HomeMy WebLinkAboutResolution - 122 - CO#1 To Contract - Anthony Mechanical - Digester Additions, SE Reclamation Plant - 04/12/1979-/-4 JWF : hw
RESO. #122 - 4/12/79
RESOLUTION
BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF LUBBOCK:
THAT the Mayor of the City of Lubbock BE and is hereby authorized and
directed to execute for and on behalf of the City of Lubbock a Change Order
#1 to a contract with Anthony Mechanical, Inc., for extra work on digester
additions at the Southeast REclamation Plant, attached herewith which shall be
spread upon the minutes of the Council and as spread upon the minutes of this
Council shall constitute and be a part of this Resolution as if fully copied
herein in detail.
Passed by the City Council this 12th day of April ,1979.
ATTEST:
tVelyn Gafiga, City S&Erlltr-Treasurer
APPROVED AS TO FORM: (/
O.
J. rth'Fullingim, Asst. if
ity Attorney
DIRK W=, MAYOR
TO: Anthony. Mechanical Inc.
P.O. Box 2706
Lubbock, -Texas 79408
Original amount of the contract
Net amount this change order
Amended amount of contract
Additional time of completion
TIED TO RESO. #122 - 4/12/79
Change Order No. 1
Digester Additions
S.E. Water Reclamation Plant
GWO 10949
$119,897.00
$ 695.75
$120,592.75
None
WHEREAS, it is desirable to make changes in the plans and specifi-
cations for this project;
THIS AGREEMENT WITNESSETH: In consideration of the mutual advantages
gained, the Owner and the Contractor agree to the change shown herein
and in the attached exhibits and data and the Owner and the Contractor
agree that the original contract between them shall be modified and
amended to the extend herein indicated.
IN WITNESS WHEREOF, the Owner and the Contractor have hereto set
their hands this the 12th day of April, 1979.
Anthony Mechanical, Inc.
By�, .
Contractor
CITY OF LUBBOCK
OWNER
By
M.11150 -i
ATTEST:
Ci y Secre ary
City
Attachment to Change Order X61
Anthony Mechanical, Inc.
G.W.O. 10949
EXPLANATION OF CHANGE
Modifying eductor tube on gas lifter installed in digester #5.
BREAKDOWN OF CHANGE
Crane rental and operator = $453.75
Truck (18 wheel for 2 hours) = $ 16.00
Plumber foreman 4 hrs. @ $23.00 = $ 92.00
Plumber helper 4 hrs. @ $13.50 - $ 54.00
Truck driver 4 hrs. @ $20.00 = $ 80.00
Anthony Mechanical, Inc.
Contractor
TOTAL = $695.75