HomeMy WebLinkAboutResolution - 495 - Accept Paving Improvements - Kerr Co - Lot 231, Live Oak Addition - 05/22/1980RESOLUTION #495 - 5/22/80
( C4' RESOLUTION
CIV
RESOLUTION ACCEPTING IMPROVEMENTS ON PORTIONS OF STREETS AND/OR AVENUES
AS LISTED BELOW:
WHEREAS, in conformance with the paving requirement provisions of City
Ordinance 1331, the subdivider of Live Oak Addition, Lot 231 made arrangements
with Kerr Construction Co. for the construction of paving improvements on cer-
tain streets dedicated in said subdivision under the provisions of said Ordi-
nance prior to the recording of the subdivision plat of Live Oak Addition,
Lot 231 including the following streets:
West 1/2 of Hartford Avenue from its intersection with the North Property
line of Lot 231, Live Oak Addition to its intersection with the center-
line of 70th Street, known and designated as New Subdivision Sub -Unit
Number 63A of Unit Number 2026.
North 1/2 of 70th Street from its intersection with the east lip line
of Indiana Avenue to its intersection with the west lip line of Hart-
ford Avenue known and designated as New Subdivision Sub -Unit Number
63B of Unit Number 2026.
AND WHEREAS, the construction of the above improvements on the abovemen-
tioned streets was performed under the supervision of the City Engineer, and
said improvements have been completed and have been inspected and found to
have been constructed in accordance with City specifications and in accor-
dance with the provisions of City Ordinance 1331.
THEREFORE, BE IT RESOLVED BY THE CITY OF LUBBOCK, TEXAS.
I.
That the improvements on said portions of the abovementioned streets be
and the same are hereby accepted and the City Engineer be and he is hereby
authorized to direct the payment of the City's portion of the cost and to
release escrow money.
II.
This resolution will take effect and be in force from and after its passage.
PASSED AND APPROVED THIS
ATTEST:
Evelyn Gaf=f ga, City 3ecr'et,S�ty
APPR VED TO CONTENT: (//
Dom' -0e npngs ty;Engineer
22ND DAY OF MAY 0.
Bill McAlister, Mayor
APOV'IS TO
if City *t ney •
y -
Sub -Unit
NS 2026
63-A
NS 2026 -
CONSOLIDATED FINAL ESTIMATE
LIVE OAK ADDITION, LOT 231
Accepted 5-22-1980
S.Y.
S.Y. Concrete S.Y. S.Y. L.F.
Paving L.F. Slab Valley Re -sur- C & G
Location 6" Base C & G Removal Gutter facing Removal
W. 1/2 of Hartford 1,464.65 .- 758.00
Ave. from NPL of Lot
231 to centerline of
70th St.
87.23
63-B N. 1/2 of 70th St. 1,450.80 614.20 18.10 24.44 83.73 46.14
from ELL of Indiana
Ave. to WLL of Hart-
ford Ave.
TOTAL QUANTITIES. 2,915.45 1,372.20 18.10 24.44 170.96 46.14
NOTE:
This construction was performed under a Lump Sum Contract for $23,980.00.