HomeMy WebLinkAboutResolution - 627 - CO#3 To Contract - Kerr Co - 1979 Assessment Paving Program, GWO 10,976 - 10/09/1980JWF:bs
RESOLUTION
BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF LUBBOCK:
RESOLUTION #621 -
(Reso. #86, 3/8/79
THAT the Mayor of the City of Lubbock BE and is hereby authorized and
directed to execute for and on behalf of the City of Lubbock a Change Order
No. 3 to the 1979 Assessment Paving Program (G.W.O. 10,976), with Kerr
Construction Company, a copy of which is attached herewith which shall be
spread upon the minutes of the Council and as spread upon the minutes of th
Council shall constitute and be a part of this Resolution as if fully copie
herein in detail.
by the City Council this 9th d
Evelyn°GaFffia, Ci y tary-Treasurer
APPROVED AS TO CONTENT:
I A,$ 7 a, -
Don JeriVings, C y Engineer
APPROVED AS TO FORM:
)
1
1019)
j
u
i
f
i
Resolution #627 - 10/9/80
Change Order Number 3
to GWO 10,976
TO: Kerr Construction Company
Box 888
Lubbock, Texas 79408
Gentlemen:
WHEREAS, it is desirable to make changes in the plans and specifications
for G.W.O. 10,976, being namely the following changes in the specifications:
1. The completion date of Unit -Numbers 2237-1 and 2237-2 be extended from
October 15, 1980 to December 15, 1980.
2. Statement 1 of the Deadline for Hot Mix Surfacing located in the proposal
and in Section I, paragraph 20, be revised to read as follows:
1. 1 1/2" surfacing with T.H.D. Type "C" A.C. will be permitted
after October 15 and before December 15 provided the Contrac-
tor abides by the following restrictions:
A. The surfacing shall be guaranteed by a letter from the Con-
tractor for a period of one (1) year after acceptance of
the unit.
B. A dilute emulsion treatment of:a-_xate._.dete.rmi.ned_by the Engineer
will be applied to the surface within ten (10) days of the
placement of the surface.
C. The A.C. surface will have a minimum temperature of 300' F
immediately after placement by the lay -down machine.
D. The A.C. surface will not be placed when the air temperature
is below 50° F.
E. Standby rollers shall be located at the job site for immediate
use if needed.
Original Amount of Contract G.W.O. 10,976 $1,694,618.04
Increased by Change Order No. 1 38,261.44
Increased by Change Order No. 2 204,081.32
Increased by Change Order No. 3 0.00
Total Amount of Contract $1,936,960.80
THIS AGREEMENT WITNESSETH: In consideration of the mutual advantages
gained, the Owner and the Contractor agree to the changes shown herein and
in the revised plans. The Contractor agrees to proceed with construction and
to adhere to applicable specifications, under the direction of the Engineer.
Furthermore, the parties agree that the original contract between the Owner
and the Contractor shall be modified to.the extent herein indicated.
IN WITNESS WHEREOF, the Owner and the Contractor have hereto set their
hands this 9th day of October, 1980.
Kerr Construction Company
(Contractor)
By 10,Title:
CITY OF LUBBOCK
(Owner)
By
Bill McAlister, Mayor
RECOMMENDED
Don J nin , City Engineer
APPROVED AS TO FORM:
&O'n C. Ross, Jr., City Attorney
Attest:
elyn G fga, Ci retary
FOR APPROV
Lar y ingham, i Manager