HomeMy WebLinkAboutResolution - 2011-R0106 - Change Order To Contract - Allen Butler Construction Inc. - 03/02/2011Resolution No. 2011—RO106
March 2, 2011
Item No. 5.5
RESOLUTION
BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF LUBBOCK:
THAT the Mayor of the City of Lubbock is hereby authorized and directed to
execute for and on behalf of the City of Lubbock, Change Order No. 1 to that certain
Contract by and between the City of Lubbock and Allen Butler Construction, Inc., 10-
022 -MA, and related documents. Said Change Order No. 1 is attached hereto and
incorporated in this resolution as if fully set forth herein and shall be included in the
minutes of the City Council.
Passed by the City Council on March 2, 2011
TOM MARTIN, MAYOR
Rebec a Garza, City Secretary
APPROVED AS TO CONTENT:
� n
Marsha Reed, P.E., Chie Operations Officer
APPROVED AS TO FORM:
X.ad�Weaver, Assistant City Attorney
vw:ccdocs/RES.ChgOrd#]Contract-Allen Butler
January 3, 2011
CITY OF LUBBOCK
CHANGE ORDER
Change Order #: I
Contractor: Allen Butler Construction, Inc.
Date:
1-26-2011
BID/ITB/RFP #:
ITB 10 -022 -MA
Contract #:
9295
Project Name: Indiana Ave. 103` to FM 1585
"Change Order" means a written order to a Contractor executed by the Owner in accordance with the contract authorizing an
addition to, deletion from, or adjustment or revision of the requirements of the contract documents, or an adjustment to the
compensation payable to Contractor, or to the time for performance of the contract and completion of the Project, or a
combination thereof, which does not alter the nature of the thing to be constructed and is an integral part of the project objective.
Adjustments to "Estimated Quantities" to a line item in a Unit Price contract do not require a Change Order. All work that alters
the nature of the thing to be constructed or that is not an integral part of the project objective must be let out for public bid.
Description of change (alteration, deviation, addition, or deletion) caused by conditions encountered during construction
not covered by the specifications and drawings of the project (attack additional pages ifnecessmy):
Amendment # 1 is for the addition of street lighting to the Contractor's tasks. Originally LP&.L had requested
to the lighting on the City's Capital Projects but is not able to follow through with that commitment at this time.
The contract time will also be increased by twenty three(23) working days due to changes to the Contract and
impendance by Utility Contractors.
Where the Change Order is negotiated, the Change Order must be fully documented and itemized as to costs, including material
quantities, material costs, taxes, insurance, employee benefits, other related costs, profit and overhead. Where certain unit prices
arc contained in the initial contract, no deviations are allowed in computing negotiated change order costs.
ITEMIZED COSTS MUST BE FULLY DOCUMENTED AND ATTACHED TO THIS FORM.
ITEM DESCRIPTION
A. ORIGINAL CONTRACT VALUE:
B. AMOUNT OF THIS CHANGE ORDER: Council approval required ifover 525.000
C. PERCENT OF CONTRACT VALUE THIS CHANGE ORDER (B/A):
D. AMOUNT OF PREVIOUS CHANGE ORDERS:
E. TOTAL AMOUNT OF ALL CHANGE ORDERS (B+D):
F. PERCENT OF CONTRACT OF ALL CHANGE ORDERS (E/A): 25%Maximum
G. NEW CONTRACT AMOUNT (A+E):
AMOUNT
$8,297,936.95
$70,200.00
0.8%
$0
$70,200.00
0.8%
$8,368,136.95
It is mutually agreed that the above dollar amount and the time extension, as applicable, as set forth in this Change Order constitutes
full compensation to the Contractor for all costs, expenses and damages to the Contractor, whether direct, consequential or otherwise,
in anyway incident to, or arising out of or resulting directly or indirectly; from the work performed or modified by the Contractor
under this Change Order.
/K 2
Date (2) PROJECT ARC CT/ENGINEER Date
Approved asw on d
--
(3) OWNER'S REPRESENTATIVE Date
(5) CAPUAL PROJECTS MANAGER Date
Change Orders over $25,000 require a Contract Cover Sheet and the following signatures.
Date
CITY OF K �A T: 3/2/11 3/2/11
(7) MA OR Date (8) CIT SECRETARY Date
Council Date: March 2, 2011 Agenda Item #: 5.5 Resolution #: 201 — 0106
PWC -045 (Rev 01108)
Kimley-Horn
and Associates, Inc.
February 9, 2011
Mr. Neil Welch, P.E.
City of Lubbock Public Works
P.O. Box 2000
Lubbock, TX 79457
Re: Indiana Ave. Reconstruction
Change Order #I — Street Lighting and Additional Contract Time
KHA No. 063126004
Dear Mr. Welch:
Attached is Change Order #1 for the Indiana Ave. Reconstruction project. The
change order addresses two separate items. First, the City wishes to add the
installation of street lighting to the construction contract. The original
construction contract didn't include installation of the street lighting because
LP&L had requested to install the street lighting themselves. Since they are not
able to meet that commitment at this time, the work needs to be added to the
construction contract.
The second item is for the extension of contract time to perform the work. Early
in the project the contractor was unable to fully mobilize and proceed with the
work because franchise utility relocations were not complete and clear. Due to
the delay in relocating the franchise utilities and the City's desire to install final
asphalt paving in warmer temperatures in March instead of February, the City
wishes to increase the contract time by twenty-three (23) working days.
Kimley-Horn and Associates, Inc. has reviewed the request and recommends
approval of Change Order #1. Thank you for the opportunity to be of service to
the City of Lubbock. If you have any questions or comments, please do not
hesitate to call.
Very truly yours,
KIMLEEY-HORN AND ASSOCIATES, INC,
G. Brad Tribble, P.E,
GBT/jlp
Attachment - Change Order #I
K:1LAC_Roadway%063126004_Lub_lndiaaa_RPRICORR1C41 L. I doe
2
TEL 214 420 5500
FAX 214 420 5680
■
Sine 275
2201 West Royal Lane
Iwg, Texas
75063-3206
ALLEN BUTLER CONSTRUCTION, INC.
#24 SOUTH LAKESHORE DRIVE
RANSOM CANYON, TEXAS 79336
PHONE: 806-745-7498 FAX: 806-745-7577
January 26, 2011
Mr. Neil Welch
City of Lubbock
1625 —13"' Street
Lubbock, Texas 79401
PROJECT: INDIANA AVE. PAVING IMPROVEMENTS 103RD ST TO FM 1585
Dear Mr. Welch:
As requested by COL, we offer the following changes as listed below:
CHANGE ORDER
Parts: Approximately 22,OOOLF of #2 triplex Conch XL cable,
wedge clamps, dead end automatics, eyebolts, compression
fittings and all necessary hardware to complete the installation. $31,200.00
Labor: includes a crew of joumeymen electricians. $22,800.00
ui meat: $9,500.00
SUB ITEM TOTAL
CONTRACTORS MARKUP
ADDITION FOR BONDING
CHANGE ORDER TOTAL
Please let us know if you have questions.
Rick Humphries
Sr. Project Manager
Allen Butler Construction Co., Inc.
T $63,500.00
= $6,350.00
350.00
$70,200.00