RESOLUTION
BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF LUBBOCK:
THAT the Mayor of the City of Lubbock is authorized and directed to
execute for and on behalf of the City of Lubbock Change Order No. 3 to Phase
No. 1 Renovation of Plant No. 1, S.E. Water Reclamation Plant, said change
order to be entered into with Anthony Mechanical, Inc., the contractor on said
phase of this project, a copy of which change order is attached hereto and
made a part hereof.
Passed by the City Council this 25th day of September , 1980.
BI MCALISTER, MAYOR
-ATTEST:
Evhlyn ,Oaffga, 'City SerTreasurer
-APPROVED AS'TO CONTENT:
y Wils C. senior Civil Engineer,
Water UlFilities
APPROVED AS TO FORM:
J.V'th Fullingim, Asst. City At ney
TO: Anthony Mechanical, Inc.
P.O. Box 2706
Lubbock, Texas 79408
Original Amount of Contract
Change Order #1
Amended Amount of Contract
Original Date of Completion
Change Order #2 (Additional Time of Completion)
Amended Date of Completion
Change Order #3
Amended Amount of Contract
RESOLUTION #618 — 9/25/80
Change Order No. 3
Phase No. 1 Renovation of Plant No.
S.E. Water Reclamation Plant
G. W. 0. 10982
$ 408,059.00
1,599.00
409,658.00
September -16, 19.80
19::weeks
January 27, 1981
$ 1,413.00
$ 411,071.00
WHEREAS, it is desirable to make changes in the plans and specifications
for this project:
THIS AGREEMENT WITNESSETH: In consideration of the mutual advantages
gained, the Owner and the Contractor agree to the change shown herein and
in the attached exhibits and data, and the Owner and the Contractor agree
that the original contract between them shall be modified and amended to the
extent herein indicated.
IN WITNESS WHEREOF, the Owner and the Contractor have hereto set their
hands this the 25th day of September, 1980.
Anthon Mechanical, Inc. CITY OF L K
OWNER
By �yJ
By%%' ! .
ayor
ATTEST:
s
RECVNDED FpR APPROVAL:
C ief ngineer, Water Utilities
Engi eying
Attachment to Change Order No. 3
Anthony Mechanical, Inc.
G.W.O. 10982
Explanation of Change
Furnishing paint and painting.two trickling filterdistributors. Each
distributor has four distribution arms. The cost of painting -is based on one
coat of Tnemec coal tar epoxy top coat #A6H413 sprayed with a dry coat thick-
ness of approximately 16 mils.
Breakdown of Change
Furnishing paint and labor $ 1284.55
10% mark-up 128.45
Total amount of Change Order $ 1413.00