxiway J Extension . . . . . . . . . .
Change Order No. 5 . . . . . . . . . . . . .
Adjusted Time for Completion of Taxiway J
Extension . . . . . . . . . . . . . . . . .
CHANGE ORDER NO. 5
Page 1 of 2
$4,349,689.00
2.262.100.00
$6,611,789.00
8,000.00
1,038,189.00
-0-
-0-
$7,657,978.00
October 31, 1977
Add 47 days
None
Add 165 days
June 1, 1978
120 days
Add 282 days
402 days
Ww..'
WHEREAS, during the construction time provided by the contract for the
Taxiway J Extension a shortage of portland cement caused delays in construction
of the project resulting in loss of working time on this portion of the project;
AND WHEREAS, during the construction-of--the,Taxiway J --Extension project,
the weather was unseasonal in that more ice, snow and cold weather occurred than
was normal, resulting in the loss of working time due to the snow, ice, cold and
wet unworkable conditions at the job site:
THIS AGREEMENT WITNESSETH: In consideration of the mutual advantages gained,
the Owner and Contractor agree that the time allowed for completion of the pro-
ject shall be extended 282 days, from 120 days to 402 days, and further agree
that there shall not be any adjustment to the contract price for the extension
of time.
IN WITNESS WHEREOF, the Owner and the Contractor have hereto set their hands
this the 12th day of April , 1979.
- - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -
RECOMMENDED: PARKHILL, SMITH & COOPER, INC., Consulting' Engineers
BY l - ! ! / 1979
APPROVED: H. B. ZACHRY COMPANY, Contractor
By J 1979
E M. RREUSn, SENIOR VICE PRESIDENT
APPROVED: CITY OF LUBBOCK, TEXAS, Owner
By C�9o� iE�/�-, 1979
ATTEST:
City Sec etary
APPROVED AS TO CONTENT
Marvin Coffee, Dir r of Aviation
APPROVED AS TO FORM:
Jc& Ross, City Attorney
CHANGE ORDER NO. 5
Page 2 of 2
PPARKHILL, SMITH & COOPER, INC.
SENGINEERS • ARCHITECTS • PLANNERS
LUBBOCK EL PASO
March 21, 1979
Mr. Marvin Coffee
Director of Aviation
Lubbock International Airport
Route 3 - Box 389
Lubbock, Texas 79401
Re: Lubbock International Airport
Taxiway J Extension
ADAP Project.No. 6-48-0138-12 .
Dear Mr. Coffee:
Transmitted herewith are eight (8) copies of Change Order No. 5
for the referenced project. Change Order No. 5 is for a time
extension due to a portland cement shortage and due to extreme
weather conditions.
Approval of Change Order No. 5 is recommended.
After execution of Change Order No. 5, please forward three
copies to FAA, forward one copy to the Contractor, return one
copy to this office. The remaining copies are for your files
and the City records.
Sincerely,
PARKHILL, SMITH & COOPER, INC.
B C
Y
B. E. Wauer, .E.
BEW/dj
Enclosures
mc: Mr. Fred Gurule, FAA - Albuquerque
CITY SECR�'ARY
4010 AVENUE R • LUBBOCK, TEXAS 79412 • PHONE $06.747.0161
ATCHESON, CARTWRIGHT & ASSOCIATES • MEMBERS A.I.A. • AFFILIATES