RESOLUTION
RESOLUTION #480 - 4/24/80
BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF LUBBOCK:
THAT the Mayor of the City of Lubbock BE and is hereby authorized and
directed to accept and execute for and on behalf of the City of Lubbock Change
Orders No. 3, No. 4, and No. 5, to an agreement with Talon Construction Company
for general, mechanical and electrical work in connection with the Holly
Avenue Power Station, Steam Unit No. 2, attached herewith which shall be
spread upon the minutes of the Council and as spread upon the minutes of this
Council shall constitute and be a part of this Resolution as if fully copied
herein in detail.
Passed by the City Council this 24th day of April ,1980.
ATTEST:
r
= f"Evelyn Gafig^a, ity Sedreea Treasurer
APPROVED AS TO"CONTENT:
J#y W#d9worth, Productiori Superintendent
Lubbock Power and Light
APPROVED AS TO FORM:
Susan M. Tom, Assistant City Attorney
r
00
"Orr JIV or If
BILL MCALI TER, MAYOR
}
CHANGE ORDEk
ENGINEER'S COPY
If this order is satisfactory, the owner is re-
quested to please sign and return Contractor's
and Engineer's copies to the Engineers.
TIPPETT & GvL E • CONSULTING ENGINEER
AEILME, TEXAS
ENGINEER'S JOB No. LB -300, LB -400, LB -5+
CHANGE. ORDER No. 3
ISSUED DATE November 10 -1978
AMOUNT (Plus or Minus) $ 24.251.69
TO Talon Construction Company CONTRACTOR
FOR Construction Additions IN CONNECTION'WITH
General, Mechanical E Electrical Construction, Holly Avenue Power Station
FOR OWNER Lubbock Power t Light, City of Lubbock, Texas
YOUR PROPOSAL FOR MAKING THE FOLLOWING CHANGES HAS BEEN ACCEPTED:
M 1. Furnishing and Installing a Brine Storage Tank and associated accessories, including
pumps, piping controls, etc., to accordance with your letter of December 15. 1977,
In the.amount of ;12,751.20.
M 2. Furnish and install six pressure switches for the boiler feed pump lubricating all
system In accordance with your letter of February 11, 1977, for the total amount
of $774.88.
M 3. Substitute embossed aluminum lagging for smooth aluminum lagging on all equipment
and piping In accordance with your letter of December 15, 1977, for the totai.price
of $747.50•
M 4. Additional pipe sleeve under the road for the coaling tower blowdown tine In
accordance with your letter of June 21, 1977, in the amount of $1,435.00.
j►�
S. Modifications to the eight inch gas line to eliminate Interference between'the gas
line and an electrical duct bank in accordance with your letter of June 21, 1977,
1n the amount of $834.90.
M 6. Extend gantry crane rails to enable lifting roof hatches without special rigging In
accordance with your ietter of October 28, 1977, in the amount of $799.76.'
M 7• Install auxiliary steam' crossover between Units i & 2 for fuel all atomizing in
accordance with your letter of May 24, 1978, in the amount of $4.984.00.
M 8. Modification of pipe hangers BFDH25 and BFDH26 to accommodate boiler thermal
expansion In accordance with your letter of September 12, 1978, In the amount
of.$1,385.48.
9. Provide power and control circuits to duplex sump pumps,ln accordance with your
letter of May 16, 1977. -In the amount of $:538.97.
THE AMOUNT OF THE CONTRACT WiLL BE (INCREASED) X(ib1fK ) IN THE SUM ON
TWENTY-FOUR THOUSAND; -TWO HUNDRED FIFTY-ONE DOLLARS AND 69/100 DOLLARS (S 24.251.69 )
WITH *XI0kAX9XP=W (NO CHANGE) IN THE CONTRACT TIME OF _COMP letIOn XX,1iXrS
OWNER'S APPROVAL a� TIPPETT b GEE, INC. ENGINEER
DATE 1 ''f 3 ' 19 By •
A. F. Clevenger. P.E
} CHANGE ORDEk
ENGINEER'S COPY
If this order is satisfactory, the owner is re-
quested to please sign and return Contractor's
and Engineer's copies to the Engineers.
TIPPETT & Get
ABILENE, TEXAS
• CONSULTING ENGINEERS
ENGINEER'S JOB No. LB -300, 400, 6 500
ZZ 191% CHANGE ORDER No. Four
�, ISSUED DATE February 8, 19 79
AMOUNT (Plus dcAgsj s 3,283.89
TO TALON CONSTRUCTION COMPANY
CONTRACTOR
FOR General, Mechanical, 6 Electrical Construction IN CONNECTION WITH
Holly Avenue Power Station, Unit No. 2
FOR OWNER LUBBOCK POWER & LIGHT, Lubbock Texas
YOUR PROPOSAL FOR MAKING THE FOLLOWING CHANGES HAS BEEN ACCEPTED:
Charges for field correction on the isolated Phase Bus iS.Surge Protection Potential
Transformer Cubicle for painting and fabrication errors -------------------------- $3,283.85
r� J -i9 i/--17 C-1 G' Cv i ? of e A /3, M14 S /,SCC'
` THE AMOUNT OF THE CONTRACT WILL BE (INCREASED) UM) IN THE SUM OF:
Three Thousand, Two Hundred Eighty-three 89/100ss-------------- DOLLARS ($ 3.283.89
WITH �t�j'{fl�E' (NO CHANGE) IN THE CONTRACT TIME OF completion DAYS
OWNER'S APPROVAL ` ' ' ENGINEER
DATE Z •- Z� 7 9 19 By T 1 PPETT GEE, INC.
CHANGE ORDER
OWNER'S COPY
If this order is satisfactory, the owner is re-
quested to please sign and return Contractor's
and Engineer's copies to the Engineers.
TIPPETT & GEE a CONSULTING ENGINEERS
AWLENE, TEXAS
ENGINEER'S JOB No. LB-300,LB-400,LB-500
CHANGE ORDER No. 5
ISSUED DATE April 12, 19 80
AMOUNT (Plus or iN(d4Di) $ 1 +981 .72
TO Talon Construction CONTRACTOR
FOR General, Mechanical and Electrical Work IN CONNECTION WITH
Holly Avenue Power Station Steam Unit No. 2
FOR OWNER Lubbock Power and Light
YOUR PROPOSAL FOR MAKING THE FOLLOWING CHANGES HAS BEEN ACCEPTED:
As itemized on the attached sheets.
THE AMOUNT OF THE CONTRACT WILL BE (INCREASED) OWAftM IN THE SUM OF:
One Thousand Nine Hundred Eighty -One and 72/100 DOLLARS (s 1,981.72 )
WITH XX MWZj)(X®(K X(NO CHANGE) IN THE CONTRACT TIME Qj( x)W6
) 7 /� )
OWNER'S APPROVAL A.L49 , T I PPP�ETT & GEE, INC. ENGINEER
DATE - �� /t/ Iq �Q By u.
A. F. Clevenger, WE.
RE: Summary description of Change Order No. 5
General, Mechanical and Electrical Construction
Holly Avenue Power Station, Steam Unit No. 2
Lubbock Power S Light
1.
Additional concrete for brine tank base
$ 277.50
2.
Extension of condenser waterbox vents
180.00
3.
Relocate cable tray T-11 in Unit 1 area to -
avoid interference with existing 3 -inch air
pipe
105.38
4.
Relocate cable tray -T-2 in Un]t 1 area to
avoid interference with existing conduits
87.81
5.
Add junction boxes to the surge protection
cubicles for cable termination
239.60
6.
Modify bus duct -support. pads-
207.23 _.
7.
Add penetration sleeves and seal sJor-two:.,_.
six- inch-gas..headers-and one six.inch.sbal air
line
72.20
8.
Furnish two auxiliary relays for condensate
pump control
456.30
9.
Replace motor starter overload headers in
motor control center
131.66
10.
Add turbine, overspeed trip switch and low
oil level trip switch to wiring
40.36
11.
Furnish and install two auxiliary relays for
circulating water pumps
168.88
12.
Relocate turbine stop valve drain entry at
miscellaneous drain tank
188.10
13.
Revise fuel oil piping to install flow trans-
mitters
566.29
14.
Add relay and box at water treatment building
153.86
15.
Reroute drain line from water treatment building
576.32
16.
Repair south branch of main plant driveway
450.00
17.
Condensate pump repair
(-) 452.41
18.
Conduit and wiring to connect additional switch
on gas valve FG -2B
296.41
19.
Change elastomeric roofing color to red
660.00
• 4y�
20. Revise Unit 1 condensate piping
21. Add 1/2" threadolet on fuel oil return
and make boiler repairs during week -end
shutdown
22. Insulate constant head chamber and piping
added by Owner
23. Install infrared flame detector cable in
separate conduits from each burner cabinet
to burner front
24. Relocate 6" piping connection on boiler
25. Credit to Owner for future repair of
Valve AS -12G, sootblower crossover line
26.-. Credit to Owner for unused portion of
cable testing" allowance
27*- Credit to Owner: -for _possible -future _repairs
on V inch sump -discharge piping
28.: 6 poles -bulbs x heads 200 each
29. 5 heads 131.34, each
30. 5 bulbs 24.88 each
31. 2 poles damaged by Talon
1 head x bulbe 131.34 + 24.88
32. Miscellaneous start-up and warranty
labor performed by LP&L personnel at
request of Talon Construction Co.
33. Calibrate and place in service the fuel oil
suction strainer differential pressure
switch
34. Dry well in pH house not put in by Talon
Construction Co.
TOTAL
$3,279.10
180.00
867.69
650.77
508.00
(-) 100.00
(-) 500.12
(-)1,700.00
(-)1,200.00
(-) 656.70
(-) 124.40
(') 254.00
(-) 156.22
(-)2,886.77
(-) ' •46.32'
(-) 284.80
$1,981.72