HomeMy WebLinkAboutResolution - 2007-R0225 - Contract - Concrete Connections - Paving Improvements, Sidewalk And Drainage - 05_24_2007Resolution No. 2007 RO225
May 24, 2007
Item No. 5.22
RESOLUTION
BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF LUBBOCK:
THAT the Mayor of the City of Lubbock is hereby authorized and directed to
execute a public works Contract #7661 and any associated documents with Concrete
Connections of Plainview, Texas, for paving improvements for Sidewalk and Drainage
Project 2007, which Contract and any associated documents are attached hereto as
Exhibit A and made a part hereof for all intents and purposes.
Passed by the City Council this 24th day of May , 2007.
DAVID A. MILLER, MAYOR
ATTEST:
a Gar4#, City Secretary
OVfiD AS(TO CONTENT:
Loomis
City Manager/Transportation and Public Works
APPROVED AS TO FORM:
r
Don Vandiver, Attorne of C unsel
DDres/ConcreteConnectionsCon07Res
May 16, 2007
No Text
CITY OF LUBBOCK
REQUEST FOR PROPOSALS
•;
TITLE: PAVING IMPROVEMENTS FOR
SIDEWALK AND DRAINAGE PROJECT 2007
ADDRESS: LUBBOCK, TEXAS
RFP NUMBER: 07-717-BM
PROJECT NUMBER: 91053 and 90025
CONTRACT PREPARED BY: PUBLIC WORKS CONTRACTING OFFICE
City of Lubbock, TX
Public Works Contracting Office
Contractor Checklist for
RFP # 07-717-BM
Before submitting your proposal, :please ensure you have completed the following:
1.
Carefully read and understand the plans and specifications and properly complete the
PROPOSAL SUBMITTAL FORM. Proposal submittal form MUST be completed in blue or
black ink or by typewriter. Signatures must be original, in blue or black ink, and by hand.
Amounts shall be written in both words and numerals and in the event of a discrepancy the
amounts written in words shall govern. Include corporate seal and Secretary's signature. Identify
addenda received (if any). Include firm's FEDERAL TAX ID number or Owner's SOCIAL
SECURITY number.
2. V
Complete and sign the CITY OF LUBBOCK INSURANCE REQUIREMENT AFFIDAVIT.
This must include the signature of the agent or broker. Contractor's signature must be original.
3.
Complete and sign the SAFETY RECORD QUESTIONNAIRE. All "YES" responses must be
explained in detail and submitted with Bid / Proposal.
/
4.
Complete and sign the SUSPENSION AND DEBARMENT CERTIFICATION. Include fcrm's
FEDERAL TAX ID number or Owner's SOCIAL SECURITY number.
5. ✓
Carefully read the BASIS OF PROPOSALS and EVALUATION CRITERIA in paragraph 32 of
the General Instructions to Offeror's. Ensure ALL criteria are addressed in your submittal.
Evaluations cannot commence until all items are available to the evaluation committee.
6. V
Clearly mark the proposal number, title, due date and time and your company name and address
on the outside of the envelope or container.
7.
Include PROPOSAL BOND or CASHIER'S OR CERTIFIED CHECK as your proposal surety.
Failure to provide a proposal surety WILL result in automatic rejection of your proposal.
S. --4 Ensure your proposal is RECEIVED by the City of Lubbock Public Works Contracting Office
prior to the deadline. Late proposals will not be accepted.
FAILURE TO PROVIDE ANY OF THE ABOVE MAY RESULT IN YOUR PROPOSAL BEING
DEEMED NON -RESPONSIVE AND, THEREFORE, NOT FURTHER EVALUATED. PLEASE
INCLUDE THIS COMPLETED PAGE AS THE FIRST PAGE OF YOUR PROPOSAL SUBMITTAL.
r 0'1�4"J , �J t , &-
11Vv4�T,,ZA
Type or Print Company/Firm name
1.
2.
3.
4.
5.
p3p
6.
7.
8.
9.
10.
11.
1
4...i
INDEX
NOTICE TO OFFERORS
GENERAL INSTRUCTIONS TO OFFERORS
TEXAS LOCAL GOVERNMENT CODE § 271.116
PROPOSAL SUBMITTAL - PROPOSAL FOR UNIT PRICE CONTRACTS
PAYMENT BOND
PERFORMANCE BOND
CERTIFICATE OF INSURANCE
CONTRACT
GENERAL CONDITIONS OF THE AGREEMENT
CURRENT WAGE DETERMINATIONS
SPECIFICATIONS
NOTICE TO OFFERORS
NOTICE TO OFFERORS
RFP # 07-717-BM
Sealed proposals addressed to Bruce MacNair, Public Works Contracting Officer, City of Lubbock, Texas, will be
received in the office of the Public Works Contracting Officer, Municipal Building, 1625 13th Street, Suite 102, Lubbock,
Texas, 79401, 1:00 P.M. on May 10, 2007, or as changed by the issuance of formal addenda to all planholders, to furnish
all labor and materials and perform all work for the construction of the following described project:
"PAVING IMPROVEMENTS FOR SIDEWWALK AND DRAINAGE PROJECT 2007"
After the expiration of the time and date above first written, said sealed proposals will be opened in the office of
the Public Works Contracting Officer and publicly read aloud. It is the sole responsibility of the proposer to ensure that
his proposal is actually in the office of the Public Works Contracting Officer for the City of Lubbock, before the
expiration of the date above first written.
Proposals are due at 1:OOP.M. on May 10, 2007, and the City of Lubbock City Council will consider the
proposals on May 24, 2007 at the Municipal Building, 1625 13th Street, Lubbock, Texas, or as soon thereafter as may be
reasonably convenient, subject to the right to reject any or all proposals and waive any formalities. The successful
proposer will be required to furnish a performance bond in accordance with Chapter 2253, Government Code, in the
amount of 100% of the total contract price in the event that said contract price exceeds $100,000 and the successful
proposer will be required to furnish a payment bond in accordance with Chapter 2253, Government Code, in the amount
of 100% of the total contract price in the event that said contract price exceeds $25,000. Said statutory bonds should be
issued by a company carrying a current Best Rating of B or superior.
Offerors are required, whether or not a payment or performance bond is required, to submit a cashier's or certified
check issued by a bank satisfactory to the City of Lubbock, or a proposal bond from a reliable surety company, payable
without recourse to the order of the City of Lubbock in an amount not less than 5% of the total amount of the proposal
submitted as a guarantee that proposer will enter into a contract and execute all necessary bonds (if required) within ten
(10) business days after notice of award of the contract to him. FAILURE OF THE PROPOSER TO INCLUDE
PROPOSAL SECURITY WITH THE PROPOSAL SUBMITTAL SHALL CONSTITUTE A NONRESPONSIVE
- PROPOSAL AND RESULT IN DISQUALIFICATION OF THE PROPOSAL SUBMITTAL.
It shall be each proposer's sole responsibility to inspect the site of the work and to inform himself regarding all
local conditions under which the work is to be done. It shall be understood and agreed that all such factors have been
thoroughly investigated and considered in the preparation of the proposal submitted. There will be a non -mandatory pre -
proposal conference on May 1, 2007 at 9:00 A.M., in the Municipal Building Training Conference Center, TCLOl,
16251P street, Lubbock, Texas.
_e Offerors may view the plans and specifications without charge at The Reproduction Company, 2102 Avenue Q,
Lubbock,Texas 79405. ONE SET OF PLANS AND SPECIFICATIONS MAY BE OBTAINED, AT THE CITY'S
EXPENSE, FROM THE REPRODUCTION COMPANY WITH A $100 REFUNDABLE DEPOSIT,
http://prr.thereproductioncompany.conl/, Phone: (806) 763-7770. Additional sets of plans and specifications may be
-- obtained at the proposer's expense.
Attention of each proposer is particularly called to the schedule of general prevailing rate of per diem wages
included in the contract documents on file in the office of the Public Works Contracting Officer of the City of Lubbock,
which document is specifically referred to in this notice to offerors. Each offerors attention is further directed to provision
of Article 5159a, Vernon's Ann. Civil St., and the requirements contained therein concerning the above wage scale and
payment by the contractor of the prevailing rates of wages as heretofore established by owner in said wage scale.
The City of Lubbock hereby notifies all offerors that in regard to any contract entered into pursuant to this
advertisement, minority and women business enterprises will be afforded equal opportunities to submit proposals in
response to this invitation and will not be discriminated against on the grounds of race, color, sex, disability, or national
origin in consideration for an award.
The City of Lubbock does not discriminate against persons with disabilities. City of Lubbock pre -
proposal meetings and proposal openings are available to all persons regardless of disability. If you require
special assistance, please contact the Public Works Contracting Office at (806) 775-2163 or waste to Post Office
Box 2000, Lubbock, Texas 79457 at least 48 hours in advance of the meeting.
CITY OF LUBBOCK
6&ux 0Vcv0Nrir
BRUCE MACNAIR,
PUBLIC WORKS CONTRACTING OFFICER
GENERAL INSTRUCTIONS TO OFFERORS
GENERAL INSTRUCTIONS TO OFFERORS
1 PROPOSAL DELIVERY TIME & DATE
2 The City of Lubbock is seeking written and sealed competitive proposals to furnish PAVING
IMPROVEMENTS FOR SIDEWALK AND DRAINAGE PROJECT 2007 per the attached
specifications and contract documents. Sealed proposals will be received no later than 1:00 P.M. CST,
May 10, 2007 at the office listed below. Any proposal received after the date and hour specified will be
rejected and returned unopened to the proposer. Each proposal and supporting documentation must be
in a sealed envelope or container plainly labeled in the lower left-hand corner: "RFP # 07-717-BM,
PAVING IMPROVEMENTS FOR SIDEWALK AND DRAINAGE PROJECT 2007" and the proposal
opening date and time. Offerors must also include their company name and address on the outside of
the envelope or container. Proposals must be addressed to:
Bruce MacNair, Public Works Contracting Officer
City of Lubbock
1625 13th Street, Suite 102
Lubbock, Texas 79401
1.1
Offerors are responsible for making certain proposals are delivered to the Public Works
Contracting Office. Mailing of a proposal does not ensure that it will be delivered on time or
delivered at all. If proposer does not hand deliver proposal, we suggest that he/she use some sort
of delivery service that provides a receipt.
1.2
Proposals will be accepted in person, by United States Mail, by United Parcel Service, or by
private courier service. No proposals will be accepted by oral communication, telephone,
electronic mail, telegraphic transmission, or telefacsimile transmission. THE CITY WILL NOT
ACCEPT FAX PROPOSALS.
1.3
The City of Lubbock reserves the right to postpone the date and time for opening proposals
-
through an addendum.
2 PRE -PROPOSAL MEETING
2.1
For the purpose of familiarizing offerors with the requirements, answering questions, and issuing
addenda as needed for the clarification of the Request for Proposals (RFP) documents, a non -
mandatory -pre -proposal meeting will be held 9:00 A.M., May 1, 2007 in the Municipal Building
--•
Training Conference Center, TCL01, 1625 131h Street , Lubbock, Texas. All persons attending the
meeting will be asked to identify themselves and the prospective proposer they represent.
2.2
It is the proposer's responsibility to attend the pre -proposal meeting though the meeting is not
mandatory. The City will not be responsible for providing information discussed at the pre -
proposal meeting to offerors who do not attend the pre -proposal meeting.
3 ADDENDA & MODIFICATIONS
3.1 Any changes, additions, or clarifications to the RFP are made by ADDENDA information
available over the Internet at http://www.RFPdeyot.com. We strongly suggest that you check
for any addenda a minimum of forty-eight hours in advance of the response deadline.
BUSINESSES WITHOUT INTERNET ACCESS may use computers available at most up blic
libraries.
3.2 Any proposer in doubt as to the true meaning of any part of the specifications or other documents
may request an interpretation thereof from the Public Works Contracting Office. At the request
of the proposer, or in the event the Public Works Contracting Office deems the interpretation to
be substantive, the interpretation will be made by written addendum issued by the Public Works
Contracting Office. Such addenda issued by the Public Works Contracting Office will be
available over the Internet at http://www.RFPd2pot.com and will become part of the proposal
package having the same binding effect as provisions of the original RFP. NO VERBAL
EXPLANATIONS OR INTERPRETATIONS WILL BE BINDING. In order to have a request
for interpretation considered, the request must be submitted in writing and must be received by
the City of Lubbock Public Works Contracting Office no later than five (5) days before the
proposal closing date.
3.3 All addenda, amendments, and interpretations of this solicitation shall be in writing. The City of
Lubbock shall not be legally bound by any amendment or interpretation that is not in writing.
Only information supplied by the City of Lubbock Public Works Contracting Office in writing or
in this RFP should be used in preparing proposal responses. All contacts that a proposer may
have had before or after receipt of this RFP with any individuals, employees, or representatives
of the City and any information that may have been read in any news media or seen or heard in
any communication facility regarding this proposal should be disregarded in preparing responses.
3.4 The City does not assume responsibility for the receipt of any addendum sent to offerors.
4 EXAMINATION OF DOCUMENTS AND REQUIREMENTS
4.1 Each proposer shall carefully examine all RFP documents and thoroughly familiarize itself with
all requirements before submitting a proposal to ensure that their proposal meets the intent of
these specifications.
- 4.2 Before submitting a proposal, each proposer shall be responsible for making all investigations
and examinations that are necessary to ascertain conditions and requirements affecting the
requirements of this Request for Proposals. Failure to make such investigations and
examinations shall not relieve the proposer from obligation to comply, in every detail, with all
provisions and requirements of the Request for Proposals.
4.3 Notices of any discrepancies or omissions in these plans, specifications, or contract
documents, shall be given to the Public Works Contracting Officer and a clarification
obtained before the proposals are received, and if no such notice is received by the Public
Works Contracting Officer prior to the opening of proposals, then it shall be deemed that
the proposer fully understands the work to be included and has provided sufficient sums in
its proposal to complete the work in accordance with these plans and specifications. If
proposer does not notify the Public Works Contracting Officer before offering of any
discrepancies or omissions, then it shall be deemed for all purposes that the plans and
specifications are sufficient and adequate for completion of the project. It is further agreed
that any request for clarification must be submitted no later than five (5) calendar days
prior to the opening of proposals.
5 PROPOSAL PREPARATION COSTS
5.1 Issuance of this RFP does not commit the City of Lubbock, in any way, to pay any costs incurred
in the preparation and submission of a proposal.
5.2 The issuance of this RFP does not obligate the City of Lubbock to enter into contract for any
services or equipment.
5.3 All costs related to the preparation and submission of a proposal shall be paid by the proposer.
6 TRADE SECRETS, CONFIDENTIAL INFORMATION AND THE TEXAS PUBLIC
INFORMATION ACT
6.1 If you consider any portion of your proposal to be privileged or confidential by statute or judicial
decision, including trade secrets and commercial or financial information, clearly identify those
portions.
6.2 The City of Lubbock will honor your notations of trade secrets and confidential information and
decline to release such information initially, but please note that the final determination of
whether a particular portion of your proposal is in fact a trade secret or commercial or financial
information that may be withheld from public inspection will be made by the Texas Attorney
General or a court of competent jurisdiction. In the event a public information request is
received for a portion of your proposal that you have marked as being confidential information,
you will be notified of such request and you will be required to justify your legal position in
writing to the Texas Attorney General pursuant to Section 552.305 of the Government Code. In
the event that it is determined by opinion or order of the Texas Attorney General or a court of
competent jurisdiction that such information is in fact not privileged and confidential under
Section 552.110 of the Government Code and Section 252.049 of the Local Government Code,
then such information will be made available to the requester.
6.3 Marking your entire proposal CONFIDENTIAL/PROPRIETARY is not in conformance with the
Texas Open Records Act.
7 LICENSES PERMITS TAXES
The price or prices for the work shall include full compensation for all taxes, permits, etc. that the
proposer is or may be required to pay.
8 UTILIZATION OF LOCAL BUSINESS RESOURCES
Prospective offerors are strongly encouraged to explore and implement methods for the utilization of
local resources, and to outline in their proposal submittal how they would utilize local resources.
9 CONFLICT OF INTEREST
9.1 The proposer shall not offer or accept gifts or anything of value nor enter into any business
arrangement with any employee, official or agent of the City of Lubbock.
9.2 By signing and executing this proposal, the proposer certifies and represents to the City the offeror
has not offered, conferred or agreed to confer any pecuniary benefit or other thing of value for the
receipt of special treatment, advantage, information, recipient's decision, opinion, recommendation,
vote or any other exercise of discretion concerning this proposal.
10 CONTRACT DOCUMENTS
10.1 All work covered by the contract shall be done in accordance with contract documents described
in the General Conditions.
10.2 All offerors shall be thoroughly familiar with all of the requirements set forth on the contract
documents for the construction of this project and shall be responsible for the satisfactory
completion of all work contemplated by said contract documents.
I I PLANS FOR USE BY OFFERORS
It is the intent of the City of Lubbock that all parties with an interest in submitting a proposal on the
project covered by the contract documents be given a reasonable opportunity to examine the documents
and prepare a proposal without charge or forfeiture of deposit. The contract documents may be
examined without charge as noted in the Notice to Offerors.
12 PROPOSER INQUIRIES AND CLARIFICATION OF REQUIREMENTS
12.1 It is the intent and purpose of the City of Lubbock that this request permits competitive
proposals. It shall be the offerors responsibility to advise the Public Works Contracting Officer
if any language, requirements, etc., or any combinations thereof, inadvertently restricts or limits
the requirements stated in this RFP to a single source. Such notification must be submitted in
writing and must be received by the City of Public Works Contracting Office no later than five
(5) calendar days before the proposal closing date. A review of such notifications will be made.
12.2 NO PROPOSER _ SHALL REQUEST ANY INFORMATION VERBALLY. ALL
REQUESTS FOR ADDITIONAL INFORMATION OR CLARIFICATION
CONCERNING THIS REQUEST FOR PROPOSALS (RFP) MUST BE SUBMITTED IN
WRITING NO LATER THAN FIVE (5) CALENDAR DAYS PRIOR TO THE
PROPOSAL CLOSING DATE AND ADDRESSED TO:
BRUCE MACNAIR, PUBLIC WORKS CONTRACTING OFFICER
City of Lubbock
Public Works Contracting Office
1625 13" Street, Suite 102
Lubbock, Texas 79401
Fax: 806-775-3326 or 806-767-2275
Email: bmacnairAML1ubbock.us
RFPDepot: www.rfodgpot.com
13 TIME AND ORDER FOR COMPLETION
13.1 The construction covered by the contract documents shall be substantially completed within
FORTY (40) WORKING DAYS from the date specified in the Notice to Proceed issued by the
City of Lubbock to the successful proposer.
13.2 The Contractor will be permitted to prosecute the work in the order of his own choosing,
provided, however, the City reserves the right to require the Contractor to submit a progress
schedule of the work contemplated by the contract documents. In the event the City requires a
progress schedule to be submitted, and it is determined by the City that the progress of the work
is not in accordance with the progress schedule so submitted, the City may direct the Contractor
to take such action as the City deems necessary to ensure completion of the project within the
time specified.
14 PAYMENT
All payments due to Contractor shall be made in accordance with the provisions of the General
Conditions of the contract documents.
15 AFFIDAVITS OF BILLS PAID
., The City of Lubbock reserves the right, prior to final acceptance of this project to require the Contractor
--= to execute an affidavit that all bills for labor, materials and incidentals incurred in the construction of the
improvements contemplated by the contract documents have been paid in full and that there are no
claims pending, of which the Contractor has been notified.
16 MATERIALS AND WORKMANSHIP
The intent of these contract documents is that only materials and workmanship of the best quality and
grade will be furnished. The fact that the specifications may fail to be sufficiently complete in some
detail will not relieve the Contractor of full responsibility for providing materials of high quality and for
protecting them adequately until incorporated into the project. The presence or absence of a
representative of the City on the site will not relieve the Contractor of full responsibility of complying
with this provision. The specifications for materials and methods set forth in the contract documents
provide minimum standards of quality, which the Owner believes necessary to procure a satisfactory
proj ect.
17 GUARANTEES
17.1 All equipment and materials incorporated in the project and all construction shall be guaranteed
against defective materials and workmanship. Prior to final acceptance, the Contractor shall
furnish to the Owner, a written general guarantee which shall provide that the Contractor shall
remedy any defects in the work, and pay for any and all damages of any nature whatsoever
resulting in such defects, when such defects appear within ONE year from date of final
acceptance of the work as a result of defective materials or workmanship, at no cost to the Owner
(City of Lubbock).
17.2 Notwithstanding any provisions contained in the contractual agreement, the Contractor
represents and warrants fault -free performance and fault -free result in the processing date and
date -related data (including, but not limited to calculating, comparing and sequencing) of all
hardware, software and firmware products delivered and services provided under this Contract,
individually or in combination, as the case may be from the effective date of this Contract. Also,
the Contractor warrants calculations will be recognized and accommodated and will not, in any
way, result in hardware, software or firmware failure. The City of Lubbock, at its sole option,
may require the Contractor, at any time, to demonstrate the procedures it intends to follow in
order to comply with all the obligations contained herein.
17.3 The obligations contained herein apply to products and services provided by the Contractor, its
sub -contractor or any third party involved in the creation or development of the products and
services to be delivered to the City of Lubbock under this Contract. Failure to comply with any
of the obligations contained herein, may result in the City of Lubbock availing itself of any of its
rights under the law and under this Contract including, but not limited to, its right pertaining to
termination or default.
17.4 The warranties contained herein are separate and discrete from any other warranties specified in
this Contract, and are not subject to any disclaimer of warranty, implied or expressed, or
limitation to the Contractor's liability which may be specified in this Contract, its appendices, its
schedules, its annexes or any document incorporated in this Contract by reference.
18 PLANS FOR THE CONTRACTOR
The contractor will, upon written request, be furnished up to ten sets of plans and specifications and related
contract documents for use during construction. Plans and specifications for use during construction will
only be furnished directly to the Contractor. The Contractor shall then distribute copies of plans and
specifications to suppliers, subcontractors or others, as required for proper prosecution of the work
contemplated by the Contractor.
19 PROTECTION OF THE WORK
The Contractor shall be responsible for the care, preservation, conservation, and protection of all
materials, supplies, machinery, equipment, tools, apparatus, accessories, facilities, and all means of
construction, and any and all parts of the work whether the Contractor has been paid, partially paid, or
not paid for such work, until the date the City issues its certificate of completion to Contractor. The City
reserves the right, after the proposals have been opened and before the contract has been awarded, to
require of a proposer the following information:
(a) The experience record of the proposer showing completed jobs of a similar nature to the one
covered by the intended contract and all work in progress with bond amounts and percentage
completed.
,,,. (b) A sworn statement of the current financial condition of the proposer.
(c) Equipment schedule.
20 TEXAS STATE SALES TAX
20.1 This contract is issued by an organization which qualifies for exemption provisions pursuant to
provisions of Article 20.04 of the Texas Limited Sales, Excise and Use Tax Act.
- 20.2 The Contractor must obtain a limited sales, excise and use tax permit which shall enable him to
buy the materials to be incorporated into the work without paying the tax at the time of purchase.
21 PROTECTION OF SUBSURFACE LINES AND STRUCTURES
It shall be the Contractor's responsibility to prosecute the work contemplated by the contract documents
in such a way as to exercise due care to locate and prevent damage to all underground pipelines, utility
lines, conduits or other underground structures which might or could be damaged by Contractor during
_ the construction of the project contemplated by these contract documents. The City of Lubbock agrees
that it will furnish Contractor the location of all such underground lines and utilities of which it has
knowledge. However, such fact shall not relieve the Contractor of his responsibilities aforementioned.
All such underground lines or structures cut or damaged by Contractor during the prosecution of the
work contemplated by this contract shall be repaired immediately by Contractor to the satisfaction of the
City of Lubbock, Texas, at Contractor's expense.
22 BARRICADES AND SAFETY MEASURES
The contractor shall, at his own expense, furnish and erect such barricades, fences, lights and danger
signals, and shall take such other precautionary measures for the protection of persons, property and the
work as may be necessary. The Contractor will be held responsible for all damage to the work due to
failure of barricades, signs, and lights to protect it, and when damage is incurred, the damaged portion
shall be immediately removed and replaced by Contractor at his own cost and expense. The Contractor's
responsibility for maintenance of barricades, signs, and lights shall not cease until the date of issuance to
Contractor of City's certificate of acceptance of the project.
23 EXPLOSIVES
23.1 The use of explosives will not be permitted unless written permission to do so is obtained by the
Contractor from the City. In all cases where written permission is obtained for the use of
explosives, the Contractor shall assume full responsibility for all damage, which may occur as a
direct or indirect result of the blasting. In addition, in all cases where explosives are authorized
- to be used, the Contractor shall use utmost care so as not to endanger life or property and the
Contractor shall further use only such methods as are currently utilized by persons, firms, or
corporations engaged in similar type of construction activity.
23.2 Explosive materials shall not be stored or kept at the construction site by the Contractor.
23.3 In all cases where explosives are to be used during the construction of the project contemplated
by this contract, it shall be the duty of the Contractor to notify each utility company having
structures (above or below the ground) in proximity to the site of the work of Contractor's
intention to use explosives, and such notice shall be given sufficiently in advance to enable the
companies to take such steps as they may deem necessary to protect their property from injury.
Such notice, however, shall not relieve the Contractor of responsibility for any damage resulting
from his blasting operations.
_. 24 CONTRACTOR'S REPRESENTATIVE
The successful proposer shall be required to have a responsible local representative available at all times
while the work is in progress under this contract. The successful proposer shall be required to furnish
the name, address and telephone number where such local representative may be reached during the time
that the work contemplated by this contract is in progress.
25 INSURANCE
25.1 The Contractor shall not commence work under this contract until he has obtained all insurance
as required in the General Conditions of the contract documents, from an underwriter authorized
to do business in the State of Texas and satisfactory to the City. Proof of coverage shall be
furnished to the City and written notice of cancellation or any material change will be provided
ten (10) days in advance of cancellation or change. All policies shall contain an agreement on
the part of the insurer waiving the right to subrogation. The Contractor shall procure and carry at
his sole cost and expense through the life of this contract, insurance protection as hereinafter
specified. Coverage in excess of that specified herein also shall be acceptable. Such insurance
shall be carried with an insurance company authorized to transact business in the State of Texas
and shall cover all operations in connection with this contract, whether performed by the
Contractor or a subcontractor, or separate policies shall be provided covering the operation of
each subcontractor. A certificate of insurance specifying each and all coverages shall be
submitted before contract execution.
25.2 PROOF OF COVERAGE SHALL BE FURNISHED TO THE CITY OF LUBBOCK IN
THE FORM OF A CERTIFICATE OF INSURANCE. THE INSURANCE
CERTIFICATES FURNISHED SHALL NAME THE CITY OF LUBBOCK AS A
PRIMARY ADDITIONAL INSURED AND PROVIDE A WAIVER OF SUBROGATION
IN FAVOR OF THE CITY OF LUBBOCK AS REQUIRED BELOW, OR IN THE
ALTERNATIVE, SHALL BE ACCOMPANIED BY A STATEMENT FROM THE
CONTRACTOR TO THE EFFECT THAT NO WORK ON THIS PARTICULAR
PROJECT SHALL BE SUBCONTRACTED. IT SHALL BE THE CONTRACTOR'S
RESPONSIBILITY TO PROVIDE TO THE OWNER ALL PROOF OF COVERAGE
INSURANCE DOCUMENTS INCLUDING WORKERS COMPENSATION COVERAGE
FOR EACH SUBCONTRACTOR.
26 LABOR AND WORKING HOURS
26.1 Attention of each proposer is particularly called to the schedule of general prevailing rate of per
diem wages included in these contract documents. The wage rate that must be paid on this
project shall not be less than specified in the schedule of general prevailing rates of per diem
wages as above mentioned. The proposer' attention is further directed to the requirements of
Article 5159a, Vernon's Annotated Civil Statutes providing for the payment of the wage
schedules above mentioned and the proposer's obligations thereunder. The inclusion of the
schedule of general prevailing rate of per diem wages in these contract documents does not
release the Contractor from compliance with any wage law that may be applicable. Construction
work under this contract requiring an inspector will not be performed on weekends or holidays
unless the following conditions exist:
26.1.1 The project being constructed is essential to the City of Lubbock's ability to provide the
necessary service to its citizens.
26.1.2 Delays in construction are due to factors outside the control of the Contractor. The
Contractor is approaching the penalty provisions of the contract and Contractor can show
_-, he has made a diligent effort to complete the contract within the allotted time.
-- 26.2 Before construction work requiring an inspector is to be performed on weekends or holidays, the
Contractor must notify the Owner's Representative not less than three full working days prior to
the weekend or holiday he desires to do work and obtain written permission from the Owner's
Representative to do such work. The final decision on whether to allow construction work
requiring an inspector on weekends or holidays will be made by the Owner's Representative.
26.3 In any event, if a condition should occur or arise at the site of this project or from the work being
done under this contract which is hazardous or dangerous to property or life, the Contractor shall
immediately commence work, regardless of the day of the week or the time of day, to correct or
alleviate such condition so that it is no longer dangerous to property or life.
27 PAYMENT OF EMPLOYEES AND FILING OF PAYROLLS
The contractor and each of his subcontractors shall pay each of his employees engaged in work on the
project under this contract in full (less mandatory legal deductions) in cash, or by check readily cashable
-- without discount, not less often than once each week. The Contractor and each of his subcontractors
engaged at the site of the work shall not later than the seventh day following the payment of wages, file
with the Owner's Representative, or Engineer, a certified, sworn, legible copy of such payroll. This shall
- contain the name of each employee, his classification, the number of hours worked on each day, rate of
pay, and net pay. The affidavit shall state that the copy is a true and correct copy of such payroll, that no
rebates or deductions (except as shown) have been made, or will in the future be made from the wages
- paid as shown thereon. The Contractor must classify employees according to one of the classifications
set forth in the schedule of general prevailing rate of per diem wages, which schedule is included in the
contract documents. The Contractor shall forfeit as a penalty to the City of Lubbock on whose behalf
this contract is made, ten dollars for each laborer, workman, or mechanic employed for each calendar
_ day, or portion thereof, such laborer, workman or mechanic is paid less than the wages assigned to his
particular classification as set forth in the schedule of general prevailing rate of per diem wages included
in these contract documents.
28 PROVISIONS CONCERNING ESCALATION CLAUSES
Proposals submitted containing any conditions which provide for changes in the stated proposal price
due to increases or decreases in the cost of materials, labor or other items required for the project will be
rejected and returned to the proposer without being considered.
29 PREPARATION FOR PROPOSAL
29.1 The proposer shall submit his proposal on forms furnished by the City. All blank spaces in the
form shall be correctly filled in and the proposer shall state the price both in words and numerals,
for which he intends to do the work contemplated or furnish the materials required. Such prices
shall be written in ink, distinctly and legibly, or typewritten. In case of discrepancy between the
price written in words and the price written in figures, the price written in words shall govern.
29.2 If the proposal is submitted by an individual, his name must be signed by him or his duly
authorized agent. If a proposal is submitted by a firm, association, or partnership, the name and
address of each member must be given and the proposal signed by a member of the firm,
association or partnership, or person duly authorized. If the proposal is submitted by a company
or corporation, the company or corporate name and business address must be given, and the
proposal signed by an official or duly authorized agent. Powers of attorney authorizing agents or
others to sign proposals must be properly certified and must be in writing and submitted with the
proposal. The proposal shall be executed in ink.
29.3 Each proposal shall be enclosed in a sealed envelope, addressed as specified in the Notice to
Offerors, and endorsed on the outside of the envelope in the following manner:
28.3.1 Proposer's name
28.3.2 Proposal for (description of the project).
_ 29.4 Proposal submittals may be withdrawn and resubmitted at any time before the time set for
opening of the proposals, but no proposal may be withdrawn or altered thereafter.
29.5 Pursuant to Texas Local Government Code 252.043(g), a competitive sealed proposal that
has been opened may not be changed for the purpose of correcting an error in the proposal
price. THEREFORE, ANY CORRECTIONS TO THE PROPOSAL PRICE MUST BE
- MADE ON THE PROPOSAL SUBMITTAL FORM PRIOR TO PROPOSAL OPENING.
30 BOUND COPY OF CONTRACT DOCUMENTS
Proposer understands and agrees that the contract to be executed by proposer shall be bound and include
the following:
(a) Notice to Offerors.
(b) General Instructions to Offerors.
(c) Proposer's Submittal.
(d) Statutory Bond (if required).
(e) Contract Agreement.
(f) General Conditions.
(g) Special Conditions (if any).
(h) Specifications.
(i) Insurance Certificates for Contractor and all Sub -Contractors.
(j) All other documents made available to proposer for his inspection in accordance with the Notice
to Offerors.
If Plans and Specifications are too bulky or cumbersome to be physically bound, they are to be
considered incorporated by reference into the aforementioned contract documents.
31 QUALIFICATIONS OF OFFERORS
The proposer may be required before the award of any contract to show to the complete satisfaction of
the City of Lubbock that it has the necessary facilities, ability, and financial resources to provide the
- service specified therein in a satisfactory manner. The proposer may also be required to give a past
history and references in order to satisfy the City of Lubbock about the proposer's qualifications. The
City of Lubbock may make reasonable investigations deemed necessary and proper to determine the
ability of the proposer to perform the work, and the proposer shall furnish to the City of Lubbock all
information for this purpose that may be requested. The proposer's proposal may be deemed not to meet
specifications or the proposal may be rejected if the evidence submitted by, or investigation of, the
proposer fails to satisfy the City of Lubbock that the proposer is properly qualified to carry out the
obligations of the contract and to complete the work described therein. Evaluation of the proposer's
qualifications shall include but not be limited to:
(a) The ability, capacity, skill, and financial resources to perform the work or provide the service
required.
(b) The ability of the proposer to perform the work or provide the service promptly or within the time
specified, without delay or interference.
(c) The character, integrity, reputation, judgment, experience, and efficiency of the proposer.
(d) The quality of performance of previous contracts or services.
(e) The safety record of the Contractor and proposed Sub -Contractors
Before contract award, the recommended contractor for this project may be required to show that he has
experience with similar projects that require the Contractor to plan his work efforts and equipment needs
with City of Lubbock specifications in mind. Demonstration of experience shall include a complete list
of ALL similar municipal and similar non -municipal current and completed projects for the past three
(3) years for review. This list shall include the names of supervisors and type of equipment used to
perform work on these projects. In addition, the Contractor may be required to provide the name(s) of
supervisor(s) that will be used to perform work on this project in compliance with City of Lubbock
specifications herein.
32 BASIS OF PROPOSALS AND SELECTION CRITERIA
The City of Lubbock will use the Competitive Sealed Proposals procurement method as authorized by
the Texas Legislature and further defined by Texas Local Government Code Section 271.116. The
selection criteria used to evaluate each proposal will include the following:
-- 32.1 60% Price.
_3 32.2 15% Resume and references of proposed job superintendent. City shall have an opportunity to
interview the job superintendent at a time to be named after receipt of proposals.
32.3 5% List of potential items from proposer that could reduce the cost of work, but result in the same
end product. List shall include suggestions of materials/assemblies, etc.
32.4 5% Insurance claims and litigation during the last three years.
32.5 5% Construction time.
32.6 10% List of subcontractors — DUE WITHIN TWO BUSINESS DAYS AFTER OPENING.
The estimated budget for the construction phase of this project is $ 60,000.
Proposals shall be made using the enclosed Proposal Submittal Form.
33 SELECTION
33.1 Selection shall be based on the responsible offeror whose proposal is determined to be the most
advantageous to the City of Lubbock considering the relative importance of evaluation factors included in
this RFP.
33.2 NO INDIVIDUAL OF ANY USING DEPARTMENT HAS THE AUTHORITY TO LEGALLY
AND/OR FINANCIALLY COMMIT THE CITY TO ANY CONTRACT, AGREEMENT OR
PURCHASE ORDER FOR GOODS OR SERVICES, UNLESS SPECIFICALLY SANCTIONED BY
THE REQUIREMENTS OF THIS REQUEST FOR PROPOSAL.
33.3 The City shall select the offeror that offers the best value for the City based on the published selection
criteria and on its ranking evaluation. The City shall first attempt to negotiate a contract with the selected
offeror. The City and its engineer or architect may discuss with the selected offeror options for a scope or
time modification and any price change associated with the modification. If the City is unable to negotiate
a contract with the selected offeror, the City shall, formally and in writing, end negotiations with that
offeror and proceed to the next offeror in the order of the selection ranking until a contract is reached or
all proposals are rejected.
33.4 In determining best value for the City, the City is not restricted to considering price alone, but may
consider any other factor stated in the selection criteria.
33.5 A proposal will be subject to being considered irregular and may be rejected if it shows
omissions, alterations of form, conditional alternate proposals, additions or alternates in lieu
of the items specified, if the unit prices are obviously unbalanced (either in excess of or below
reasonably expected values), or irregularities of any kind "
TEXAS LOCAL GOVERNMENT CODE § 271.116
SELECTING CONTRACTOR FOR CONSTRUCTION SERVICES
THROUGH COMPETITIVE SEALED PROPOSALS
§ 271.116. SELECTING CONTRACTOR FOR CONSTRUCTION SERVICES THROUGH
COMPETITIVE SEALED PROPOSALS.
(a) In selecting a contractor through competitive sealed proposals for construction, rehabilitation, alteration,
or repair services for a facility or for construction of a project to which Section 252.043(d-1) applies, a
governmental entity shall follow the procedures prescribed by this section.
(b) The governmental entity shall select or designate an engineer or architect to prepare construction
documents for the project. The selected or designated engineer or architect has full responsibility for complying
- with Chapter 1001 or 1051, Occupations Code, as applicable. If the engineer or architect is not a full-time
employee of the governmental entity, the governmental entity shall select the engineer or architect on the basis
of demonstrated competence and qualifications as provided by Section 2254.004, Government Code.
(c) The governmental entity shall provide or contract for, independently of the contractor, the inspection
services, the testing of construction materials engineering, and the verification testing services necessary for
acceptance of the facility or project by the governmental entity. The governmental entity shall select those
services for which it contracts in accordance with Section 2254.004, Government Code, and shall identify them
in the request for proposals.
(d) The governmental entity shall prepare a request for competitive sealed proposals that includes
construction documents, selection criteria, estimated budget, project scope, schedule, and other information that
contractors may require to respond to the request. The governmental entity shall state in the request for
proposals the selection criteria that will be used in selecting the successful offeror.
(e) The governmental entity shall receive, publicly open, and read aloud the names of the offerors and, if
any are required to be stated, all prices stated in each proposal. Not later than the 45th day after the date of
opening the proposals, the governmental entity shall evaluate and rank each proposal submitted in relation to
the published selection criteria.
(f) The governmental entity shall select the offeror that offers the best value for the governmental entity
based on the published selection criteria and on its ranking evaluation. The governmental entity shall first
attempt to negotiate a contract with the selected offeror. The governmental entity and its engineer or architect
may discuss with the selected offeror options for a scope or time modification and any price change associated
with the modification. If the governmental entity is unable to negotiate a contract with the selected offeror, the
governmental entity shall, formally and in writing, end negotiations with that offeror and proceed to the next
offeror in the order of the selection ranking until a contract is reached or all proposals are rejected.
(g) In determining best value for the governmental entity, the governmental entity is not restricted to
considering price alone, but may consider any other factor stated in the selection criteria.
PROPOSAL SUBMITTAL
PROPOSAL SUBMITTAL
UNIT PRICE PROPOSAL CONTRACT
IDATE: D -7
I PROJECT NUMBER: # 07-717-BM — PAVING IMPROVEMENTS FOR SIDEWALK AND DRAINAGE
PROJECT 2007
Proposal of �av�c.tz�.}-L 1^ .G�-1t1, (hereinafter called Proposer)
To the Honorable Mayor and City Council City of Lubbock, Texas (hereinafter called Owner)
Ladies and Gentlemen:
The Offeror, in compliance with your Request for Proposals for the construction of PAVING IMPROVEMENTS FOR
SIDEWALK AND DRAINAGE PROJECT 2007 having carefully examined the plans, specifications, instructions to
offerors, notice to offerors and all other related contract documents and the site of the intended work, and being familiar
with all of the conditions surrounding the construction of the intended project including the availability of materials and
labor, hereby intends to furnish all labor, materials, and supplies; and to construct the project in accordance with the plans,
specifications and contract documents, within the time set forth therein and at the price stated below. The price to cover
all expenses incurred in performing the work required under the contract documents.
Estimated
Item Quantity
No. & Unit Description of Item Total Amount
1. 7,250 SF Six-inch wide Portland cement concrete drainage channel City of Lubbock Class A concrete
g ty ,
including all subgrade preparation, reinforcement, and jointing, complete in place,
TOTAL ITEM #1: TMlz.d; O0UA-1z5 AV-'D 5&1LnJ`fV C&�J TS $ 3 ��b /SF( Z44 Z�✓� � )
(Unit Price Amounts shall be shown in both words and numerals. In case of discrepancy, the amount shown in words shall govern.)
2. 30 SY Type D HMAC paving repair adjacent to curb removal, including repair of base and asphalt
surface, complete in place.
TOTAL ITEM #2: Fl F7 f DOS-/rw Av A Na $ 5_0 '?�' /SY( 1 sZ) D DO )
(Unit Price Amounts shall be shown in both words and numerals. In case of discrepancy, the amount shown in words shall govern.)
3. 100 LF 30-inch curb and gutter, City of Lubbock Class A concrete, including subgrade
preparation and jointing, complete in place.
TOTAL ITEM #3: E;' HT-66-0 Vo �t A-�ZS Av,t-) Na Gt--,,jyS `� I goo$ I4 � /LF( )
(Unit Price Amounts shall be shown in both words and numerals. In case of discrepancy, the amount shown in words shall govern.)
4. 5 EACH City of Lubbock standard handicap ramps, including four foot square landings, and detectable
warning brick pavers, furnished and installed, complete in place.
S �31 STOTAL ITEM #4:G� r� D-42 "—)
(Unit Price Amounts shall be shown in both words and numerals. In case of discrepancy, the amount shown in words shall govern.)
Offeror's Initials
t
11
Estimated
Item Quantity
No. & Unit Description of Item Total Amount
5. 100 LF Remove and legally dispose of existing curb and gutter, including any remaining
miscellaneous concrete, and all necessary incidentals to complete the work.
TOTAL ITEM #5: 1 C r) Qow,,ArfA-1-XNO CAS $ f o 2F(
(Unit Price Amounts shall be shown in both words and numerals. In case of discrepancy, the amount shown in words shall govern.)
6. 9,360 SF Four -foot wide concrete sidewalk, City of Lubbock Class A concrete, including subgrade
preparation and all necessary incidentals to complete the work, furnished and installed,
complete in place.
TOTAL ITEM #6: `r1klzC�r D0t4Likt7J, AMI> _r" 4f,W'z, $ 3. /SF( Z1716)110. )
(Unit Price Amounts shall be shown in both words and numerals. In case of discrepancy, the amount shown in words shall govern.)
7. 3 EACH Remove existing trees, including disposal, backfill, and necessary incidentals to complete the
O 6a
TOTAL ITEM #7: rk'20 LLW /EA( I SD )
(Unit Price Amounts shall be shown in both words and numerals. In case of discrepancy, the amount shown in words shall govern.)
TOTAL PROPOSAL, ITEMS #1- #7:
MATERIALS: f *Tq 006-T"L14Mtf) TZLb if ow �i,( y s►x rNb c67/rS $
LABOR.rwI.41LV-�v6AfJD T1+VJ,6, gVJ/psti4 6QQr !!!$ (iVb Na cn-Ls, $ Z �, 3 .Z Sr �
TOTAL PROPOSAL
ITEMS #1 - #7: Si -11%/ EOWZ TADI'MOD SIX PIA4AbRg-b F-yP-W o/J6r b'u IO� to "le( .
(Unit Price Amounts shall be shown in both words and numerals. In case of discrepancy, the amount shown in words 1 govern.)
Offeror hereby agrees to commence the work on the above prol*ec on a date to be specified in a written "Notice
Proceed" of the Owner and to substantially complete the project within ( QO) # Days Completed by Contractor
( r-Dr l-LI W v9444,Jb aA `P5 ) Written Days Completed by Contractor WORKING DA!
thereafter as stipulated in the specifications and other contract documents. Offeror hereby further agrees to pay to Owl
as liquidated damages the sum of $200 (TWO HUNDRED DOLLARS) for each WORKING DAY in excess of the til
set forth herein above for completion of this project, all as more fully set forth in the general conditions of the contra
documents.
Offeror understands and agrees that this proposal submittal shall be completed and submitted in accordance
instruction number 29 of the General Instructions to Offerors.
Offeror understands that the Owner reserves the right to reject any or all proposals and to waive any formality
the proposing.
The Offeror agrees that this proposal shall be good for a period of sixty (60) calendar days after the
closing time for receiving proposals.
The undersigned Offeror hereby declares that he has visited the site of the work and has carefully examined 0
plans, specifications and contract documents pertaining to the work covered by this proposal, and he further agrees 1
commence work on the date specified in the written notice to proceed, and to substantially complete the work on which b
has proposed; as provided in the contract documents.
` Offeror's Initials
Offerors are'required, whether or not a payment or performance bond is required, to submit a cashier's check or certified
4 check issued by a bank satisfactory to the City of Lubbock, ora proposal bond from a reliable surety company, payable
without recourse to the order of the City of Lubbock in an amount not less than five percent (51/6) of the total amount of
the proposal submitted as a guarantee that offeror will enter into a contract, obtain all required insurance policies, and
execute all necessary bonds (if required) within ten (10) days after notice of award of the contract to him.
Enclosed with this proposal is a Cashier's Check or Certified Check for
Dollars ($ or a Proposal Bond in the sum of
d F P l a.,4AO Dollars ($ which it is agreed shall be collected and retained
by the Owner as liquidated damages in the event the proposal is accepted by the Owner and the undersigned fails
to execute the necessary contract documents, insurance certificates, and the required bond (if any) with the Owner
within ten (10) business days after the date of receipt of written notification of acceptance of said proposal;
otherwise, said check or bond shall be returned to the undersigned upon demand.
Offeror understands and agrees that the contract to be executed by Offeror shall be bound and include all contract
documents made available to him for his inspection in accordance with the Notice to Offerors.
Pursuant to Texas Local Government Code 252.043(a), a
competitive sealed proposal that has been opened may not be
changed for the purpose of correcting an error in the proposal
price. THEREFORE, ANY CORRECTIONS TO THE
PROPOSAL PRICE MUST BE MADE ON THE PROPOSAL
SUBMITTAL FORM PRIOR TO PROPOSAL OPENING.
(Seal if Offeror is a Corporation)
ATTEST:
Secretary
Offeror acknowledges receipt of the following addenda:
Addenda No.
Date.
Addenda No.
Date,
Addenda No.
Date
Addenda No.
Date
0
Date: s 7 - t
Authorized Signature
4jl*r� (l*" 5 6W.,-J
(Printed or Typed Name)
�✓tC.f7 0-P ►J t1 w`(j v, r4
Company
Address
Pt -A-, 0 V14.,
14A-L.&-
C�ty�
CouWbJ�
S
State
Telephone:
Zip Code
Fax:
FEDERAL TAX ID or SOCIAL SECURITY No.
za-.3q/.,-1s's&
M/WBE Firm: Woman Black American Native American
Hispanic American Asian Pacific American Other (Specify)
a
CITY OF LUBBOCK
INSURANCE REQUIVWUMNT AFFIDAM
To Be Cowpk 0ed by Offeror and Agent
And Auxabed to Proposal Submimi
L the undoliped Offam, oeriifj► duct the inumce requixe rents o=%Jn d m tWe proposal document have been
rsvisaod by me with the below idanti5ed Inauranee AgenyBroker. N I am awarded d& cmmt d by ttte City of Lubbock,
I w111 be able to, within ten (10) business days 28ar being noosed of mcb award by the City of Lubbock, Aunisb a valid
insuraaoe ae dficate to the City meeting all of the requkements defined in thus proposal.
1A U.4-� JZ,", V1 ni Wks Se�1an(1 —
M*stme) Contractor (Prkd)
CONMCrOR'S FIRM NAM: iv 'r^,
(Fibut or TYM)
CONTRACTOR'$ FIRM ADDRESS:_ -34%1 �R11'�trtGt,7i ��►,�Vt� 1 iG
-71ol a.
Name of ArmvBrokar. e4tcZ4"11.1A t--R L.,L
Agm / Broker (S )
Addsess of AgcnVBmker- 3 ira5 ly . 6t wa , 00« paC�d Fc 1 crd
AgenuBroker Telephone Numbw.. ( 7 jp 5 S`1 4
NOTE TO CONTRACTOR
it the tone requ bvon t specified above b not met, the City bae the right is reject this prepowd and award the
contract to aaeaw coafnretor. N you bave any gae0k as eoaeeraing tbose requiremmb, please mataet the Public
Weft Coatractina Offiimw for the City of Lubbeek at 006) 775-2163.
mopoBAL g omv-BM — PAWqG i1N.Pi vrAmNTS FOR SIDEWALK AND DRAINAGE PROJECT 1007
4
TOTAL P.02
0..
SAFETY RECORD QUESTIONNAIRE
(Must Be Submitted With Proposal Submittal)
The City of Lubbock City Council desires to avail itself of the benefits of Section 252.0435 of the Local Government
Code, and consider the safety records of potential contractors prior to awarding proposals on City contracts. Pursuant to
Section 252.0435 of the Local Government Code, City of Lubbock has adopted the following written definition and
criteria for accurately determining the safety record of a proposer prior to awarding proposals on City contracts.
The definition and criteria for determining the safety record of a proposer for this consideration shall be:
The City of Lubbock shall consider the safety record of the offerors in determining the responsibility thereof. The City may
consider any incidence involving worker safety or safety of the citizens of the City of Lubbock, be it related or caused by
environmental, mechanical, operational, supervision or any other cause or factor. Specifically, the City may consider, among
other things:
a. Complaints to, or final orders entered by, the Occupational Safety and Health Review Commission (OSHRC),
against the proposer for violations of OSHA regulations within the past three (3) years.
b. Citations (as defined below) from an Environmental Protection Agency (as defined below) for violations within
the past five (5) years. Environmental Protection Agencies include, but are not necessarily limited to, the U.S.
Army Corps of Engineers (USACOE), the U.S. Fish and Wildlife Service (USFWS), the Environmental
Protection Agency (EPA), the Texas Commission on Environmental Quality (TCEQ), the Texas Natural Resource
Conservation Commission (TNRCC) (predecessor to the TCEQ), the Texas Department of State Health Services
(DSHS), the Texas Parks and Wildlife Department (TPWD), the Structural Pest Control Board (SPCB), agencies
of local governments responsible for enforcing environmental protection or worker safety related laws or
regulations, and similar regulatory agencies of other states of the United States. Citations include notices of
violation, notices of enforcement, suspension/revocations of state or federal licenses or registrations, fines
assessed, pending criminal complaints, indictments, or convictions, administrative orders, draft orders, final
orders, and judicial final judgments.
C. Convictions of a criminal offense within the past ten (10) years, which resulted in bodily harm or death.
d. Any other safety related matter deemed by the City Council to be material in determining the responsibility of the
offeror and his or her ability to perform the services or goods required by the proposal documents in a safe
environment, both for the workers and other employees of offeror and the citizens of the City of Lubbock.
In order to obtain proper information from offerors so that City of Lubbock may consider the safety records of potential
contractors prior to awarding proposals on City contracts, City of Lubbock requires that offerors answer the following
three (3) questions and submit them with their proposals:
QUESTION ONE
Has the offeror, or the firm, corporation, partnership, or institution represented by the offeror, or anyone acting for such
firm, corporation, partnership or institution, received citations for violations of OSHA within the past three (3) years?
YES NO V
If the offeror has indicated YES for question number one above, the offeror must provide to City of Lubbock, with its
proposal submission, the following information with respect to each such citation:
Date of offense, location of establishment inspected, category of offense, final disposition of offense, if any, and penalty
assessed.
t2 "Offeror's Initials
UESTION TWO
Has the offeror, or the firm, corporation, partnership, or institution represented by the offeror, or anyone acting for such
firm, corporation, partnership or institution, received citations for violations of environmental protection laws or
regulations, of any kind or type, within the past five years? Citations include notice of violation, notice of enforcement,
suspension/revocations of state or federal licenses, or registrations, fines assessed, pending criminal complaints,
indictments, or convictions, administrative orders, draft orders, final orders, and judicial final judgments.
YES NO ✓
If the offeror has indicated YES for question number two above, the offeror must provide to City of Lubbock, with its
proposal submission, the following information with respect to each such conviction:
Date of offense or occurrence, location where offense occurred, type of offense, final disposition of offense, if any, and
penalty assessed.
QUESTION THREE
Has the offeror, or the firm, corporation, partnership, or institution represented by offeror, or anyone acting for such firm,
corporation, partnership, or institution, ever been convicted, within the past ten (10) years, of a criminal offense which
resulted in serious bodily injury or death?
YES NO ✓
If the offeror has indicated YES for question number three above, the offeror must provide to City of Lubbock, with
proposal submission, the following information with respect to each such conviction:
Date of offense, location where offense occurred, type of offense, final disposition of offense, in any, and
assessed.
ACKNOWLEDGEMENT
THE STATE OF TEXAS
COUNTY OF LUBBOCK
I certify that I have made no willful misrepresentations in this Questionnaire nor have I withheld information in
statements and answers to questions. I am aware that the information given by me in this questionnaire will
investigated, with my full permission, and that any misrepresentations or omissions may cause my proposal to be reject
Si ature
Title
SUSPENSION AND DEBARMENT CERTIFICATION
Federal Law (A-102 Common Rule and OMB Circular A-110) prohibits non -Federal entities from contracting with or
making sub -awards under covered transactions to parties that are suspended or debarred or whose principals are
suspended or debarred. Covered transactions include procurement contracts for goods or services equal to or in excess of
$25,000 and all non -procurement transactions (e.g., sub -awards to sub -recipients). ,
Contractors receiving individual awards of $25,000 or more and all sub -recipients must certify that their organization and
its principals are not suspended or debarred by a Federal agency.
Before an award of $25,000 or more can be made to your firm, you must certify that your organization and its principals
are not suspended or debarred by a Federal agency.
I, the undersigned agent for the firm named below, certify that neither this firm nor its principals are suspended or
debarred by a Federal agency.
COMPANY NAME:o �t,Gti I .ti+La''J
FEDERAL TAX ID or SOC S CURITY No. 710 —
Signature of Company Official:
r
Printed name of company official signing above: 2 J 1 �1 � �S�'1 °"'►�'
Date Signed: ' 7,01
PAYMENT BOND
Bond # AL0658
STATUTORY PAYMENT BOND PURSUANT TO SECTION 2253.021(a)
OF THE TEXAS GOVERNMENT CODE
(CONTRACTS MORE THAN $25,000)
Plainview Construction Services, Inc.
KNOW ALL MEN BY THESE PRESENTS, that dba Concrete Connection (hereinafter called the Principal(s),
as Principal(s), and _Contractors Bonding and Insurance Company
(hereinafter called the Surety(s), as Surety(s), are held and firmly bound unto the City of Lubbock (hereinafter called the
Obligee), in the amount of Sixty Four Thousand Six Hundred Forty On Dollars ($ 64,641.00 ) lawful money of the
United States for the payment whereof, the said Principal and Surety bind themselves, and their heirs, administrators,
executors, successors and assigns, jointly and severally, firmly by these presents.
WHEREAS, the Principal has entered into a certain written contract with the Obligee, dated the 24th day of
May , 20 07 , to RFP # 07-717-BM - Paving Improvements for Sidewalk
and Drainage Project 2007
and said Principal under the law is required before commencing the work provided for in said contract to execute a bond
in the amount of said contract which contract is hereby referred to and made a part hereof as fully and to the same extent
as if copied at length herein.
NOW, THEREFORE, THE CONDITION OF THIS OBLIGATION IS SUCH, that if the said Principal shall pay
all claimants supplying labor and material to him or a subcontractor in the prosecution of the work provided for in said
contract, then, this obligation shall be void; otherwise to remain in full force and effect;
PROVIDED, HOWEVER, that this bond is executed pursuant to the provisions of Section 2253.021(a) of the
Texas Government Code, and all liabilities on this bond shall be determined in accordance with the provisions of said
Article to the same extent as if it were copied at length herein.
IN WITNESS WHEREOF, the said Principal (s) and Surety (s) have signed and sealed this instrument this
6th day of June 20 07.
Contractors Bonding and Insurance Company
Surety
0itle) ttorney-in-Fact
Plainview Construction Services, LP dba Concrete Connections
(Company Name)
By: Ujrt u/V115�y14mT
(Printed Name)
(Signature)
1/,&
(Title)
The undersigned surety company represents that it is duty qualified to do business in Texas, and hereby
designates Alan Henry Agency an agent resident in Lubbock County to whom any requisite notices may be delivered
and on whom service of process may be had in matters arising out of such suretyship.
Contractors Bonding and Insurance Company
Surety
* B} CQ C,2J
(Title) Staci Gross, Attorney-in-Fac
7 Approved as to form:
City o ck
By:
i ttorne
wT * Note: If signed by an officer of the Surety Company there must be on file a certified extract from the by-laws showing
that this person has authority to sign such obligation. If signed by an Attorney in Fact, we must have copy of power of
attorney for our files.
n
2
No Text
(--,"e�-flfiicate off Qppoh'is ent arul Resoluaiony; of the Board of Directors
invnia-kru and SC' mmy a CAntrac.tors 113or, d i2)g artd in suntrwe (Vn Many haebycatify'Llrat the President has appointed
dic AnornevahHoFam idtoitiholl on Q 6unt Adc of US po" , cr of aurvey. un(Or and by the awho'dy of Te PAWNg resolutiolls
YLWWd Fy dic Board of Direcu"T oUbruma, Boiding and lns,irancc, Connpany at a nwmhg dWy held on Dmembu 11 1993:
WAN UAt IN to (TU WWL C W anlv TWA VNSWMt, Secr,.~iary or am, oosisiant Sea tart', andany lithe
a W k aim d pin"00V hOWd IT Wu MR) RJ� (h 01-,,al ftN- h0l'iZed Officer or Employec' ')
i I in", ap[-o I:-, i Aus- A Is kk I or ;qWY Is "4 1 h a UGhvriq as dek twit I bib ed in I he instrument c-vidot-Icing the appoint me nt
hn Mcn Can, Wand on OWN Q Wypapy. W CWcuic &no dcli"r and aff'r, tl,.c cad of the Company to bonds,
upon Qir'N"nomwon. Mon n1war) ship uhh"Imb 0, ;H kind : `ird any AuthcOW (Wicer or Finployee may
ran my anv six! i rau"on-inq a A' ow pn-n And razip any power lo'."uton-Ir,", is! y gratitce, to such person,
RIANA 11) "WITY0. Sa spy book injawkwq. rMognizowc, cs- wraySpobligation shall be valid and
-'�pno ih'Cca'nq-�P"y:
h"r-, ni'�"Inwd 1, the Anwo;'�/cdl Ofl'icer oi' luid, ai!�',-stcd and �)calcd Ofa
nod I, rovowdy w,
Li;v I wN 0-nal ny the WwwNd (At ca � I nip it. cc mi A coan-tanigncd said scaled
(I q 4nd Fx ran jN& hy a Ad v wdwr/,-d in-bac-1, or iq-a'lu: or
iiii! tt ]I dud C.cc net! an! SC51 CA dc a "kal ho racnim"d) IR; onc, or rniorc at-lorneys-in-
01 or ancan; siltrsup[it 6) nuid ;k Ahin the hrod, of dw ;w1hin4y cAdwiced by the
om or o C W Popov Wucd 10 1 hc Go-trtany to stich pepain or persoris,
RPSIMA 0) hi 0 153, 10 Wly '411hai/coOkfay or NIQ-ceaudd, nod ofdw(onTanynut'
knnk"U lk 0000iomy reo"s; 4mumg or vai-HOwAm WvW amkHzhq to ewcution mW dchvay of any
Nout UodaiRWn iningn0yKA or who ywayship Wiparions of we (bmparty (,..lc-so-111c-wise st-'ecilied in W
co'nann"Y AWHI nnd ax" rnlwc awl 4W mW so Und sindi hu've flat, com-ic force and. Ctfcct as though
lt,WW' Wvd'
RPM A U 1) hi Q HIT, inn OP ran, rVa"Wol" Ord" onus of UNCrips onwom ing jwvas (W auonwy and
�iwhwy -1, Kv i onmin Ii j i No tv ral A Unm , hu ah Won; of p(m co id w It prevLously ox in Te Wore
,v! 1 W nwXnn, on Vdtan iv sn WN -51 or hicsir-ndc nowc" of womey',
1' � ' t"Q k . :: , tl. a nAn 1 5 W Am cc aud cdon: and Wt (we 14ni of a nownr of
'.o1 i ,, 1c "] , €. c ' An i AW U hkh too Nm?"Un W a oar"Mix be awched to a
hal lamph1. W nyok Anq al ' -0� 1 ov Who, '% Khc 'ALUNd h, anwher In"M WW CMMTQ. is NX Power ol-
.Iw Nhwu NO; Nvli,: to Ihc, bid
o ;wind
W MY, U. 21SW
Nkno ox% RVIV
TWI !"w"v NWA i"iyowly aqw;mY im Sid0r,md
R. Kit I-Amd persomHy knownto me
W in 0 no On, w!viv. and tyki-ow0don!
ki inc ad I that 'i hcy c,,,Lecuted thesanne in their
onn in h1V QN,
-y"aw"o 1 o 0010 id= Wimirnywha,h We'Jacial
executed the insuvnicrit,
f scad)
A �nQ 4 Won Wmy i4hT'
0 L j
Bocce O9M
1313 VaNa Scrape
F.O. box 9271
CBIC Sea(:le, WA 93109-0271
CONTRACTORS BONDING (80017,65-C s;
(5001 . e`5-CSC Naclortal
AND INSURANCE COMPANY (20e) 382.962: Fax
IMPORTANT NOTICE
To obtain information or make a complaint
You may contact the Texas Department of Insurance to obtain information or. companies,
coverage„ rights or complaints at:
1 (800) 252-3439
You may write the Texas Department of Insurance at:
P.0 Box 141,1104
Austin, TX 787:4-9104
FAX - (512) 475-1771
PREMIUM OR CLAIM DISPUTE::
Should you have a dispute concerning your premium or or about a claim you should contact the
agent or the company first_ If the dispute is not resolved, you may convict the Texas Department
of Insurance.
ATTACH THIS NOTICE TO YOUR PCLICY:
This notice is for information only and does not become a parr or condition or the attached
document.
CERTIFICATE OF INSURANCE
CERTIFICATE OF INSURANCE
TO: CITY OF LUBBOCK KEVIN WHISENANT DATE: 6-07-2007
P.O. BOX 2000, Suite 102 CONCRETE CONNECTION
LUBBOCK, TX 79457 3 411 Grandview TYPE OF PROJECT:
THIS IS TO CERTIFY THAT Plainview, Texas 79072 (Name and Address of Insured) is,
at the date of this certificate, insured by this Company with respect to the business operations hereinafter described, for
the typed of insurance and in accordance with the provisions of the standard policies used by this company, the further
hereinafter described. Exceptions to standard policy noted hereon.
TYPE OF INSURANCE
POLICY NUMBER
EFFECTIVE
EFFECTIVE
LIMITS
DATE
DATE
GENERAL LIABILITY
❑ Commercial General Liability
General Aggregate $
❑ Claims Made
Products-Comp/Op AGG $
❑ Occurrence
Personal & Adv. Injury $
❑ Owner's & Contractors Protective
Each Occurrence $
❑
Fire Damage (Any one Fire) $
Med Exp (Any one Person)
$
AUT0MO77FE LIABILITY
❑ Any Auto
Combined Single Limit $
❑ All Owned Autos
Bodily Injury (Per Person) $
❑ Scheduled Autos
Bodily Injury (Per Accident) $
❑ Hired Autos
Property Damage $
❑ Non -Owned Autos
❑
GARAGE LIABILITY
❑ Any Auto
Auto Only - Each Accident $
❑
Other than Auto Only:
Each Accident $
Aggregate $
❑ BUILDERS RISK
❑ 100% of the Total Contract Price
$
❑ BVSTALLA7701VFLOATER
$
EXCESS LIABILITY
❑ Umbrella Form
Each Occurrence $
Aggregate $
❑ Other Than Umbrella Form
$
WORKERS COMPENSA 7TON AND
EMPLOYERS' LIABILITY
The Proprietor/ ❑ Included
Statutory Limits
Partners/Executive id Excluded
0001142094
2- 2 7- 0 7
2- 2 7- 0 8
Each Accident
Officers are:
Disease Policy Limit $!) UU VU, VV_
Disease Employee o
-Each U U , U
OTHER
71 The above policies either in the body thereof or by appropriate endorsement provide that they may not be changed or
canceled by the insurer in less than the legal time required after the insured has received written notice of such change or
cancellation, or in case there is no legal requirement, in less than five days in advance of cancellation.
FIVE COPIES OF THE CERTIFICATE OF INSURANCE TEXAS MUTUAL I
r
MUST BE SENT TO THE CITY OF LUBBOCK ra a Insure
etle:ren t
The Insurance Certificates Furnished shall name the City of Lubbock as a Primary Additional Insured on General
Liability and Automobile Liability and provide a Waiver of Subrogation in favor of the City of Lubbock.
ACORD,M CERTIFICATE OF LIABILITY INSURANCE
06/oi/2007
PRODUCER
SUZANNA HARRISON AGENCY, INC
3825 W. GREEN OAKS BLVD. STE 100
ARLINGTON, TEXAS 76016
THIS CERTIFICATE IS ISSUED AS A MATTER OF INFORMATION
ONLY AND CONFERS NO RIGHTS UPON THE CERTIFICATE
HOLDER. THIS CERTIFICATE DOES NOT AMEND, EXTEND OR
ALTER THE COVERAGE AFFORDED BY THE POLICIES BELOW.
INSURERS AFFORDING COVERAGE
NAIC #
INSURED
KEVIN WHISENANT BUILDER
DBA: CONCRETE CONNECTION
3411 GRANDVIEW ST
PLAINVIEW, TX 79072-6652
INSURER& NATIONWIDE INSURANCE COMPANY
INSURERB: NATIONWIDE INSURANCE COMPANY
INSURERC:
INSURER D:
INSURER E:
(`AVFRAnPA
THE POLICIES OF INSURANCE LISTED BELOW HAVE BEEN ISSUED TO THE INSURED NAMED ABOVE FOR THE POLICY PERIOD INDICATED. NOTWITHSTANDING
ANY REQUIREMENT, TERM OR CONDITION OF ANY CONTRACT OR OTHER DOCUMENT WITH RESPECT TO WHICH THIS CERTIFICATE MAY BE ISSUED OR
MAY PERTAIN, THE INSURANCE AFFORDED BY THE POLICIES DESCRIBED HEREIN IS SUBJECT TO ALL THE TERMS, EXCLUSIONS AND CONDITIONS OF SUCH
POLICIES. AGGREGATE LIMITS SHOWN MAY HAVE BEEN REDUCED BY PAID CLAIMS.
INSR DD' POLICY NUMBER
OF INSURANCE
POLICY EFFECTIVE
POLICY EXPIRATIONTYPE
LIMITS
A ' GENERAL LIABILITY ACP 5501877913
X I COMMERCIAL GENERAL LIABILITY
CLAIMS MADE a OCCUR
06/30/2006
06/30/2007
EACH OCCURRENCE
$600,000
DAMAGE TO RENTE
PREMISES Ea occurence
$100,000
MED EXP (Any one person)
$ 5,000
PERSONAL BADV INJURY
$600,000
GENERAL AGGREGATE
$1,000,000
PRODUCTS - COMP/OP AGG
$1,000,000
GEN'L AGGREGATE LIMIT APPLIES PER:
' POLICY PRO- LOC
AUTOMOBILE LIABILITY ACP 5501877913
06/30/2006
06/30/2007
COMBINED SINGLE LIMIT
B ANY AUTO
(Ea accident)
$600,000
BODILY INJURY
(Per person)
$
X ALL OWNED AUTOS
X SCHEDULED AUTOS
BODILY INJURY
(Per accident)
$
�I X j HIRED AUTOS
NON -OWNED AUTOS
PROPERTYDAMAGE
(Per accident)
$
I
GARAGE LIABILITY
AUTO ONLY - EA ACCIDENT
$
OTHER THAN EA ACC
$
ANY AUTO
$
AUTO ONLY: AGG
EXCESS/UMBRELLA LIABILITY
EACH OCCURRENCE
$
OCCUR CLAIMS MADE
AGGREGATE
$
_
$
$
DEDUCTIBLE
$
RETENTION $
WORKERS COMPENSATION AND
EMPLOYERS' LIABILITY
I ANY PROPRIETOR/PARTNER/EXECUTIVE
WCRY LIMIT 9LIMIT I 0ER
E.L. EACH ACCIDENT
$
E.L. DISEASE - EA EMPLOYEE
$
I OFFICER/MEMBER EXCLUDED?
If yes, describe under
SPECIAL PROVISIONS below
E.L. DISEASE - POLICY LIMIT
$
OTHER
1
I
DESCRIPTION OF OPERATIONS / LOCATIONS! VEHICLES! EXCLUSIONS ADDED BY ENDORSEMENT/ SPECIAL PROVISIONS
CITY OF LUBBOCK, ITS OFFICERS, AGENTS AND EMPLOYEES ARE NAMED AS PRIMARY ADDITIONAL INSUREDS ON THE
GENERAL LIABILITY, PER CIS 20 37. WAIVER OF SUBROGATION IN FAVOR OF THE CITY OF LUBBOCK ON THE GENERAL
LIABILITY AND AUTOMOBILE LIABILITY POLICY.
BID NUMBER RFP #07-717-BM
UhKIIPIGAIIt HIULUhK GANGELLATIUN
CITY OF LUBBOCK SHOULD ANY OF THE ABOVE DESCRIBED POLICIES BE CANCELLED BEFORE THE EXPIRATION
BUILDING INSPECTION DEPARTMENT DATE THEREOF, THE ISSUING INSURER WILL ENDEAVOR TO MAIL 30 DAYS WRITTEN
PO BOX 2000 NOTICE TO THE CERTIFICATE HOL ER NAMED TO THE LEFT, BUT FAILURE TO DO SO SHALL
LUBBOCK, TX 79457 IMPOSE NO OBLIGATION OR IAB LITY OF ANJ KIN PON THE INSURER, I S AGENTS OR
FAX: 806-775-2089 REPRESENTATIVES.
AUTHORIZED REPRESENTATIVE ft 11 , _ i t
I
ACORD 25 (2001/08)
v I
TION 1988
IMPORTANT
If the certificate holder is an ADDITIONAL INSURED, the policy(ies) must be endorsed. A statement
on this certificate does not confer rights to the certificate holder in lieu of such endorsement(s).
If SUBROGATION IS WAIVED, subject to the terms and conditions of the policy, certain policies may
require an endorsement. A statement on this certificate does not confer rights to the certificate
holder in lieu of such endorsement(s).
DISCLAIMER
The Certificate of Insurance on the reverse side of this form does not constitute a contract between
the issuing insurer(s), authorized representative or producer, and the certificate holder, nor does it
affirmatively or negatively amend, extend or alter the coverage afforded by the policies listed thereon.
4CORD 25 (2001108)
POLICY NUMBER ACP GLO 5521877913 CONTRACTORS
THIS ENDORSEMENT CHANGES THE POLICY. PLEASE READ IT CAREFULLY.
WAIVER OF TRANSFER OF RIGHTS OF RECOVERY
AGAINST OTHERS TO US
This endorsement modifies insurance provided under the following:
CONTRACTORS POLICY
SCHEDULE
Name of Person or Organization:
CITY OF LUBBOCK
PO BOX 2000
LUBBOCK, TX 79457
(If no entry appears above, information required to complete this endorsement will be shown in the Declarations as
applicable to this endorsement.)
The TRANSFER OF RIGHTS OF RECOVERY AGAINST OTHERS TO US Condition (Section J. - CONTRACTORS
COMMON POLICY CONDITIONS) is amended by the addition of the following:
We waive any right of recovery we may have against the person or organization shown in the Schedule above
because of payments we make for injury or damage arising out of your ongoing operations or "your work" done
under a contract with that person or organization and included in the "products -completed operations hazard." This
waiver applies only to the person or organization shown in the Schedule above.
Includes Copyrighted Material of Insurance
ACP-0107 (3-02) Services Office, Inc., 1988, 1991
POLICY NUMBER: ACP GLO 5521877913 COMMERCIAL GENERAL LIABILITY
THIS ENDORSEMENT CHANGES THE POLICY. PLEASE READ IT CAREFULLY.
ADDITIONAL INSURED - OWNERS, LESSEES OR
CONTRACTORS - COMPLETED OPERATIONS
This endorsement modes insurance provided under the following:
COMMERCIAL GENERAL LIABILITY COVERAGE PART
SCHEDULE
Name Of Additional Insured Person(s)
Or Organization(s): Location And Description Of Completed Operations
CITY OF LUBBOCK
PO BOX 2000
LUBBOCK, TX 79457
Information required to complete this Schedule, if not shown above, will be shown in the Declarations.
Section If — Who Is An Insured is amended to include as an additional insured the person(s) or organization(s)
shown in the Schedule, but only with respect to liability for "bodily injury" or "property damage" caused, in whole or in
part, by "your work" at the location designated and described in the schedule of this endorsement performed for that
additional insured and included in the "products -completed operations hazard".
CG 20 37 07 04 Copyright, ISO Properties, Inc., 2004 Page 1 of 1
(:J
CONTRACTORCHECKLIST
A CONTRACTOR SHALL:
(1) provide coverage for its employees providing services on a project, for the duration of the project based
on proper reporting of classification codes and payroll amounts and filling of any coverage agreements;
(2) provide a certificate of coverage showing workers' compensation coverage to the governmental entity
prior to beginning work on the project;
(3) provide the governmental entity, prior to the end of the coverage period, a new certificate of coverage
showing extension of coverage, if the coverage period shown on the contractor's current certificate of
coverage ends during the duration of the project;
(4) obtain from each person providing services on a project, and provide to the governmental entity:
(A) a certificate of coverage, prior to that person beginning work on the project, so the governmental
entity will have on file certificates of coverage showing coverage for all persons providing
services on the project; and
(B) no later than seven days after receipt by the contractor, a new certificate of coverage showing
extension of coverage, if the coverage period shown on the current certificate of coverage ends
during the duration of the project;
(5) retain all required certificates of coverage on file for the duration of the project and for one year
thereafter;
_. (6) notify the governmental entity in writing by certified mail or personal delivery, within ten (10) days after
the contractor knew or should have known, of any change that materially affects the provision of
coverage of any person providing services on the project;
(7) post a notice on each project site informing all persons providing services on the project that they are
required to be covered, and stating how a person may verify current coverage and report failure to provide
coverage. This notice does not satisfy other posting requirements imposed by the Act or other
commission rules. This notice must be printed in at least 19-point normal type, and shall be in both
English and Spanish and any other language common to the worker population. The text for the notices
shall be the following text provided by the commission on the sample notice, without any additional
words or changes:
PROOF OF COVERAGE SHALL BE FURNISHED TO THE CITY OF LUBBOCK IN THE FORM OF A
CERTIFICATE OF INSURANCE. THE INSURANCE CERTIFICATES FURNISHED SHALL NAME THE
CITY OF LUBBOCK AS A PRIMARY ADDITIONAL INSURED AND PROVIDE A WAIVER OF
SUBROGATION IN FAVOR OF THE CITY OF LUBBOCK, OR IN THE ALTERNATIVE, SHALL BE
ACCOMPANIED BY A STATEMENT FROM THE CONTRACTOR TO THE EFFECT THAT NO WORK ON
THIS PARTICULAR PROJECT SHALL BE SUBCONTRACTED. IT SHALL BE THE CONTRACTOR'S
RESPONSIBILITY TO PROVIDE TO THE OWNER ALL PROOF OF COVERAGE INSURANCE
DOCUMENTS INCLUDING WORKERS COMPENSATION COVERAGE FOR EACH SUBCONTRACTOR.
2
REQUIRED WORKERS' COMPENSATION COVERAGE
"The law requires that each person working on this site or providing services related to this construction project must (see
reverse) be covered by workers' compensation insurance. This includes persons providing, hauling, or delivering
equipment and materials, or providing labor or transportation or other service related to the project, regardless of the
identity of their employer or status as an employee."
"Call the Texas Workers' Compensation Commission at (512) 440- 3789 to receive information on the
legal requirement for coverage, to verify whether your employer has provided the required coverage, or to
report an employer's failure to provide coverage." and
(8) contractually require each person with whom it contracts to provide services on a project, to:
(A) provide coverage based on proper reporting of classification codes and payroll amounts and
M filing of any coverage agreements for all of its employees providing services on the project, for
the duration of the project;
(B) provide a certificate of coverage to the contractor prior to that person beginning work on the
project;
(C) include in all contracts to provide services on the project the language in subsection (e) (3) of this
rule;
(D) provide the contractor, prior to the end of the coverage period, a new certificate of coverage
- showing extension of coverage, if the coverage period shown on the current certificate of
coverage ends during the duration of the project;
(E) obtain from each other person with whom it contracts, and provide to the contractor:
(i) a certificate of coverage, prior to the other person beginning work on the project; and
(ii) prior to the end of the coverage period, a new certificate of coverage showing extension of the
coverage period, if the coverage period shown on the current certificate of coverage ends during
the duration of the project;
(F) retain all required certificates of coverage on file for the duration of the project and for one year
thereafter;
(G) notify the governmental entity in writing by certified mail or personal delivery, within (ten) 10
days after the person knew or should have known, of any change that materially affects the
provision of coverage of any person providing services on the project; and
(H) contractually require each other person with whom it contracts, to perform as required by
paragraphs (A) - (H), with the certificate of coverage to be provided to the person for whom they
are providing services.
3
CONTRACT
CONTRACT #7661
STATE OF TEXAS
COUNTY OF LUBBOCK
THIS AGREEMENT, made and entered into this 24`h day of May, 2007 by and between the City of Lubbock,
County of Lubbock, State of Texas, acting by and through the Mayor, City of Lubbock, thereunto authorized to do so,
hereinafter referred to as OWNER, and Concrete Connection of the City of Plainview, County of Hale and the State of
Texas hereinafter termed CONTRACTOR.
WITNESSETH: That for and in consideration of the payments and agreements hereinafter mentioned, to be made and
performed by the OWNER and under the conditions expressed in the bond bearing even date herewith (if any) the
_. CONTRACTOR hereby agrees with OWNER to commence and complete the construction of certain improvements
described as follows:
RFP # 07-717-BM - PAVING IMPROVEMENTS FOR SIDEWALK AND DRAINAGE PROJECT 2007 - $64 641
and all extra work in connection therewith, under the terms as stated in the contract documents and at his (or their) own
proper cost and expense to furnish all materials, supplies, machinery, equipment, tools, superintendence, labor, insurance
and other accessories and services necessary to complete the said construction in accordance with the contract documents
as defined in the General Condition of Agreement. Concrete Connection's proposal dated May 10`h, 2007 is
incorporated into and made a part of this agreement.
The CONTRACTOR hereby agrees to commence work within ten days after the date written notice to do so shall have
been given to him and to substantially complete same within the time specified in the contract documents.
The OWNER agrees to pay the CONTRACTOR in current funds for the performance of the contract in accordance
with the proposal submitted therefore, subject to additions and deductions, as provided in the contract documents and to
make payment on account thereof as provided therein.
IN WITNESS WHEREOF, the parties to these presents have executed this agreement in Lubbock, Lubbock County,
Texas in the year and day first above written.
CONTRACTOR: ll CITY OF LUBBOCK, TE (OWNER):,
MAYOR
By: ATTEST:
PRIATEDNAME: le-L-VIJLJ¢)�-444;,-JA-,J-T—
TITLE: P AA
ty Secreta
COMPLETE ADDRESS:
Address 3,o t t lo+Z9 �; e•-J
City, State, Zip PLA4 Wlxt-,�
ATTEST:
Corporate Setketary
GENERAL CONDITIONS OF THE AGREEMENT
0
GENERAL CONDITIONS OF THE AGREEMENT
l9
Whenever the word Owner, or First Party, are used in this contract, it shall be understood as referring to the City
of Lubbock, Texas.
2. CONTRACTOR
Whenever the word Contractor, or Second Party, is used, it shall be understood to mean the person, persons, co-
partnership or corporation, to wit CONCRETE CONNECTION who has agreed to perform the work embraced
in this contract, or their legal representative.
OWNER'S REPRESENTATIVE
Whenever the word Owner's Representative or representative is used in this contract, it shall be understood as
referring to, City of Lubbock, or its representative RXEITH SMITH ASSISTANT CITY ENGINEER, so
designated who will inspect constructions; or to such other representatives, supervisors, architects, engineers, or
inspectors as may be authorized by said Owner to act in any particular under this agreement. Engineers,
supervisors or inspectors will act for the Owner under the direction of Owner's Representative, but shall not
directly supervise the Contractor or persons acting on behalf of the Contractor.
4. CONTRACT DOCUMENTS
The contract's documents shall consist of the Notice to Offerors, General Instructions to Offerors, Proposal,
Signed Agreement, Statutory Bonds (if required), General Conditions of the Agreement, Special Conditions of the
Agreement (if any), Specifications, Plans, Insurance Certificates, and all other documents made available to
Offeror for inspection in accordance with the Notice to Offerors. The above described materials are sometimes
referred to herein as the "contract" or "contract documents".
INTERPRETATION OF PHRASES
Whenever the words "Directed," "Permitted," "Designated," "Required," "Considered Necessary," "Prescribed,"
or words of like import are used, it shall be understood that the direction, requirement, permission, order,
designation or prescription of the Owner's Representative is intended; and similarly, the words "Approved,"
"Acceptable," "Satisfactory," or words of like import shall mean approved by or acceptable or satisfactory to the
Owner's Representative.
6. SUBCONTRACTOR
The term Subcontractor, as employed herein, includes only those having a direct contract with the Contractor for
performance of work on the project contemplated by these contract documents. Owner shall have no
responsibility to any Subcontractor employed by Contractor for performance of work on the project contemplated
by these contract documents, but said Subcontractors will look exclusively to Contractor for any payments due
Subcontractor.
7. WRITTEN NOTICE
Written notice shall be deemed to have been duly served if delivered in person to the individual or to a member of
the firm or to an officer of the corporation for whom it is intended, or if delivered at or sent certified mail to the
last business address known to the party who gives the notice.
8. CONTRACTOR'S RESPONSIBILITIES
Unless otherwise stipulated, the Contractor shall provide and pay for all materials, supplies, machinery,
equipment, tools, superintendence, labor, insurance, and all water, light, power, fuel, transportation and all other
facilities necessary for the execution and completion of the work covered by the contract documents. Unless
otherwise specified, all materials shall be new and both workmanship and materials shall be of a good quality.
The Contractor shall, if required, furnish satisfactory evidence as to the kind and quality of materials. Materials
or work described in words which so applied have well known, technical or trade meaning shall be held to refer
such recognized standards.
All work shall be done and all materials furnished in strict conformity with the contract documents.
9. SUBSTANTIALLY COMPLETED
The term "Substantially Completed" is meant that the structure or project contemplated by the contract documents
has been made suitable for use or occupancy or the facility is in a condition to serve its intended purpose, but still
may require minor miscellaneous work and adjustment.
10. LAYOUT
Except as specifically provided herein, the Contractor shall be responsible for laying out all work and shall
accomplish this work in a manner acceptable to the Owner's Representative. The Owner's Representative will
check the Contractor's layout of all major structures and any other layout work done by the Contractor at
Contractor's request, but this check does not relieve the Contractor of the responsibility of correctly locating all
work in accordance with the Plans and Specifications.
11. KEEPING OF PLANS AND SPECIFICATIONS ACCESSIBLE
The Contractor shall be furnished copies of all Plans and Specifications without expense to Contractor and
Contractor shall keep one copy of same consistently accessible on the job site.
12. RIGHT OF ENTRY
The Owner's Representative may make periodic visits to the site to observe the progress or quality of the executed
work and to determine, in general, if the work is proceeding in accordance with the contract documents. Owner's
Representative will not be required to make exhaustive or continuous onsite inspections to check the quality or
quantity of the work, nor will Owner's Representative be responsible for the construction means, methods,
techniques, sequences or procedures, or the safety precautions incident thereto. Notwithstanding the Owner's
Representative's rights of entry hereunder, the Owner's Representative will not be responsible for the Contractor's
failure to perform the work in accordance with the Contract Documents.
13. LINES AND GRADES
All lines and grades shall be furnished by the Owner's Representative whenever Owner's Representative deems
said lines and grades are necessary for the commencement of the work contemplated by these contract documents
or the completion of the work contemplated by these contract documents. Whenever necessary, Contractor shall
_._, suspend its work in order to permit Owner's Representative to comply with this requirement, but such suspension
will be as brief as practical and Contractor shall be allowed no extra compensation therefore. The Contractor
shall give the Owner's Representative ample notice of the time and place where lines and grades will be needed.
All stakes, marks, etc., shall be carefully preserved by the Contractor, and in case of careless destruction or
removal by Contractor, its Subcontractors, or its employees, such stakes, marks, etc., shall be replaced by the
Owner's Representative at Contractor's expense.
14. OWNER'S REPRESENTATIVE'S AUTHORITY AND DUTY
Unless otherwise specified, it is mutually agreed between the parties to this Agreement that the Owner's
Representative has the authority to review all work included herein. The Owner's Representative has the
authority to stop the work whenever such stoppage may be necessary to ensure the proper execution of the
contract. The Owner's Representative shall, in all cases, determine the amounts and quantities of the several kinds
of work which are to be paid for under the contract documents, and shall determine all questions in relation to said
work and the construction thereof, and shall, in all cases, decide every question which may arise relative to the
execution of this contract on the part of said Contractor. The decision of the Owner's Representative shall be
conclusive in the absence of written objection to same delivered to Owner's Representative within fifteen (15)
calendar days of any decision or direction by Owner's Representative. In the absence of timely written objection
by Contractor, as provided herein, any and all objection or objections shall be deemed waived.
15. SUPERINTENDENCE AND INSPECTION
It is agreed by the Contractor that the Owner's Representative shall be and is hereby authorized to appoint from
time to time such subordinate engineers, supervisors, or inspectors as the said Owner's Representative may deem
proper to inspect the materials furnished and the work done under this Agreement, and to see that said material is
furnished and said work is done in accordance with the specifications therefore. The Contractor shall furnish all
reasonable aid and assistance required by the subordinate engineers, supervisors or inspectors for the proper
inspection and examination of the work. The Contractor shall regard and obey the directions and instructions of
any subordinate engineers, supervisors or inspectors so appointed, when such directions and instructions are
consistent with the obligations of this Agreement and accompanying plans and specifications provided, however,
should the Contractor object to any orders by any subordinate engineer, supervisor or inspector, the Contractor
may within fifteen (15) calendar days make written appeal to the Owner's Representative for its decision. In the
absence of timely written objection by Contractor, as provided herein, any and all objection or objections shall be
deemed waived.
16. CONTRACTOR'S DUTY AND SUPERINTENDENCE
The Contractor shall give personal attention to the faithful prosecution and completion of this contract and shall
keep on the work, during its progress, a competent superintendent and any necessary assistants, all satisfactory to
Owner's Representative. The superintendent shall represent the Contractor in its absence and all directions given
to superintendent shall be binding as if given to the Contractor. It is expressly agreed that adequate supervision
by competent and reasonable representatives of the Contractor is essential to the proper performance of the work
and lack of such supervision shall be grounds for suspending operations of the Contractor.
The work, from its commencement to completion, shall be under the exclusive charge and control of the
Contractor and all risk in connection therewith shall be borne by the Contractor.
The Owner or Owner's Representatives shall not be responsible for the acts or omissions of the Contractor, or any
subcontractors, or any of Contractor's agents or employees, or any other persons performing any of the work.
17. CONTRACTOR'S UNDERSTANDING
It is understood and agreed that the Contractor has, by careful examination, satisfied itself as to the nature and
location of the work, the confirmation of the ground, the character, quality and quantity of materials to be
encountered, the character of equipment and facilities needed preliminary to and during the prosecution of the
work, and the general and local conditions, and all other matters which in any way affect the work under the
contract documents. No oral agreement or conversation with any officer, agent, or employee of the Owner, or
Owner's Representative either before or after the execution of this contract, shall affect or modify any of the
terms or obligations herein contained. Subject to the rights of Owner as set forth in Paragraph 23 hereof, all
modifications and/or amendments to the contract documents, shall be in writing, and executed by Owner's
Representative and Contractor.
Unless otherwise specified herein, all loss, expense or damage to Contractor arising out of the nature of the work
to be done, or from the action of the elements, or from any unf�seen circumstance and the prosecution of the
work, shall be sustained and borne by the Contractor at its own cost and expense.
18. CHARACTER OF WORKERS
The Contractor agrees to employ only orderly and competent workers, skillful in the performance in the type of
work required under this contract, to do the work; and agrees that whenever the Owner's Representative shall
inform Contractor in writing that any man or men on the work, are, in Owner's Representative's sole opinion,
incompetent, unfaithful, disorderly, or otherwise unacceptable to Owner or Owner's Representative, such man or
men shall be discharged from the work and shall not again be employed on the work without the Owner's
Representative's written consent.
19. CONSTRUCTION PLANT
The Contractor shall provide all labor, tools, equipment, machinery and materials necessary in the prosecution
and completion of this contract where it is not otherwise specifically provided that Owner shall furnish same, and
it is also understood that Owner shall not be held responsible for the care, preservation, conservation, or
protection of any materials, tools, equipment or machinery or any part of the work until it is finally completed and
accepted.
The building of structures for the housing of men or equipment will be permitted only at such places as the
Owner's . Representative shall consent or direct, and the sanitary conditions of the grounds in or about such
structure shall at all times be maintained in a manner satisfactory to the Owner's Representative.
20. SANITATION
Necessary sanitary conveniences for the use of laborers on the work site, properly secluded from public
observation, shall be constructed and maintained by the Contractor in such manner and at such points as shall be
approved by the Owner's Representative and their use shall be strictly enforced.
21. OBSERVATION AND TESTING
The Owner or Owner's Representative shall have the right at all times to observe and test the work. Contractor
shall make necessary arrangements and provide proper facilities and access for such observation and testing at any
f location wherever such work is in preparation or progress. Contractor shall ascertain the scope of any observation
that may be contemplated by Owner or Owner's Representative and shall give ample notice as to the time each
part of the work will be ready for such observation. Owner or Owner's Representative may reject any such work
found to be defective or not in accordance with the contract documents, regardless of the stage of its completion
or the time or place of discovery of such errors and regardless of whether Owner's Representative has previously
accepted the work through oversight or otherwise. If any such work should be covered without approval or
consent of the Owner, it must, if requested by Owner or Owner's Representative, be uncovered for examination at
Contractor's expense. In the event that any part of the work is being fabricated or manufactured at a location
where it is not convenient for Owner or Owner's Representative to make observations of such work or require
testing of said work, then in such event Owner or Owner's Representative may require Contractor to furnish
Owner or Owner's Representative certificates of inspection, testing or approval made by persons competent to
perform such tasks at the location where that part of the work is being manufactured or fabricated. All such tests
will be in accordance with the methods prescribed by the American Society for Testing and Materials or such
other applicable organization as may be required by law or the contract documents.
If any such work which is required to be inspected, tested, or approved is covered up without written approval or
consent of the Owner or Owner's Representative, it must, if requested by the Owner or Owner's Representative, be
uncovered for observation and testing at the Contractor's expense. The cost of all such inspections, tests and
approvals shall be borne by the Contractor unless otherwise provided herein. Any work which fails to meet the
requirements of any such tests, inspections or approvals, and any work which meets the requirements of any such
tests or approvals but does not meet the requirements of the contract documents shall be considered defective, and
shall be corrected at the Contractor's expense.
Neither observations by the Owner or Owner's Representative, nor inspections, tests, or approvals made by
Owner, Owner's Representative, or other persons authorized under the contract documents to make such
inspections, tests, or approvals shall relieve the Contractor from its obligation to perform the work in accordance
with the requirements of the contract documents.
22. DEFECTS AND THEIR REMEDIES
It is expressly agreed that if the work or any part thereof, or any material brought on the site of the work for use in
the work or selected for the same, shall be deemed by the Owner or Owner's Representative as unsuitable or not in
conformity with plans, specifications and/or contract documents, the Contractor shall, after receipt of written
notice thereof from the Owner's Representative, forthwith remove such material and rebuild or otherwise remedy
such work so that it shall be in full accordance with the contract documents. It is further agreed that any remedial
action contemplated as hereinabove set forth shall be at Contractor's expense.
23. CHANGES AND ALTERATIONS
The Contractor further agrees that the Owner may make such changes and alterations as the Owner may see fit, in
the line, grade, form dimensions, plans or materials for the work herein contemplated, or any part thereof, either
before or after the beginning of the construction, without affecting the validity of this contract and the
accompanying bond.
If such changes or alterations diminish the quantity of the work to be done, they shall not constitute the basis for a
claim for damages, or anticipated profits on the work that may be dispensed with. If they increase the amount of
work, and the increased work can fairly be classified under the specifications, such increase shall be paid
according to the quantity actually done and at the unit price established for such work under this contract;
otherwise such additional work shall be paid for as provided under Extra Work. In case the Owner shall make
such changes or alterations as shall make useless any work already done or material already furnished or used in
said work, then the Owner shall recompense the Contractor for any material or labor so used, and for actual
expenses incurred in preparation for the work as originally planned.
24. EXTRA WORK
The term "extra work" as used in this contract shall be understood to mean and include all work that may be
required by the Owner or Owner's Representative to be done by the Contractor to accomplish any change,
alteration or addition to the work as shown on the plans and specifications or contract documents and not covered
by Contractor's proposal, except as provided under Changes and Alterations herein.
It is agreed that the Contractor shall perform all extra work under the direction of the Owner's Representative
when presented with a written work order signed by the Owner's Representative; subject, however, to the right of
the Contractor to require written confirmation of such extra work order by the Owner. It is also agreed that the
compensation to be paid to the Contractor for performing said extra work shall be determined by the following
methods:
Method (A) - By agreed unit prices; or
Method (B) - By agreed lump sum; or
Method (C) - If neither Method (A) or Method (B) be agreed upon before the extra work is
commenced, then the Contractor shall be paid the lesser of the following: (1) actual field
cost of the extra work, plus fifteen (15%) percent; or (2) the amount that would have been
charged by a reasonable and prudent Contractor as a reasonable and necessary cost for
performance of the extra work.
In the event said extra work be performed and paid for under Method (C)(1), then the provisions of this paragraph
shall apply and the "actual field cost" is hereby defined to include the cost of all workmen, such as foremen,
timekeepers, mechanics and laborers, materials, supplies, teams, trucks, rentals on machinery and equipment, for
the time actually employed or used on such extra work, plus actual transportation charges necessarily incurred,
together with all expenses incurred directly on account of such extra work, including Social Security, Old Age
Benefits, Maintenance Bonds, Public Liability and Property Damage and Workers' Compensation and all other
insurances as may be required by law or ordinances or directed by the Owner or Owner's Representative, or by
them agreed to. Owner's Representative may direct the form in which accounts of the actual field cost shall be
kept and records of these accounts shall be made available to the Owner's Representative. The Owner's
Representative may also specify in writing, before the work commences, the method of doing the work and the
type and kind of machinery and equipment to be used; otherwise, these matters shall be determined by the
Contractor. Unless otherwise agreed upon, the prices for the use of machinery and equipment shall be determined
by using 100%, unless otherwise specified, of the latest Schedule of Equipment and Ownership Expenses adopted
by the Associated General Contractors of America. Where practical, the terms and prices for the use of
machinery and equipment shall be incorporated in the written extra work order. The fifteen percent (15%) of the
actual field cost to be paid to Contractor shall cover and compensate Contractor for its profit, overhead, general
superintendence and field office expense, and all other elements of cost and expense not embraced within the
actual field cost as herein defined, save that where the Contractor's Camp or Field Office must be maintained
primarily on account of such Extra Work, then the cost to maintain and operate the same shall be included in the
"actual field cost."
No claim for extra work of any kind will be allowed unless ordered in writing by Owner's Representative. In case
any orders or instructions appear to the Contractor to involve extra work for which Contractor should receive
compensation or an adjustment in the construction time, Contractor shall prior to commencement of such extra
work, make written request to the Owner's Representative for a written order authorizing such extra work. Should
a difference of opinion arise as to what does or does not constitute extra work or as to the payment therefore, and
the Owner's Representative insists upon its performance, the Contractor shall proceed with the work after making
written request for written order and shall keep adequate and accurate account of the actual field cost thereof, as
provided under Method (C) (1). If Contractor does not notify Owner's Representative before the commencement
of any extra work, any claim for payment due to alleged extra work shall be deemed waived.
25. DISCREPANCIES AND OMISSIONS
E
It is further agreed that it is the intent of the contract documents that all work described in the proposal, the
specifications, plans and other contract documents, is to be done for the prices quoted by the Contractor and that
such price shall include all appurtenances necessary to complete the work in accordance with the intent of these
6
contract documents as interpreted by Owner's Representative. Notices of any discrepancies or omissions in
these plans, specifications, or contract documents, shall be given to the Owners' Representative and a
clarification obtained before the proposals are received, and if no such notice is received by the Owner's
Representative prior to the opening of proposals, then it shall be deemed that the Contractor fully
understands the work to be included and has provided sufficient sums in its proposal to complete the work
in accordance with these plans and specifications. If Contractor does not notify Owner's Representative
before offering of any discrepancies or omissions, then it shall be deemed for all purposes that the plans
and specifications are sufficient and adequate for completion of the project. It is further agreed that any
request for clarification must be submitted no later than five (5) calendar days prior to the opening of
proposals.
26. RIGHT OF OWNER TO MODIFY METHODS AND EQUIPMENT
If at any time the methods or equipment used by the Contractor are found to be inadequate to secure the quality of
work with the rate of progress required under this contract, the Owner or Owner's Representative may order the
Contractor in writing to increase their safety or improve their character and efficiency and the Contractor shall
comply with such order.
If, at any time, the working force of the Contractor is inadequate for securing the progress herein specified, the
Contractor shall, if so ordered in writing, increase its force or equipment, or both, to such an extent as to give
reasonable assurance of compliance with the schedule of progress.
27. PROTECTION AGAINST ACCIDENT TO EMPLOYEES AND THE PUBLIC AND GENERAL INDEMNITY
The Contractor shall take out and procure a policy or policies of Workers' Compensation Insurance with an
insurance company licensed to transact business in the State of Texas, which policy shall comply with the
Workers' Compensation laws of the State of Texas. The Contractor shall at all times exercise reasonable
precaution for the safety of employees and others on or near the work and shall comply with all applicable
provisions of federal, state and municipal laws and building and construction codes. All machinery and
equipment and other physical hazards shall be guarded in accordance with the "Manual of Accident Prevention in
Construction" of Associated General Contractors of America, except where incompatible with federal, state or
municipal laws or regulations. The Contractor, its sureties and insurance carriers shall defend, indemnify and
hold harmless the Owner and all of its officers, agents and employees against any all losses, costs, damages,
expenses, liabilities, claims and/or causes of action, whether known or unknown, fixed, actual, accrued or
contingent, liquidated or unliquidated, including, but not limited to, attorneys' fees and expenses, in connection
with, incident to, related to, or arising out of, the Contractor's or any subcontractor's, agent's or employee's, in
any manner whatsoever, omission, execution and/or supervision of this contract, and the project which is the
subject matter of this contract.
The safety precautions taken shall be the sole responsibility of the Contractor, in its sole discretion as an
Independent Contractor; inclusion of this paragraph in the Agreement, as well as any notice which may be given
by the Owners or the Owner's Representative concerning omissions under this paragraph as the work progresses,
are intended as reminders to the Contractor of its duty and shall not be construed as any assumption of duty to
supervise safety precautions by either the Contractor or any of its subcontractors.
28. CONTRACTOR'S INSURANCE
The Contractor shall not commence work under this contract until he has obtained all insurance as required in the
General Conditions of the contract documents, from an underwriter authorized to do business in the State of
Texas and satisfactory to the City. Proof of coverage shall be furnished to the City and written notice of
cancellation or any material change will be provided ten (10) calendar days in advance of cancellation or change.
3 All policies of insurance, required herein, including policies of insurance required to be provided by Contractor
- and its subcontractors, shall contain a waiver of any and all of the insurer's or payor's, in the event of self-
7
insurance, rights to subrogation that any such insurer or payor, in the event of self-insurance, may acquire by
virtue of payment of any loss under such insurance or self-insurance. All certificates of insurance submitted to
the City in conformity with the provisions hereof shall establish such waiver.
The Contractor shall procure and carry at its sole cost and expense through the life of this contract, insurance
protection as hereinafter specified. Coverage in excess of that specified herein also shall be acceptable. Such
insurance shall be carried with an insurance company authorized to transact business in the State of Texas and
shall cover all operations in connection with this contract, whether performed by the Contractor or a
subcontractor, or separate policies shall be provided covering the operation of each subcontractor. A certificate of
insurance specifying each and all coverages shall be submitted prior to contract execution.
PROOF OF COVERAGE SHALL BE FURNISHED TO THE CITY OF LUBBOCK IN THE FORM OF
A CERTIFICATE OF INSURANCE ALONG WITH A COPY OF THE ADDITIONAL INSURED
ENDORSEMENT. THE INSURANCE CERTIFICATES FURNISHED SHALL NAME THE CITY OF
LUBBOCK AS A PRIMARY ADDITIONAL INSURED AND PROVIDE A WAIVER OF
SUBROGATION IN FAVOR OF THE CITY OF LUBBOCK AS REQUIRED BELOW, OR IN THE
ALTERNATIVE, SHALL BE ACCOMPANIED BY A STATEMENT FROM THE CONTRACTOR TO
THE EFFECT THAT NO WORK ON THIS PARTICULAR PROJECT SHALL BE SUBCONTRACTED.
IT SHALL BE THE CONTRACTOR'S RESPONSIBILITY TO PROVIDE TO THE OWNER ALL
PROOF OF COVERAGE INSURANCE DOCUMENTS INCLUDING WORKERS COMPENSATION
COVERAGE FOR EACH SUBCONTRACTOR.
A. General Liability Insurance (Primary Additional Insured and Waiver of Subrogation required)
The contractor shall have Comprehensive General Liability Insurance with limits of $500&0 Combined
Single Limit in the aggregate and per occurrence to include:
Products & Completed Operations Hazard
Contractual Liability
Personal Injury & Advertising Injury
B. Owner's and Contractor's Protective Liability Insurance — NOT REQUIRED.
C. Comprehensive Automobile Liability Insurance (Waiver of Subrogation Required)
The Contractor shall have Comprehensive Automobile Liability Insurance with limits of not less than;
Bodily Injury/Property Damage, 500 000 Combined Single Limit, to include all owned and non -owned
cars including: Employers Non -ownership Liability Hired and Non -owned Vehicles. The City is to be
named as a primary additional insured on this policy for this specific job and copy of the endorsement
doing so is to be attached to the Certificate of Insurance.
D. Builder's Risk Insurance/Installation Floater Insurance — NOT REQUIRED.
E. Umbrella Liability Insurance — NOT REQUIRED.
F. Worker's Compensation and Employers Liability Insurance (Waiver of Subrogation required)
Worker's Compensation Insurance covering all employees whether employed by the Contractor or any
Subcontractor on the job with Employers Liability of at least $500,000.
Definitions:
Certificate of coverage ("certificate") - A copy of a certificate of insurance, a certificate of
authority to self -insure issued by the commission, or a coverage agreement (TWCC-81, TWCC-
82, TWCC-83, or TWCC-84), showing statutory workers' compensation insurance coverage for
the person's or entity's employees providing services on a project, for the duration of the project.
Duration of the project - includes the time from the beginning of the work on the project until the
Contractor's/person's work on the project has been completed and accepted by the governmental
entity.
Persons providing services on the project ("subcontractor" in Section 406.096, Texas Labor
Code) - includes all persons or entities performing all or part of the services the Contractor has
undertaken to perform on the project, regardless of whether that person contracted directly with
the Contractor and regardless of whether that person has employees. This includes, without
limitation, independent contractors, subcontractors, leasing companies, motor carriers, owner -
operators, employees of any such entity, or employees of any entity which furnishes persons to
provide services on the project. "Services" include, without limitation, providing, hauling, or
delivering equipment or materials, or providing labor, transportation, or other service related to a
project. "Services" does not include activities unrelated to the project, such as food/beverage
vendors, office supply deliveries, and delivery of portable toilets.
2. The Contractor shall provide coverage, based on proper reporting of classification codes and
--- payroll amounts and filing of any coverage agreements, which meets the statutory requirements
of Texas Labor Code, Section 401.011(44) for all employees of the contractor providing services
on the project, for the duration of the project.
3. The Contractor must provide a certificate of coverage to the governmental entity prior to being
awarded the contract.
4. If the coverage period shown on the Contractor's current certificate of coverage ends during the
duration of the project, the Contractor must, prior to the end of the coverage period, file a new
certificate of coverage with the governmental entity showing that coverage has been extended.
5. The Contractor shall obtain from each person providing services on the project, and provide to the
governmental entity:
(a) a certificate of coverage, prior to that person beginning work on the project, so the
governmental entity will have on file certificates of coverage showing coverage for all
persons providing services on the project; and
(b) no later than seven days after receipt by the Contractor, a new certificate of coverage
showing extension of coverage, if the coverage period shown on the current certificate of
coverage ends during the duration of the project.
6 The Contractor shall retain all required certificates of coverage for the duration of the project and
for one year thereafter.
7. The Contractor shall notify the governmental entity in writing by certified mail or personal
delivery, within 10 days after the Contractor knew or should have known, of any change that
materially affects the provision of coverage of any person providing services on the project.
9
8. The Contractor shall post on each project site a notice, in the text, form and manner prescribed by
the Texas Workers' Compensation Commission, informing all persons providing services on the
project that they are required to be covered, and stating how a person may verify coverage and
report lack of coverage.
9. The Contractor shall contractually require each person with whom it contracts to provide services
on the project, to:
(a) provide coverage, based on proper reporting of classification codes and payroll amounts
and filing of any coverage agreements, which meets the statutory requirements of Texas
_ Labor Code, Section 401.011(44) for all of its employees providing services on the
project, for the duration of the project;
(b) provide to the Contractor, prior to that person beginning work on the project, a certificate
of coverage showing that coverage is being provided for all employees of the person
providing services on the project, for the duration of the project;
(c) provide the Contractor, prior to the end of the coverage period, a new certificate of
coverage showing extension of coverage, if the coverage period shown on the current
certificate of coverage ends during the duration of the project;
(d) obtain from each other person with whom it contracts, and provide to the Contractor:
(1) a certificate of coverage, prior to the other person beginning work on the project;
and
(2) a new certificate of coverage showing extension of coverage, prior to the end of
the coverage period, if the coverage period shown on the current certificate of
coverage ends during the duration of the project;
(e) retain all required certificates of coverage on file for the duration of the project and for
one year thereafter;
(f) notify the governmental entity in writing by certified mail or personal delivery, within 10
days after the person knew or should have known, of any change that materially affects
the provision of coverage of any person providing services on the project; and
(g) contractually require each person with whom it contracts to perform as required by
paragraphs (a) - (g), with the certificates of coverage to be provided to the person for
whom they are providing services.
10. By signing this contract or providing or causing to be provided a certificate of coverage, the
Contractor is representing to the governmental entity that all employees of the Contractor who
will provide services on the project will be covered by worker's compensation coverage for the
duration of the project, that the coverage will be based on proper reporting of classification codes
and payroll amounts, and that all coverage agreements will be filed with the appropriate insurance
carrier or, in the case of a self -insured, with the commission's Division of Self -Insurance
Regulation. Providing false or misleading information may subject the Contractor to
administrative penalties, criminal penalties, civil penalties, or other civil actions.
11. The Contractor's failure to comply with any of these provisions is a breach of contract by the
Contractor which entitles the governmental entity to declare the contract void if the Contractor
10
does not remedy the breach within ten days after receipt of notice of breach from the
governmental entity.
G. Proof of Coverage
Before work on this contract is commenced, each Contractor and subcontractor shall submit to the Owner
for approval five Certificates of Insurance covering each insurance policy carried and offered as evidence
of compliance with the above insurance requirements, signed by an authorized representative of the
insurance company setting forth:
(1) The name and address of the insured.
(2) The location of the operations to which the insurance applies.
(3) The name of the policy and type or types of insurance in force thereunder on the date borne by
such certificate.
(4) The expiration date of the policy and the limit or limits of liability thereunder on the date borne
by such certificate.
(5) A provision that the policy may be canceled only by mailing written notice to the named insured
at the address shown in the proposal specifications.
(6) A provision that written notice _shall be given to the City ten days prior to any change in or
cancellation of the policies shown on the certificate.
(7) The certificate or certificates shall be on the form (or identical copies thereof) contained in the job
specifications. No substitute of nor amendment thereto will be acceptable.
(8) If policy limits are paid, new policy must be secured for new coverage to complete project.
(9) A Contractor shall:
(a) provide coverage for its employees providing services on a project, for the duration of the
project based on proper reporting of classification codes and payroll amounts and filling
of any coverage agreements;
(b) provide a certificate of coverage showing workers' compensation coverage to the
governmental entity prior to beginning work on the project;
(c) provide the governmental entity, prior to the end of the coverage period, a new certificate
of coverage showing extension of coverage, if the coverage period shown on the
Contractor's current certificate of coverage ends during the duration of the project;
(d) obtain from each person providing services on a project, and provide to the governmental
entity:
(i) a certificate of coverage, prior to that person beginning work on the project, so
the governmental entity will have on file certificates of coverage showing
coverage for all persons providing services on the project; and
(ii) no later than seven days after receipt by the Contractor, a new certificate of
coverage showing extension of coverage, if the coverage period shown on the
current certificate of coverage ends during the duration of the project;
(e) retain all required certificates of coverage on file for the duration of the project and for
one year thereafter;
11
(f) notify the governmental entity in writing by certified mail or personal delivery, within 10
days after the Contractor knew or should have known, of any change that materially
affects the provision of coverage of any person providing services on the project;
(g) post a notice on each project site informing all persons providing services on the project
that they are required to be covered, and stating how a person may verify current
coverage and report failure to provide coverage. This notice does not satisfy other
posting requirements imposed by the Texas Worker's Compensation Act or other
commission rules. This notice must be printed with a title in at least 30-point bold type
and text in at least 19-point normal type, and shall be in both English and Spanish and
any other language common to the worker population. The text for the notices shall be
the following text provided by the commission on the sample notice, without any
additional words or changes:
REQUIRED WORKERS' COMPENSATION COVERAGE
"The law requires that each person working on this site or providing services related to
-- this construction project must be covered by workers' compensation insurance. This
includes persons providing, hauling, or delivering equipment or materials, or providing
labor or transportation or other service related to the project, regardless of the identity
of their employer or status as an employee. "
"Call the Texas Workers' Compensation Commission at 8001372-7713 or 5121804-4000
(http://www twcc.state.tr-usltwcccontacts.html) to receive information of the legal
requirements for coverage, to verify whether your employer has provided the required
- coverage, or to report an employer's failure to provide coverage;" and
(h) contractually require each person with whom it contracts to provide services on a project,
to:
(i) provide coverage based on proper reporting of classification codes and payroll
amounts and filing of any coverage agreements for all of its employees providing
services on the project, for the duration of the project;
(ii) provide a certificate of coverage to the Contractor prior to that person beginning
work on the project;
(iii) include in all contracts to provide services on the project the following language:
"By signing this contract or providing or causing to be
provided a certificate of coverage, the person signing this
contract is representing to the governmental entity that all
employees of the person signing this contract who will
provide services on the project will be covered by workers'
compensation coverage for the duration of the project, that
the coverage will be based on proper reprinting of
classification codes and payroll amounts, and that all
coverage agreements will be filed with the appropriate
insurance carrier or, in the case of a self -insured, with the
commission's Division of Self -Insurance Regulation.
Providing false or misleading information may subject the
Contractor to administrative penalties, criminal penalties,
civil penalties, or other civil actions.";
(iv) provide the Contractor, prior to the end of the coverage period, a new certificate
of coverage showing extension of coverage, if the coverage period shown on the
current certificate of coverage ends during the duration of the project;
12
(v) obtain from each other person with whom it contracts, and provide to the
Contractor:
(1) a certificate of coverage, prior to the other person beginning work on the
project; and
(2) prior to the end of the coverage period, a new certificate of coverage
showing extension of the coverage period, if the coverage period shown
on the current certificate of coverage ends during the duration of the
project;
(vi) retain all required certificates of coverage on file for the duration of the project
and for one year thereafter;
(vii) notify the governmental entity in writing by certified mail or personal delivery,
within 10 days after the person knew or should have known, of any change that
materially affects the provision of coverage of any person providing services on
the project; and
(viii) contractually require each other person with whom it contracts, to perform as
required by paragraphs (i)-(viii), with the certificate of coverage to be provided
to the person for whom they are providing services.
29. DISABLED EMPLOYEES
Contractors having more than fifteen (15) employees agree to comply with the Americans with Disabilities Act of
1990, and agree not to discriminate against a qualified individual with a disability because of the disability of such
individual in regard to job application procedures, the hiring, advancement, or discharge of employees, employee
compensation, job training, and other terms, conditions, and privileges of employment.
30. PROTECTION AGAINST CLAIMS OF SUBCONTRACTORS LABORERS MATERIALMEN AND
FURNISHERS OF MACHINERY, EQUIPMENT AND SUPPLIES
Without limiting, in any way, manner or form, the indemnity provided by Contractor in paragraph 27 hereof, the
Contractor agrees that it will indemnify and save the Owner and all of its officers, agents and employees,
harmless against any and all claims, liabilities, losses, damages, expenses and causes of action arising out of, in
any way, manner or form, the demands of subcontractors, laborers, workmen, mechanics, material men and
furnishers of machinery and parts thereof, equipment, power tools, and supplies, incurred in the performance of
this contract and the project which is the subject matter of this contract. When Owner so desires, the Contractor
shall furnish satisfactory evidence that all obligations of the nature hereinabove designated have been paid,
discharged or waived.
31. PROTECTION AGAINST ROYALTIES OR PATENT INVENTION
The Contractor shall pay all royalties and license fees, and shall provide for the use of any design, device, material
or process covered by letters patent or copyright by suitable legal agreement with the Patentee or owner thereof.
Without limiting, in any way, manner or form, the indemnity provided by Contractor in paragraph 27 hereof, the
Contractor shall defend all suits or claims for infringement of any patent or copyrights and shall indemnify and
save the Owner, and all of its officers, agents and employees harmless from any loss on account thereof, except
that Owner shall defend all such suits and claims and shall be responsible for all such loss when a particular
design, device, material or process or the product of a particular manufacturer or manufacturers is specified or
required in these contract documents by Owner; provided, however, if choice of alternate design, device, material
or process is allowed to the Contractor, then Contractor shall indemnify and save Owner, and all of its officers,
agents and employees harmless from any loss on account thereof. Notwithstanding anything herein to the
contrary, if the material or process specified or required by Owner and/or this contract is an infringement, the
13
Contractor shall be responsible for such loss unless it gives written notice of such infringement to the Owner's
Representative prior to offering.
32. LAWS AND ORDINANCES
The Contractor shall at all times observe and comply with all federal, state and local laws, ordinances and
regulations, which in any manner affect the contract or the work, and without limiting, in any way, manner or
form, the indemnity provided by Contractor in paragraph 27 hereof, Contractor shall indemnify and save harmless
the Owner, and all of its officers, agents, and employees against any claims arising from the violation of any such
laws, ordinances, and regulations, whether by the Contractor, its employees, or subcontractors. If the Contractor
observes that the plans and specifications are at variance therewith, he shall notify the Owner's Representative in
writing prior to proposing and any necessary changes shall be adjusted as provided in the contract for changes in
the work. In the absence of timely written notification to Owner's Representative of such variance or variances
within said time, any objection and/or assertion that the plans and specifications are at variance with any federal,
state or local laws, ordinances or regulations shall be deemed waived. If the Contractor, its employees or
subcontractors perform any work contrary to such laws, ordinances, rules and regulations, and without such notice
to the Owner's Representative, Contractor shall bear all costs arising there from.
The Owner is a municipal corporation of the State of Texas and the law from which it derives its powers, insofar
as the same regulates the objects for which, or the manner in which, or the conditions under which the Owner may
enter into contracts, shall be controlling, and shall be considered as part of this contract to the same effect as
though embodied herein.
33. SUBCONTRACTING
The Contractor agrees that it will retain personal control and will give its personal attention to the fulfillment of
this contract. The Contractor further agrees that subletting of any portion or feature of the work, or materials
required in the performance of this contract, shall not relieve the Contractor from its full obligations to the Owner,
as provided by the contract documents.
34. TIME FOR SUBSTANTIAL COMPLETION AND LIQUIDATED DAMAGES
It is hereby understood and mutually agreed by and between the Contractor and the Owner, that the date of
beginning and time for completion as specified in the contract documents, of work to be done hereunder are
essential conditions of this contract; and it is further mutually understood and agreed that the work embraced in
this contract shall be commenced as provided in the contract documents.
If the Contractor should neglect, fail, or refuse to substantially complete the work within the time herein specified,
then the Contractor does hereby agree as part of the consideration for the awarding of this contract, the Owner
may withhold permanently from Contractor's total compensation, the sum of $200 (TWO HUNDRED
DOLLARS) PER WORK DAY, not as a penalty, but as liquidated damages for the breach of the contract as
herein set forth for each and every working day that the Contractor shall be in default after the time stipulated for
substantially completing the work.
It is expressly understood and agreed, by and between Contractor and the Owner, that the time for the substantial
completion of the work described herein is reasonable time for the completion of the same, taking into
`Y consideration the average climatic range and conditions and usual industrial conditions prevailing in this locality.
_ The amount is fixed and agreed upon by and between the Contractor and the Owner because the actual damages
the Owner would sustain in such event would be difficult and/or impossible to estimate, however, the amount
agreed upon herein is a reasonable forecast of the amount necessary to render just compensation to Owner, and is
expressly agreed to be not disproportionate to actual damages as measured at time of breach.
14
IT IS FURTHER AGREED AND UNDERSTOOD BETWEEN THE CONTRACTOR AND OWNER THAT
TIME IS OF THE ESSENCE OF THIS CONTRACT.
35, TIME AND ORDER OF COMPLETION
It is the meaning and intent of this contract, unless otherwise herein specifically provided, that the Contractor
shall be allowed to prosecute its work at such time and sessions, in such order of precedence, and in such manner
as shall be most conductive to economy of construction; provided, however, that the order and time of prosecution
shall be such that the work shall be substantially completed as a whole and in part, in accordance with this
contract, the plans and specifications, and within the time of completion designated in the proposal; provided,
also, that when the Owner is having other work done, either by contract or by its own force, the Owner's
Representative may direct the time and manner of constructing work done under this contract so that conflicts will
be avoided and the construction of the various works being done for the Owner shall be harmonized.
The Contractor shall submit, at such times as may reasonably be requested by the Owner's Representative,
schedules which shall show the order in which the Contractor intends to carry on the work, with dates at which
the Contractor will start the several parts of the work and estimated dates of completion of the several parts.
36. TIME OF PERFORMANCE
The Contractor agrees that it has submitted its proposal in full recognition of the time required for the completion
of this project, taking into consideration the average climatic range and industrial conditions prevailing in this
locality, and has considered the liquidated damage provisions of paragraph 34 hereinabove set forth and expressly
agrees that it shall not be entitled to, nor will it request, an extension of time on this contract, except when its
work has been delayed by an act or neglect of the Owner, Owner's Representative, employees of the Owner or
other contractors employed by the Owner, or by changes ordered in the work, or by strike, walkouts, acts of God
or the public enemy, fire or flood. Any request for extension shall be in writing with the written request for same
setting forth all justifications, in detail, for the request, and submitted to Owner's Representative within twenty
(20) calendar days of the occurrence of the event causing said delay. A failure by Owner's Representative to
affirmatively grant the extension no later than twenty (20) calendar days of written submission by Contractor shall
be deemed a denial, and final. Further, in the absence of timely written notification of such delay and request for
extension, as provided herein, any request for extension by Contractor shall be deemed waived.
37. HINDRANCE AND DELAYS
In executing the contract, the Contractor agrees that in undertaking to complete the work within the time herein
fixed, Contractor has taken into consideration and made allowances for all hindrances and delays incident to such
work, whether growing out of delays due to unusual and unanticipated circumstances, difficulties or delays in
securing material or workmen, or any other cause or occurrence. No charge shall be made by the Contractor for
hindrance or delays from any cause during the progress of any part of the work embraced in this contract except
where the work is stopped by order of the Owner or Owner's Representative for the Owner's convenience, in
which event, such expense as in the sole judgment of the Owner's Representative that is caused by such stoppage
shall be paid by Owner to Contractor.
38. QUANTITIES AND MEASUREMENTS
No extra or customary measurements of any kind will be allowed, but the actual measured or computed length,
area, solid contents, number and weight only shall be considered, unless otherwise specifically provided. In the
event this contract is let on a unit price basis, then Owner and Contractor agree that this contract, including the
specifications, plans and other contract documents are intended to show clearly all work to be done and material
to be furnished hereunder. Where the estimated quantities are shown, and only when same are expressly stated to
be estimates, for the various classes of work to be done and material to be furnished under this contract, they are
approximate and are to be used only as a basis for estimating the probable cost of the work and for comparing
15
their proposals offered for the work. In the event the amount of work to be done and materials to be furnished are
expressly stated to be estimated, and only when same are expressly stated to be estimated, it is understood and
agreed that the actual amount of work to be done and the materials to be furnished under this contract may differ
somewhat from these estimates, and that where the basis for payment under this contract is the unit price method,
payment shall be for the actual amount of work done and materials furnished on the project.
39. PROTECTION OF ADJOINING PROPERTY
The Contractor shall take proper means to protect the adjacent or adjoining property or properties in any way
encountered, which may be injured or seriously affected by any process of construction to be undertaken under
this agreement, from any damage or injury by reason of said process of construction; and Contractor shall be
liable for any and all claims for such damage on account of his failure to fully protect all adjacent property.
Without limiting, in any way, manner and form, the indemnity provided by Contractor in paragraph 27 hereof, the
Contractor agrees to indemnify, save and hold harmless the Owner, and any of its officers, agents and employees,
against any and all claims or damages due to any injury to any adjacent or adjoining property, related to, arising
from or growing out of the performance of this contract.
40. PRICE FOR WORK
In consideration of the furnishing of all necessary labor, equipment and material and the completion of all work
by the Contractor, and on the delivery of all materials embraced in this contract in full conformity with the
specifications and stipulations herein contained, the Owner agrees to pay the Contractor the price set forth in the
proposal attached hereto, which has been made a part of this contract, and the Contractor hereby agrees to receive
such price in full for furnishing all materials and all labor required for the aforesaid work, also, for all expenses
incurred by Contractor and for well and truly performing the same and the whole thereof in the manner and
according to this agreement, the attached specifications, plans, contract documents and requirements of Owner's
Representative.
41. PAYMENTS
No payments made or certificates given shall be considered as conclusive evidence of the performance of the
-. contract, either wholly or in part, nor shall any certificate or payment be considered as acceptance of defective
work. Contractor shall at any time requested during the progress of the work furnish the Owner or Owner's
Representative with a verifying certificate showing the Contractor's total outstanding indebtedness in connection
with the work. Before final payment is made, Contractor shall satisfy Owner, by affidavit or otherwise, that there
are no outstanding liens against Owner's premises by reason of any work under the contract. Acceptance by
Contractor of final payment of the contract price shall constitute a waiver of all claims against Owner, Owner's
agents and employees, which have not theretofore been timely filed as provided in this contract.
42. PARTIAL PAYMENTS
On or before the tenth day of each month, the Contractor shall submit to Owner's Representative an application
for partial payment or, if the Contractor does not submit such application, the Owner's Representative shall
determine the amount to be partially paid. Owner's Representative shall review said application for partial
payment if submitted, and the progress of the work made by the Contractor and if found to be in order, shall
prepare a certificate for partial payment showing as completely as practical the total value of the work done by the
Contractor up to and including the last day of the preceding month. The determination of the partial payment by
the Owner's Representative shall be in accordance with Paragraph 14 hereof.
The Owner shall then pay the Contractor on or before the fifteenth day of the current month the total amount of
the Owner's Representative's Certificate of Partial Payment, less 5% of the amount thereof, which 5% shall be
16
retained until final payment, and further, less all previous payments and all further sums that may be retained by
Owner under the terms of the contract documents.
Any partial payment made hereunder shall not constitute a waiver by the Owner of any and all other rights to
enforce the express terms of the contract documents, and all remedies provided therein, as to any and all work
performed, to be performed and/or materials delivered hereunder, including, but limited to, work to which said
partial payment is attributable.
43. SUBSTANTIAL COMPLETION
Contractor shall give Owner's Representative written notice of substantial completion. Within thirty-one (31)
working days after the Contractor has given the Owner's Representative written notice that the work has been
substantially completed, the Owner's Representative and/or the Owner shall inspect the work and within said time,
if the work be found to be substantially completed in accordance with the contract documents, the Owner's
Representative shall issue to the Owner and Contractor a certificate of substantial completion. Notwithstanding
the issuance of a certificate of substantial completion, Contractor shall proceed with diligence to finally complete
the work within the time provided in this contract.
--, 44. FINAL COMPLETION AND PAYMENT
The Contractor shall give written notice to Owner's Representative of final completion. Upon written notice of
final completion, the Owner's Representative shall proceed to make final measurement to determine whether final
completion has occurred. If the Owner's Representative determines final completion has occurred, Owner's
Representative shall so certify to the Owner. Upon certification by Owner's Representative of final completion,
Owner shall pay to the Contractor on or before the 31 st working day after the date of certification of final
completion, the balance due Contractor under the terms of this agreement. Neither the certification of final
completion nor the final payment, nor any provisions in the contract documents shall relieve the Contractor of the
obligation for fulfillment of any warranty which may be required in the contract documents and/or any warranty
or warranties implied by law or otherwise.
45. CORRECTION OF WORK
Contractor shall promptly remove from Owner's premises all materials condemned by the Owner's Representative
on account of failure to conform to the contract documents, whether actually incorporated in the work or not, and
Contractor shall at its own expense promptly replace such condemned materials with other materials conforming
to the requirements of the contract documents. Contractor shall also bear the expense of restoring all work of
other contractors damaged by any such removal or replacement. If Contractor does not remove and replace any
such condemned work within a reasonable time after a written notice by the Owner or the Owner's
Representative, Owner may remove and replace it at Contractor's expense.
Neither the final payment, nor certification of final completion or substantial completion, nor any provision in the
contract documents shall relieve the Contractor of responsibility for faulty materials or workmanship, and
Contractor shall remedy any defects due thereto and pay for any damage to other work resulting therefrom, which
shall appear within a period of one (1) year from the date of certification of final completion by Owner's
Representative.
46. PAYMENT WITHHELD
The Owner or Owner's Representative may, on account of subsequently discovered evidence, withhold or nullify
the whole or part of any certification to such extent as may be necessary to protect itself from loss on account of:
(a) Defective work not remedied and/or work not performed.
(b) Claims filed or reasonable evidence indicating possible filing of claims.
17
(c) Damage to another contractor.
When the above grounds are removed, or the Contractor provides a surety bond satisfactory to the Owner, in the
amount withheld, payment shall be made for amounts withheld because of them.
47. CLAIM OR DISPUTE
It is further agreed by both parties hereto that all questions of dispute or adjustment presented by the Contractor
shall be in writing and filed with the Owner's Representative within fifteen (15) calendar days after the Owner's
Representative has given any direction, order or instruction to which the Contractor desires to take exception.
Timely written notice of dispute as provided in this contract of any decision by Owner's Representative or Owner
shall be a condition precedent to the bringing and/or assertion of any action or claim by Contractor of any right
under this Contract. If the matters set forth in the notice of dispute are not granted or otherwise responded to by
Owner's Representative within fifteen (15) calendar days of receipt of notice of dispute by Owner's
Representative, said objections shall be deemed denied. Any decision by the Owner's Representative, or deemed
denial by the Owner's Representative, shall be final and conclusive in the absence of fraud. It is further agreed
that the acceptance by the Contractor of the final payment shall be a bar to any and all claims of the Contractor,
and constitute a waiver of the right to assert any claim against Owner, Owner's agents and employees and
Owner's Representative, by Contractor.
48. NON-COMPLIANCE AND/OR ABANDONMENT BY CONTRACTOR
In case the Contractor should (1) abandon and fail or refuse to resume work within fifteen (15) calendar days after
- written notification from the Owner or the Owner's Representative, or (2) if the Contractor fails to comply with
the written orders of the Owner's Representative, when such orders are consistent with this contract, then the
Surety on the bond shall be notified in writing and directed to complete the work and a copy of said notice shall
be delivered to the Contractor. In the event a bond is not required by law, or otherwise obtained by the
Contractor, no further notice of such non-compliance to Contractor shall be required.
After receiving said notice of abandonment or non-compliance , the Contractor shall not remove from the work
any machinery, equipment, tools, materials or supplies then on the job, but the same, together with any materials
and equipment under the contract for work, may be held for use on the work by the Owner or the Surety of the
Contractor, or another contractor, in completion of the work; and the Contractor shall not receive any rental or
credit therefore (except when used in connection with Extra Work, where credit shall be allowed as provided for
under paragraph 24 of this contract); it being understood that the use of such equipment and materials will
ultimately reduce the cost to complete the work and be reflected in the final settlement.
In the event the Contractor, or Surety, whichever is applicable, should fail to commence compliance with the
notice hereinbefore provided within ten (10) calendar days after service of such notice, and/or shall fail to proceed
'.__.. with diligence to complete the project as contemplated and in compliance with all terms and provisions of the
contract documents, then the Owner may exercise any and all remedies available to it pursuant to law, contract,
equity or otherwise, including, but not limited to, providing for completion of the work in either of the following
elective manners:
(a) The Owner may employ such force of men and use of machinery, equipment, tools, materials and
supplies as said Owner may deem necessary to complete the work and charge the expense of such labor,
machinery, equipment, tools, materials and supplies to said Contractor, and the expense so charged shall
be deducted and paid by the Owner out of such moneys as may be due, or that may thereafter at any time
become due to the Contractor under and by virtue of this Agreement. In case such expense is less than
the sum which would have been payable under this contract, if the same had been completed by the
Contractor, then said Contractor shall receive the difference. In case such expense is greater than the sum
which would have been payable under this contract, if the same had been completed by said Contractor,
-- then the Contractor and/or its Surety shall pay the amount of such excess to the Owner; or
18
(b) The Owner, under sealed proposals, after notice published as required by law, at least twice in a
newspaper having a general circulation in the County of location of the work, may let the contract for the
completion of the work under substantially the same terms and conditions which are provided in this
contract. In case of any increase in cost to the Owner under the new contract as compared to what would
have been the cost under this contract, such increase shall be charged to the Contractor and the Surety
shall be and remain bound therefore. Should the cost to complete any such new contract prove to be less
than that which would have been the cost to complete the work under this contract, the Contractor or his
Surety shall be credited therewith.
In the event the Owner's Representative elects to complete the work, as described above, when the work shall
have been finally completed, the Contractor and his Surety shall be so notified and certification of completion as
provided in paragraph 44 hereinabove set forth, shall be issued. A complete itemized statement of the contract
accounts, certified to by Owner's Representative as being correct shall then be prepared and delivered to
Contractor and his Surety, if applicable, whereon the Contractor or his Surety, or the Owner as the case may be,
shall pay the balance due as reflected by said statement within 30 days after the date of certification of
completion.
In the event the statement of accounts shows that the cost to complete the work is less than that which would have
been the cost to the Owner had the work been completed by the Contractor under the terms of this contract, or
when the Contractor and/or his Surety, if applicable, shall pay the balance shown to be due by them to the Owner,
then all machinery, equipment, tools, materials or supplies left on the site of the work shall be turned over to the
Contractor and/or his Surety, if applicable. Should the cost to complete the work exceed the contract price, and
the Contractor and/or his Surety, if applicable, fail to pay the amount due the Owner within the time designated
hereinabove, and there remains any machinery, equipment, tools, materials or supplies on the site of the work,
notice thereof, together with an itemized list of such equipment and materials shall be mailed to the Contractor
and his Surety, if applicable, at the respective addresses designated in this contract; provided, however, that actual
written notice given in any manner will satisfy this condition. After mailing, or other giving of such notice, such
property shall be held at the risk of the Contractor and his Surety, if applicable, subject only to the duty of the
Owner to exercise ordinary care to protect such property. After fifteen (15) calendar days from the date of said
notice the Owner may sell such machinery, equipment, tools, materials or supplies and apply the net sum derived
from such sale to the credit of the Contractor and his Surety, if applicable. Such sale may be made at either public
or private sale, with or without notice, as the Owner may elect. The Owner shall release any machinery,
equipment, tools, materials, or supplies that remain on the jobsite and belong to persons other than the Contractor
or his Surety, if applicable, to their proper owners.
The remedies provided to Owner by law, equity, contract, or otherwise, shall be cumulative, to the extent
permitted by law. It is expressly agreed and understood that the exercise by Owner of the remedies provided in
this paragraph shall not constitute an election of remedies on the part of Owner, and Owner, irrespective of its
exercise of remedies hereunder, shall be entitled to exercise concurrently or otherwise, any and all other remedies
available to it, by law, equity, contract or otherwise, including but not limited to, liquidated damages, as provided
in paragraph 34, hereinabove set forth.
49. LIMITATION ON CONTRACTOR'S REMEDY
The remedies of Contractor hereunder shall be limited to, and Owner shall be liable only for, work actually
performed by Contractor and/or its subcontractors as set forth in the contract documents, and Owner shall not be
liable for any consequential, punitive or indirect loss or damage that Contractor may suffer in connection with the
project which is the subject matter of this contract.
50. BONDS
The Contractor is required to furnish a performance bond in accordance with Chapter 2253, Government Code, in
--3 the amount of 100% of the total contract price in the event that said contract price exceeds $100,000 and the
19
Contractor is required to furnish a payment bond in accordance with Chapter 2253, Government Code, in the
amount of 100% of the total contract price in the event that said contract price exceeds $25,000. All bonds shall
be submitted on forms supplied by the Owner, and executed by an approved Surety Company authorized to do
business in the State of Texas. It is further agreed that this contract shall not be in effect until such bonds are so
furnished.
51. SPECIAL CONDITIONS
In the event special conditions are contained herein as part of the contract documents and said special conditions
conflict with any of the general conditions contained in this contract, then in such event the special conditions
shall control.
52. LOSS OR EXPENSE DUE TO UNUSUAL OR UNANTICIPATED CIRCUMSTANCES
Unless otherwise specified herein, all loss, expense or damage to the Contractor arising out of the nature of the
work to be done, or from the action of the elements, or from any unforeseen circumstance or from unusual
obstructions or difficulties, naturally occurring, man made or otherwise, which may be encountered in the
prosecution of the work, shall be sustained and borne by the Contractor at his own cost and expense.
53. INDEPENDENT CONTRACTOR
Contractor, is, and shall remain, an independent contractor with full, complete and exclusive power and authority
to direct, supervise, and control its own employees and to determine the method of the performance of the work
covered hereby. The fact that the Owner or Owner's Representative shall have the right to observe Contractor's
work during Contractor's performance and to carry out the other prerogatives which are expressly reserved to and
vested in the Owner or Owner's Representative hereunder, is not intended to and shall not at any time change or
effect the status of the Contractor as an independent contractor with respect to either the Owner or Owner's
Representative or to the Contractor's own employees or to any other person, firm, or corporation.
54. CLEANING UP
The Contractor shall at all times keep the premises free from accumulation of debris caused by the work, and at
the completion of the work Contractor shall remove all such debris and also its tools, scaffolding, and surplus
materials and shall leave the work room clean or its equivalent. The work shall be left in good order and
condition. hi case of dispute Owner may remove the debris and charge the cost to the Contractor.
55. HAZARDOUS SUBSTANCES AND ASBESTOS
Hazardous Substances (herein so called), as defined in the Comprehensive Environmental Response,
Compensation, and Liability Act (42 U.S.C.S. §9601(14)) and the regulations promulgated thereunder, as same
may be amended from time to time, hydrocarbons or other petroleum products or byproducts and/or asbestos, in
any form, shall not (i) be utilized, in any way, manner or form, in the construction of, or incorporation into, the
Project; or (ii) be brought upon, placed, or located, by any party, on the Project site, or any other property of the
City, without the written consent of the Owner's Representative. If Contractor believes that the utilization of a
Hazardous Substance, hydrocarbons or other petroleum products or byproducts and/or asbestos is necessary in the
construction of the Project, or that it is necessary to place and/or otherwise locate upon the site of the Project or
` other property of the City, a Hazardous Substance, hydrocarbons or other petroleum products or byproducts
and/or asbestos, Contractor shall notify the Owner's Representative, and request consent therefrom, at least
twenty (20) days prior to such action. Owner's Representative may grant or deny the request of Contractor and
'- provide whatever requirements such consent, if granted, is conditioned upon, in its sole and absolute discretion. If
the request of Contractor is not granted, or otherwise not responded to, by Owner's Representative within five (5)
s days of the receipt of said request, said request shall be deemed to be denied.
20
In the event Owner's Representative shall consent to the request of Contractor, Contractor shall be responsible for
ensuring that all personnel involved in the Project are (i) trained for the level of expertise required for proper
performance of the actions contemplated by this Contract and, in particular, in all aspects of handling, storage,
disposal and exposure of Hazardous Substances, hydrocarbons or other petroleum products or byproducts and/or
asbestos; and (ii) are provided and utilize all protective equipment, including without limitation, personal
protective gear, necessary to provide protection from exposure to Hazardous Substances, hydrocarbons or other
petroleum products or byproducts and/or asbestos.
-, 56. NONAPPROPRIATION
All funds for payment by the City under this contract are subject to the availability of an annual appropriation for
this purpose by the City. In the event of non -appropriation of funds by the City Council of the City of Lubbock
for the goods or services provided under the contract, the City will terminate the contract, without termination
charge or other liability, on the last day of the then -current fiscal year or when the appropriation made for the
then -current year for the goods or services covered by this contract is spent, whichever event occurs first. If at
any time funds are not appropriated for the continuance of this contract, cancellation shall be accepted by the
..a Seller on thirty (30) days prior written notice, but failure to give such notice shall be of no effect and the City
shall not be obligated under this contract beyond the date of termination.
21
CURRENT WAGE DETERMINATIONS
RE: RESOLUTION NO.2002-R0483, NOVEMBER 14, 2002
EXHIBIT A
City of Lubbock
Building Construction Trades
Prevailing Rates
Craft
Hourly Rate
Acoustical Ceiling Installer
11.50
Air Conditioner Installer
12.00
Air Conditioner Installer -Helper
7.50
--
Asbestos Worker
9.00
Asbestos Supervisor
12.50
Bricklayer
12.50
Bricklayer -Helper
7.00
Carpenter
11.00
Carpenter -Helper
7.00
Cement Finisher
9.00
Drywall Hanger
11.00
Electrician
15.00
Electrician -Helper
8.00
Equipment Operator -Heavy
10.00
Equipment Operator -Light
9.00
Fire Sprinkler Fitter -Journey
18.00
Fire Sprinkler Fitter -Apprentice
10.00
Floor Installer
9.50
Glazier
10.50
Insulator-Piping/Boiler
10.50
'
Insulator -Helper
7.00
-
Iron Worker
11.00
Laborer -General
6.00
Mortar Mixer
6.00
j
Painter
9.50
Plumber
12.50
Plumber -Helper
7.00
Roofer
9.00
Roofer -Helper
7.00
Sheet Metal Worker
10.00
Sheet Metal Worker -Helper
7.00
r-.
Welder -Certified
11.00
1
Craft
Asphalt Heaterman
_., Asphalt Shoveler
Concrete Finisher
Concrete Finisher -Helper
Electrical Repairer -Equipment
Flagger
Form Setter
Form Setter -Helper
Laborer -General
Laborer -Utility
Mechanic
Mechanic -Helper
Power Equipment Operators
Asphalt Paving Machine
Bulldozer
Concrete Paving Machine
Front End Loader
Heavy Equipment Operator
Light Equipment Operator
Motor Grader Operator
Roller
Scraper
Tractor -Trailer
Truck Driver -Heavy
Truck Driver -Light
EXHIBIT B
Paving and Highway Construction
Prevailing Wage Rates
Hourly Rate
9.00
7.50
9.00
7.50
12.50
6.50
8.00
6.50
6.00
6.75
9.00
7.00
9.00
9.00
9.00
9.00
9.00
8.00
10.25
7.00
7.50
8.50
8.00
7.00
2
EXHIBIT C
Prevailing Wage Rates
Overtime Rate
The rate for overtime (in excess of forty hours per week) shall be as required by the Fair Labor Standards Act.
EXHIBIT D
Prevailing Wage Rates
Legal Holiday Rate
The rate for legal holidays shall be as required by the Fair Labor Standards Act.
3 '
}^ 9
Lj
: 3
SPECIFICATIONS
CITY OF LUBBOCK
PUBLIC WORKS ENGINEERING
STANDARD PAVING SPECIFICATIONS
CITY OF LUBBOCK
PUBLIC WORKS ENGINEERING
STANDARD PAVING SPECIFICATIONS
April 18, 2006
CITY OF LUBBOCK
PUBLIC WORKS ENGINEERING
STANDARD PAVING SPECIFICATIONS
TABLE OF CONTENTS
SECTION PAGE NUMBER
1.1
GENERAL
1
1.2
Specifications
1
1.3
Warranty and Acceptance
1
1.4
Testing and Inspection
2
1.5
Cleanup and Site Restoration
2
1.6
Notification of Property Owners
3
1.7
Protection of Utilities and Irrigation Systems
3
1.8
Water for Construction
3
2.1
CONCRETE
4
2.2
Classification
5
2.3
Mix Design
5
2.4
Strength Requirements
6
2.5
Cement
6
2.6
Aggregate
6
2.7
Flowable Fill
7
2.8
Water
8
2.9
Admixtures
8
2.10
Reinforcing Materials
8
2.11
Joints
9
2.12
Joint Sealing Materials
10
2.13
Curing Compounds
10
2.14
Forms for Concrete
10
2.15
Placing and Finishing Concrete
11
3.1
SUBGRADE
12
4.1
FLEXIBLE BASE (CALICHE)
13
4.2
Materials Tests
13
4.3
Flexible Base Construction
14
5.1
ASPHALT STABLIZED BASE (ASB)
15
5.2
ASB Mix design
15
5.3
Placing ASB
16
5.4
ASB Compaction
16
6.1
HOT MIX ASPHALT CONCRETE SURFACE (HMAC)
17
6.2
Thickness of HMAC Surface
18
6.3
Mix Design
18
6.4
Coarse Aggregate
19
6.5
Fine Aggregate
20
6.6
Asphalt
20
6.7
Placing HMAC
21
6.8
Compaction
22
6.9
Prime and Tack Coats
23
6.10
Emulsified Asphalt Sealer
23
7.1
STORM SEWER
23
7.2
Reinforced Concrete Pipe
24
7.3
Mortar
24
7.4
Preformed Bituminous Gasket Joints
24
7.5
Manholes
24
7.6
Manhole Frames and Covers
26
7.7
Construction Methods
26
7.8
Excavation
26
7.9
Pipe Installation
28
7.10
Backfilling
29
7.11
Trench Protection
29
8.1
FENCES
30
9.1
SALVAGE OF ASPHALT PAVING
31
10.1
BARRICADES
31
11.1 PROSECUTION OF THE WORK
AND WORKING DAYS 32
11.2 Working Days Definition 32
11.3 Work Between November 1 and January 2 33
12.1
MEASUREMENT AND PAYMENT
33
12.2
Curb and Gutter
34
12.3
Concrete Flat Slabs
34
12.4
Curb Ramps
34
12.5
Concrete Drainage Channel
34
12.6
Retaining Wall or Curb on Drain Channel or Curb Ramp
34
12.7
Concrete Median
35
12.8
Concrete Street Paving
35
12.9
Sawing and Sealing Joints
35
12.10
Storm Sewer Inlet Boxes and Manholes
35
12.11
Headwalls
35
12.12
Storm Sewer Pipe
36
12.13
Extra Vertical Feet of Manhole
36
12.14
Curb and Gutter Removal
36
12.15
Concrete Slab Removal
36
12.16
2 Sack Flowable Fill
37
12.17
Asphalt Paving
37
12.18
Asphalt Paving Repair
37
12.19
Excavation and Grading
37
12.20
Ditch Grading and Unpaved Street Surface Grading
37
13.1 STANDARD DETAILS 38
Street Crown Elevations
Typical Asphalt Street Cross -sections
Typical 24 inch Curb and Gutter
Typical 30 inch Curb and Gutter
Concrete Valley Gutter
Alley Return and Alley Paving
Tee Alley
Typical Handicap Ramp
CITY OF LUBBOCK
PUBLIC WORKS ENGINEERING
STANDARD PAVING SPECIFICATIONS
1.1 GENERAL
The construction and materials for any City of Lubbock Street/Drainage Engineering
project shall conform to the following specifications and associated plan sheets. Any
construction or materials failing to meet the requirements of these specifications or the
plan sheets shall be removed and replaced at the Contractor's expense. No consideration
will be given to requests for reduced payments, except as specified, or extended
warranties for construction or materials not in conformance with these specifications or
the plan sheets.
The Engineer may require certificates from manufacturers certifying that materials or
equipment to be incorporated into the work meet these specifications. Material Safety
Data Sheets (MSDS) shall be required on all materials. All materials or equipment shall
be subject to approval by the Engineer before being incorporated into any project. After
approval, the source and/or character of materials shall not be changed without written
authorization by the Engineer
The term Engineer used in these specifications may refer to the City of Lubbock City
Engineer or an individual designated. by the City Engineer to administer these
specifications and associated plans.
1.2 SPECIFICATIONS
Any references to these specifications, ASTM, AASHTO, TxDOT, or other designated
tests, procedures, quality standards, or requirements which are included in these
specifications or any associated plans shall be the latest edition and revision thereof.
When information indicated on plan sheets is different from these specifications, the
information on the plans shall govern.
1.3 WARRANTY AND ACCEPTANCE
All equipment, materials, and construction incorporated into any project covered by these
specifications shall be guaranteed against defective material and workmanship. Prior to
final acceptance, the contractor shall furnish to the Engineer, a Maintenance Bond which
shall provide that the contractor shall remedy any defects in the work, and pay for
any and all damages of any nature whatsoever resulting in or from such defects when
such defects appear within one year from the date of acceptance of the work. The
determination of the necessity during the warranty period for the contractor to repair or
replace the work in whole or in part shall rest with the Engineer.
1.4 TESTING AND INSPECTION
All work shall be inspected and/or tested by a representative designated by the Engineer,
who shall have the authority to halt construction when, in his opinion, construction is
being performed contrary to these specifications or associated plans. Whenever any
portion of these specifications or associated plans is violated, the Engineer may order that
portion of construction that is in violation to cease until such violation is corrected.
Contractor shall cooperate with the Engineer in providing for sampling and testing
procedures. In the event City tests indicate out of specification materials, additional tests
may be provided by the contractor at his expense. Conflicting tests provided by the
contractor will not automatically be considered as compliance with specifications, but
will be considered only as additional information to be used by the Engineer to determine
the compliance of the material or construction in question.
The testing and inspection provided by the City is intended only to verify that materials
and construction comply with plans and specifications. The City's testing and inspection
are not intended to replace the contractor's responsibility to comply with the
specifications. With respect to new material sources, or where the City lab has
determined materials do not meet specifications, the City will not re -test until the
contractor has provided his own testing to demonstrate the materials and construction are
in compliance with the plans and specifications.
Upon completion of construction, the contractor shall flood all paving improvements
within the project. Any improvements holding water one quarter inch or more in depth,
or extending more than 10 feet in length shall be removed and replaced.
1.5 CLEANUP AND SITE RESTORATION
After any construction covered by these specifications is completed, the Contractor shall
remove all equipment, surplus materials, and rubbish from the site. The contractor shall
restore all disturbed areas to their original condition satisfactory to the Engineer.
2
1.6 NOTIFICATION OF PROPERTY OWNERS
The contractor shall be responsible for maintaining positive communication with adjacent
property owners. The contractor shall notify all affected property owners with respect to
pending construction, restricted access, and driveway locations.
1.7 PROTECTION OF UTILITIES AND IRRIGATION SYSTEMS
The plans show only approximate locations of utilities as obtained from various utility
companies. It is not implied that all utilities or accurate locations are shown on the plans.
It is the contractor's responsibility to familiarize himself with all utilities and locations.
The contractor shall comply with all laws, ordinances, and regulations with respect to
utility notification and protection, including Underground Facility Damage Prevention
Notification Centers. The contractor shall call DIG TESS 1-800-545-6005 and provide
time for all utilities to be identified prior to construction.
On all projects the contractor shall exercise care not to damage any sanitary sewer pipe,
manholes, storm sewers, water lines, valves and boxes, communication cables, power
cables, gas lines, nor any other pipe or utility. The contractor will be responsible during
the construction period for damages to any utilities.
Irrigation systems affected by construction shall be properly repaired with materials equal
the existing system. The repairs shall be pressure tested to the satisfaction of the
Engineer prior to being covered.
1.8 WATER FOR CONSTRUCTION
The City will not furnish water at no charge for construction. To use City water for
construction the contractor shall acquire a water meter for use on a City fire hydrant, and
will be charged the applicable rate for the quantity of water used.
The contractor shall contact Lubbock Power and Light Customer Service Department
(775-2509) and establish a utility account. The contractor must pay the current deposit
for a fire hydrant meter. After the account is established and the deposit is paid, the
contractor may pick up a meter from the City Water Department at 600 Municipal Drive.
Fire hydrants shall be operated only by use an approved fire hydrant wrench. No pipe
wrenches, or other unapproved devices, shall be used to open and close a fire hydrant.
3
For top loading trucks or containers the contractor shall provide a back flow prevention
assembly on the discharge side of the meter. The backflow prevention assembly shall be
in the form of two spring loaded ball check valves. When filling the truck or container
there shall be an air gap of at least two times the opening diameter of the truck or
container.
For bottom loading trucks the contractor shall provide a Reduced Pressure Zone (RPZ)
type backflow prevention assembly. All Reduced Pressure Zone type back flow
prevention assemblies must be tested, and the test results approved by the City prior to
use. The test results shall be sent to the City of Lubbock Water Utilities Department,
Meter and Customer Service Supervisor for approval.
In accordance with City of Lubbock Ordinance No. 10208 "Pertaining to Backflow
Prevention", the City representatives are authorized to suspend water use from a fire
hydrant by a contractor until the proper and correct backflow prevention devices are
installed.
2.1 CONCRETE
These specifications shall govern Portland cement concrete used for curb and gutter,
valley gutters, alley paving, sidewalks, street paving, drainage channels. The concrete
shall be produced at a Ready -Mix Concrete Batch Plant conforming to ASTM C 94.
The concrete shall be transported to the project location in approved Revolving Drum
Agitator Trucks, and shall be placed within one hour of mixing time. The concrete shall
be continuously mixed during transit.
No patching of any nature shall be allowed in repairing any damage to concrete
improvements. Where damage occurs, the section shall be removed to the nearest joints
and shall be replaced with new construction. Small cracks with no evidence of
displacement may be repaired with epoxy, only where approved by the Engineer.
All concrete shall have 5%, plus or minus 1-1/2%, air entrainment in conformance with
ASTM C 260.
All concrete street pavement shall include proper jointing as determined by the Engineer
and a minimum reinforcement of number 4 bars on 18" centers both ways, or as indicated
on plans.
When delivered to the jobsite each truck shall provide the load ticket indicating weights
of all concrete ingredients, including cement, aggregates, water, and admixtures.
H
JI 2.2 CLASSIFICATION
The following City of Lubbock classes of concrete shall be used:
Class A Curb and gutter, sidewalks, curb ramps, drainage channels,
medians, inlet boxes, headwalls, junction boxes, driveways, and
retaining walls.
Class B Valley gutters and fillets, alley returns, and alley paving.
Class C Concrete street pavement.
Class D Utility encasements
Class E Fast setting concrete pavement such as "Fast Track" Concrete
Pavement or, other special design.
2.3 MIX DESIGN
Twenty to thirty days prior to beginning any concrete construction the contractor shall
submit the following to the Engineer for approval:
1. Test certificates from an approved commercial testing laboratory on all
proposed aggregate. Certificates shall indicate material source, gradation, and
loss from 5 cycle Magnesium Sulfate or Sodium Sulfate test (not to exceed 18%)
2. A mix design based on water -cement ratio.
3. Results of compression tests in conformance with ASTM C 39 and/or flexural
tests in conformance with ASTM C 78, made by an approved commercial testing
laboratory. Tests shall be made on 6 cylinders and/or 6 beams at curing times
appropriate to the class of concrete.
The City Engineer will approve or reject the mix design and materials based on these
submittals. This approval shall be subject to additional testing during construction.
G
Mix designs for various classes of concrete shall conform to the following:
Minimum Sacks Maximum Gal Maximum Slump
Class Cement per CY Water per Sack Inches
A 5.0
6.5
5
B 5.5
5.5
5
C 6.0
6.0
3
D 4.5
6.5
5
E 7.0
5.0
As specified by
concrete batch plant
2.4 STRENGTH REQUIREMENTS
The various classes of concrete shall conform to the following minimum strengths in psi
as determined by the average of two test cylinders or beams. If cores are subsequently
used to prove compressive strength where test cylinders indicate failures, the required
compressive strength shall be increased by 10%.
COMPRESSIVE FLEXURAL
Class 3 Dav 7 Day 28 Dav
A - 2100 3000 -
B 2500 3000 - -
C - 2500 3600 600 (28 day)
D - - 2500 -
E 3000 psi at 24 hours
2.5 CEMENT
Cement shall be Type I, Type II, Type III, or Type V cements, conforming to ASTM C
150 "Standard Specification for Portland Cement". Air entrained cement shall be Type
IA, Type IIA, Type IIIA, or Type VA conforming to ASTM C 175 "Specification for
Adding Air Entraining to Portland Cement" and ASTM C 226 "Standard Specification
for Air -Entraining Portland Cement".
2.6 AGGREGATE
Concrete aggregate shall consist of natural, washed and screened sand, and washed and
screened gravel or clean crushed stone conforming to ASTM C 33.
on
The aggregates shall be well graded from coarse to fine with a maximum size of 1-1/2
inches, and shall conform to ASTM C 136.
All aggregate shall be free of injurious amounts of clay, soft or flaky materials, loam, or
organic impurities.
Coarse aggregate for Class C or E concrete shall be crushed limestone (Brownwood type
or equivalent).
Fine aggregate shall be graded from fine to coarse and shall conform to ASTM C 136.
The gradation for aggregate shall meet the following requirements by weight:
FINE AGGREGATE COARSE AGGREGATE
m.,
Sieve Percent Retained Sieve Percent Retained
3/8 inch 0 1-3/4 inch 0
No. 4 0-5 1-1/2 inch 0-5
No.16 20-55 3/4inch 30-65
No. 30 45-75 3/8 inch 70-90
No. 50 70-90 No. 4 95-100
No. 100 98-100
Maximum amounts of organic impurities shall conform to ASTM C 40 and ASTM C 87.
Maximum amounts of impurities finer than the #200 sieve shall conform to ASTM C
117. Maximum amounts of soft particles shall conform to ASTM C 123. Maximum
amounts of friable particles shall conform to ASTM C 142.
Stockpiles shall be protected from dusty conditions by drift fences or other methods
approved by the Engineer. Stockpiling methods used shall not allow aggregate to roll
down the slope as it is added to existing stockpiles. Stockpiles shall be built in layers of
uniform thickness. Equipment shall not be permitted to operate over the same lift
repeatedly.
2.7 FLOWABLE FILL
Flowable fill shall consist of a concrete mixture of pea gravel and sand with a cement
content of 1-1/2 sacks per cubic yard. Flowable fill shall be used for backfill in all utility
ditches within the right of way, and other areas as specified. Utility ditches in existing
paved streets shall be backfilled with flowable fill from the bottom of the ditch to the
paving surface. Use of concrete in place of flowable fill is not acceptable, and if used in
place of flowable fill shall be removed by the contractor.
7
2.8 WATER
Water shall be clean, clear, free from oil, acid or organic matter and free from injurious
amounts of alkali, salts, or other chemicals and shall conform to AASHTO T26.
2.9 ADMIXTURES
Admixtures may be applied to the concrete mix design when approved by the Engineer to
achieve any desired special properties. Chemical admixtures shall conform to ASTM C
494. Chemical admixtures shall not be used as a substitute for Cement.
Mineral admixtures such as Fly Ash and Natural Pozzolans in conformance with ASTM
C 618 may not be used with Types I, II, III, and V Portland Cement unless specifically
gpproved by the Engineer. If approved only Class C or Class F fly ash may be used.
When fly ash is permitted to be used, "cement" in relation to mix design shall be defined
as "cement plus fly ash". Fly ash may constitute no more than 15% by absolute volume
of the cement as approved by the Engineer.
2.10 REINFORCING MATERIALS
GENERAL - All concrete, except for curb and gutter, shall incorporate wire mesh or fiber
reinforcement, and/or other reinforcement as indicated on plan sheets. Metal
reinforcement shall be grade 40 (40KSI) unless indicated otherwise on plan sheets.
All steel reinforcing materials shall be securely held in proper position with devices
appropriate to the type of reinforcement used, subject to approval by the Engineer.
STEEL - Wire mesh shall conform to ASTM A 185, and shall be 6"x 6"-10 gauge welded
wire fabric, or size as indicated on plan sheets. Reinforcing bars shall be open-hearth
basic oxygen or electric furnace new billet steel manufactured in accordance with ASTM
A 615 and ASTM A 305. Steel reinforcing materials stored at any location shall be
protected from accumulations of grease, mud or other foreign matter, and rust producing
materials. When incorporated into construction, steel reinforcement shall be free from
rust, scale, oil, mud, and structural defects.
Dowels for slip joints shall be smooth plain round bars free from burrs, rough surfaces,
and deformations. Sleeves or wrapping shall be as indicated on plan sheets.
Chairs shall be used to support the reinforcing steel in the correct position while concrete
is being placed. Chairs shall be made of plastic (preferred) or steel, and shall be of
adequate size to positively hold the reinforcing materials in position.
FIBER - Fiber reinforcement may be used in place of wire mesh only if approved by the
City Engineer. Fiber reinforcement shall be either 100% virgin polypropylene, collated,
fibrillated fibers specifically manufactured for use as concrete reinforcement, containing
no reprocessed olefin materials, or steel fibers equivalent to Novocon Xorex. The
quantity of fiber reinforcement used shall be 1.5 pounds per cubic yard, or as
recommended by the fiber manufacturer.
The minimum physical characteristics on the fiber shall be as follows:
Specific Gravity
Tensile Strength
Length
2.11 JOINTS
0.91
70,000 psi to 110,000 psi
3/4"
Curb and gutter (Class A concrete)shall be constructed with an expansion joint at the
tangent point of each return at intersections and at intervals not more than 40 feet between
the intersections. The 40 foot intervals may be omitted for machine placed curb and
gutter. Construction joints formed by removable metal templates accurately shaped to the
cross-section of the curb and gutter shall be located at the midpoint of each section
between expansion joints, or as directed by the Engineer. Tooled contraction joints, cut at
least one quarter the concrete depth, shall be placed at 10 foot intervals.
Alley paving (Class B concrete) shall be constructed with an expansion joint at each cold
joint. Tooled contraction joints, cut 3/4 inch wide 1-5/8 inch deep, shall be placed at 13
foot intervals. Alley paving contraction joints shall be sealed with an asphaltic sealer.
Street Paving (Class C or E concrete) shall be constructed with contraction and expansion
joints as indicated on plan and detail sheets. Unless otherwise specified, the joints shall
be sawed 1/2 inch wide and to depth equal to 1/4 of the pavement thickness plus one half
inch. Joints shall be saw cut within 12 hours of placement of the concrete paving. The
joints shall be sealed with an elastomeric system as specified in section 2.12.
Valley gutters and fillets shall be constructed with tooled construction joints. The joints
shall be sealed with an elastomeric system as indicated in section 2.12.
E
2.12 JOINT SEALING MATERIALS
Bituminous premolded expansion joint material shall conform to ASTM D 1751, and
shall be placed as indicated on plan sheets or elsewhere in these specifications.
Elastomeric sealant for contraction joints shall be, or shall be equivalent to, W.R.
Meadows "SOF-SEAL", W.R. Meadows #158 cold applied, or "GARDOX" as required
by plan sheets. Hot poured sealant for joints between Portland cement concrete and
Bituminous concrete shall conform to ASTM D 3405. Hot poured joint sealant for all
other joints in Portland cement concrete pavement, shall conform to ASTM D 3406.
Cold poured joint sealant shall conform to ASTM C 920.
Elastomeric joint sealant shall be mixed and applied in accordance with the
manufacturer's recommendations. Prior to application, joints shall be cleaned by
sandblasting and otherwise prepared so that the sealant adheres to the surfaces to form an
effective seal against moisture and solid particles. The sealant shall be a soft, highly
flexible, rubber like material after curing which shall not track, flow, crack, or break
when exposed to hot and cold temperature extremes typical of local conditions.
Backer rod used with elastomeric sealant shall be 25% greater in diameter than the joint
width. It shall be made of polyethylene foam or other material as recommended by the
sealant manufacturer. Compression of the backer rod material shall be approximately
25% shrinkage at 8 psi applied stress. The material shall not melt, shrink, evaporate, or
absorb water, and shall be compatible with the application of the sealant to be used.
2.13 CURING COMPOUNDS
All fresh concrete surfaces shall be completely covered with a liquid membrane forming
curing compound and the application shall conform to DMS - 4650 and TxDOT Item
"Concrete Structures - Curing Materials".
No other methods of moisture retention on fresh concrete shall be used unless specifically
approved by the Engineer.
2.14 FORMS FOR CONCRETE
Forms for concrete construction shall be set to the lines and grades established by the
Engineer after subgrade has been prepared. The forms shall be held together and in place
in such a manner that they will not move during the placing and working of the concrete.
The forms shall be cleaned and oiled prior to placing concrete.
10
Face forms and construction joints (removable metal plates) shall be set to hold the
concrete in place until it is to be finished.
Forms that are warped or damaged in any manner so as to make them unacceptable to the
Engineer shall not be used. Forms for radii shall be set in the same manner as straight
forms, and shall be set to produce curves true to the plans. Face forms will not be
required for curb and gutter on radii if a true section can be obtained by other methods
acceptable to the Engineer.
2.15 PLACING AND FINISHING CONCRETE
Placing of concrete shall not start before sunrise, and shall stop one hour before sunset.
Concrete shall be placed as close to its proper location as practical. Sufficient concrete
shall be placed to allow for shrinkage and extra material for finishing. The concrete shall
be floated and troweled to the approximate section. No water shall be added during
placement or finishing of any concrete, unless specifically authorized by the Engineer.
For curb and gutter removal of face forms and finishing shall be started after a partial set
occurs. For all concrete construction approved forms, templates, and tools shall be used
to form the cross -sections indicated on plan or detail sheets.
Concrete shall not be placed when the ambient temperature is below 40 degrees F as
determined by the National Weather Service continuous broadcast, 748-1071 selection 2.
Concrete shall not be placed on frozen subgrade. The contractor shall have available
sufficient covering material, approved by the Engineer, to immediately protect concrete
should the air temperature fall below 33 degrees F. This protection shall remain in place
--. as long as the temperature continues below 32 degrees, to a maximum of 5 days. No salt
or other chemical admixtures shall be added to the concrete to prevent freezing.
All concrete placed for pavement shall be consolidated by use of mechanical vibrators
approved by the Engineer and designed to vibrate the concrete internally. Vibrators shall
be operated in a manner not to interfere with joints, and shall not come in contact with
forms. The surface of concrete street paving shall incorporate a heavy broom finish, or
tined finish if indicated on plans. All other concrete surfaces shall be completed with a
light broom finish.
11
Finished concrete surfaces shall not have irregularities in excess of 1/8 inch when tested
with a 10 foot straightedge. Prior to acceptance, the contractor shall apply sufficient water
to all concrete and paving to determine locations of ponding. Ponded areas shall be
removed and replaced. Any concrete construction damaged by equipment, tools, vandals,
or other influences shall be replaced at the contractor's expense.
3.1 SUBGRADE
Subgrade material for concrete or asphalt construction shall consist of suitable native soil
or off site soil, free from vegetation or other objectionable matter. All unstable or
objectionable material shall be removed from the subgrade and replaced with approved
material. The material shall be suitable for forming a stable embankment and shall meet
the following requirements:
Liquid Limit
45 maximum
Plasticity Index
15 maximum
Linear Shrinkage
2 min - 10 max
Subgrade material which does not meet the above requirements may be conditioned with
lime or caliche screenings. The conditioning shall produce a uniform subgrade material
which meets all of these specified subgrade requirements
Subgrade shall be prepared in conformance with the lines and grades shown on the plans,
or as directed by the Engineer, by scarifying and compacting to a minimum of 95% of
Standard Proctor Density at optimum moisture content plus or minus 2%. Subgrade shall
be constructed in maximum of 6 inch lifts. The total thickness of the subgrade shall be 6
inches minimum for streets 36 feet wide or less, 12 inches minimum for streets greater
than 36 feet wide, or as indicated on plan sheets.
The compaction method for subgrade shall provide for each lift to be compacted to the
specified density using appropriate equipment. After each section of subgrade is
complete, tests as determined necessary by the City Engineer will be made by the City of
Lubbock Testing Lab with respect to moisture and density using nuclear testing
equipment. At any time the City Engineer may require proof rolling on streets or alleys
with a 25 ton pneumatic roller, or equivalent, to test the uniformity of compaction.
All utility ditches shall be determined to be stable prior to construction of subgrade over
such utility ditch.
12
Any fill placed within existing or proposed street right of way in execution of an
approved cut and fill plan shall meet these specifications for materials and construction.
Cut and fill operations shall comply with Chapter 25 of the City of Lubbock Code of
Ordinances.
Subgrade which has become wet, or otherwise altered, after completion may be subject to
retesting and reprocessing as determined by the Engineer.
4.1 FLEXIBLE BASE WALICHE
The material for flexible base shall consist of crushed caliche, limestone, calcareous clay
particles, conglomerate, gravel, sand, or other approved granular materials produced from
oversize quarried aggregate, sized by crushing and produced from a naturally occurring
single source. Blending of sources shall be allowed only if both sources individually
meet the requirements of these specifications. If material characteristics within the
approved source change, the material shall be subject to retesting and re -approval prior to
continued use. The Contractor shall not change material sources without approval by the
Engineer.
All base material sources are subject to approval by the Engineer. Approved sources that
do not test consistently within the limits of these specifications during construction may
be rejected by the Engineer.
Flexible base material may be conditioned by addition of crushed concrete (Class A
Concrete minimum). Blending of crushed concrete and caliche shall be performed at the
- contractor's production site. The crushed concrete shall be processed to remove wood,
steel and other contaminants, including brick and asphalt materials, before blending. The
final blended material shall meet the material and performance specifications as stated
herein.
4.2 MATERIAL TESTS
Flexible base material shall conform to the following test requirements:
Sieve Analysis
Sieve Size 2-1/2" 1-3/4" 7/8" 1/2" #4 #40
%Retained 0 5-10 10-35 30-50 45-65 70-85
13
Atterberg Limits
Material passing the No. 40 Sieve shall be known as "Soil Binder" and shall meet the
following requirements:
Liquid Limit 45 maximum
Plasticity Index 15 maximum and 3 minimum
Linear Shrinkage 10 maximum
Wet Ball Mill
When tested in accordance with Tex- 116-E (Wet Ball Mill) the base material shall have a
value not to exceed 55. The percent of material passing the #40 sieve shall not increase
by more than 30 during the test.
4.3 FLEXIBLE BASE CONSTRUCTION
Areas behind curbs shall be backfilled and leveled with approved topsoil prior to placing
base material. Approved flexible base material shall be hauled in vehicles of uniform
capacity and dumped evenly along the project length for processing and compaction.
Processing shall be accomplished in multiple lifts of 3 inches compacted thickness. Each
course shall be wetted and rolled with a pneumatic roller as required to produce a uniform
compaction of 95% minimum of Standard Proctor Density at a moisture content 1% to
2% below optimum. At any time the Engineer may require proof rolling with a 25 ton
pneumatic roller to ensure uniform compaction of base. Processing for compaction of
caliche base with a sheeps foot type roller will not be permitted.
The base shall be maintained by blading, watering, or other methods until the wearing
surface is placed. Windrow caliche shall not be removed until the base has passed finish
inspection. Base which becomes wet, or other wise altered, may be subject to retesting
and reprocessing as determined by the Engineer.
The compacted flexible base shall be finished and shaped immediately proceeding the
application of the surface treatment. All loose or unconsolidated material shall be
removed and the surface moistened and rolled with a steel wheel roller. All irregularities,
depressions, or weak spots which develop shall be corrected by scarifying, adding or
removing material as required, reshaping, and recompacting, or other methods approved
by the Engineer.
Any deviation in the surface of the finished base in excess of 3/8 inch from the
established grade or true cross-section, using a 10 foot long straight edge, shall be
corrected as provided above.
14
5.1 ASPHALT STABILIZED BASE (ASB)
Asphalt stabilized base shall consist of a compacted mixture of graded gravel aggregate
(caliche is not an acceptable aggregate for ASB) and asphalt cement mixed hot in a
mixing plant in accordance with these specifications. Unless otherwise specified, the
materials and construction shall conform to TxDOT Item 292 Asphalt Treatment (Plant
Mixed). The contractor's plant and equipment are subject to approval by the Engineer,
.and shall be appropriate and in suitable condition to produce the base material
consistently in compliance with these specifications.
In place compaction control is required for all ASB. The material shall be placed and
compacted to a minimum density as determined by TxDOT Test Method Tex- 126-E.
Samples of the compacted ASB will be removed by City personnel from locations
designated by the Engineer to determine composition, compaction, thickness, and density.
The contractor shall replace the pavement removed from core holes at no cost to the City.
ASB found to be deficient in composition, compaction, thickness, or density shall be
corrected at the contractor's expense as directed by the Engineer.
5.2 ASB MIX DESIGN
The contractor shall provide a current mix design using the approved materials indicating
gradation and optimum asphalt content. The aggregate mixture shall conform to the
following master gradation:
Sieve Size 1-1/2" 3/4" 1/2" #4 #40
Percent Retained by Weight 0 8-30 30-55 50-70 70-90
Material passing the #40 sieve shall be known as soil binder and shall meet the following
requirements:
Liquid Limit shall not exceed 45
Plasticity Index shall not exceed 15
Linear Shrinkage shall not exceed 5
The mineral aggregate shall not contain more than 0.5% moisture prior to entering the
pugmill for mixing with asphalt.
The ASB mixture shall consist of a uniform mixture of mineral aggregate and asphaltic
material. The mineral aggregate shall conform to the gradation requirements specified.
15
The percent asphaltic material shall be determined in accordance with Test Method Tex.-
126-E or Test Method Tex.-204-F and procedures outlined in TxDOT Bulletin C-14. In
no case shall the asphalt content be less than 4% or more than 9% by weight. Asphalt for
the mixture shall meet the requirments of TxDOT Item "Asphalt, Oils, and Emulsions".
The grade of asphalt and source must be approved by the Engineer prior to use.
The contractor shall submit the mix design prepared by a qualified lab for approval by the
Engineer. The Engineer will approve the asphalt content to be used in the mixture after
design tests have been made with the aggregate to be used. The asphalt content of the
production mixture shall not vary from the design more than 0.2% dry weight based on
total mixture.
5.3 PLACING ASB
Asphalt Stabilized Base shall be placed and compacted in 3 inch lifts to form a 9 inch
thick compacted base, unless otherwise directed by the Engineer. Prior to placing ASB,
the subgrade shall be prepared as previously specified. The cross-section shall be
constructed to form the specified crown on the HMAC surface at the centerline of the
street, or as indicated on the plans.
ASB shall not be placed when the air temperature, as reported by the National Weather
Service 748-1071 selection 2, is below 45 degrees F and falling. During June, July, and
August ASB shall be placed at a temperature between 255 and 285 degrees F. During
other months ASB shall be placed at a temperature between 275 and 325 degrees F. Any
ASB material that is above, or below the specified temperature range may be rejected by
the engineer. No payment will be made for any rejected material. Any ASB material that
is rejected shall be disposed of at a location observed and approved by the engineer's
representative.
The ASB material shall be spread on the approved prepared surface using an approved
spreading machine. The material shall be placed in such a manner that when properly
compacted the finished course is smooth, of uniform density, and in conformance with
the cross -sections and grades shown on the associated plans.
5.4 ASB COMPACTION
The ASB shall be compacted thoroughly and uniformly with approved rollers to a density
of 93% to 96% of Marshall Density. Lab specimens for Marshall Density shall be
molded at 275 degrees F for mixes using Performance Grade asphalt, and 250 degrees F
for mixes using AC-10.
16
Rolling shall be continued until no further increase in density can be obtained and all
roller marks are eliminated. Compaction shall be completed before the ASB mixture
cools below 185 degrees F.
The compacted ASB shall conform the cross -sections, lines, and grades shown on the
plans or as directed by the Engineer. The surface shall be smooth and have a uniform
texture acceptable to the Engineer.
6.1 HOT MIX ASPHALT CONCRETE SURFACE (HMAC)
Hot mix asphalt concrete surface shall consist of a minimum of one and one half inch
thick compacted mixture of coarse aggregate, fine aggregate, mineral filler (if required),
and asphalt cement mixed hot in a mixing plant in accordance with these specifications.
Unless otherwise specified, the materials and construction shall conform to TxDOT Item
340 Dense Graded Hot Mix Asphalt Method.
The contractor's plant and equipment are subject to approval by the Engineer, and shall
be appropriate and in suitable condition to produce the HMAC surface consistently in
compliance with these specifications. Approval of the source and character of the
materials shall be obtained from the Engineer prior to use. The combined mineral
aggregate , after final processing by the mixing plant and prior to addition of asphalt and
mineral filler, shall have a sand equivalent value of not less than
45 when tested in accordance with Test Method Tex 203-F. The percent of flat of
elongated slivers of stone for any aggregate shall not exceed 25% when tested in
accordance with Test Method Tex 224-F.
Asphaltic mixtures with aggregates which exhibit stripping characteristics shall be
conditioned with either lime or liquid anti -stripping agent approved by the Engineer.
Anti -stripping agents shall meet requirements of TxDOT Item "Asphalt Anti -stripping
Agents", and shall be added at the manufacturer's recommended dosage and temperature
range.
Core samples. of the HMAC surface will be removed by City personnel from locations
designated by the Engineer (minimum of 2 cores per 600 foot block) to determine
composition, compaction, thickness, and density. HMAC surface found to be deficient in
composition, compaction, thickness, or density shall be corrected at the contractor's
expense as directed by the Engineer. The contractor shall replace the pavement removed
from core holes at no cost to the City.
17
6.2 THICKNESS OF HMAC SURFACE
The thickness of HMAC surface shall be a minimum of one and one half (1-1/2) inches,
unless otherwise indicated on plans. If only one core measures zero to 1/4 inch less than
required thickness no corrective action shall be required. If two or more cores measure at
least 1/4 inch less than the specified thickness, the HMAC surface shall be considered
deficient with respect to thickness. Additional cores will be taken at 25 foot spacing to
define the limits of deficiency. No additional compensation will be made to the
contractor for thickness of HMAC surface greater than specified.
The paving surface shall not have variations exceeding 1/8 inch between any two contact
points on a 10 foot straightedge. Defects shall be remedied as directed by the engineer
using methods specified in TxDOT Item 585 Ride Quality for Pavement Surfaces.
6.3 MIX DESIGN
The contractor shall provide a current HMAC mix design using the approved materials,
indicating gradation and optimum asphalt content.
If approved by the engineer the contractor may furnish an alternate mix design based on
specific proposed materials. Otherwise the aggregate mixture shall conform to the
following master gradation:
Tvpe "C" (Coarse Graded Surface Course - Streets Greater than 36 feet wide
Percent passing 7/8"
100
Percent passing 5/8"
98-100
Percent retained on 3/8"
12-25
Percent retained on No. 4
15-30
Percent retained on No. 10
12-30
Total percent retained on No. 10
53-65
Percent retained on No. 40
10-20
Percent retained on No. 80
5-15
Percent retained on No. 200
5-15
Percent passing No. 200
1-6
18
Tvoe "D" ( Fine Graded Surface Course - Streets 36 feet or less wide
Percent passing 5/8"
100
Percent retained on 3/8"
5-15
Percent retained on No. 4
30-50
Percent retained on No.10
12-30
Total Retained on No. 10
53-65
Percent retained on No.40
10-20
Percent retained on No. 80
5-15
Percent retained on No. 200
5-15
Percent passing No. 200
1-6
Material passing the No. 40 sieve shall be known as soil binder and shall meet the
following requirements:
Liquid Limit shall not exceed 45
Plasticity Index shall not exceed 15
Linear Shrinkage shall not exceed 5
The mineral aggregate shall not contain more than 0.5% moisture prior to entering the
pugmill for mixing with asphalt. The HMAC mixture shall consist of a uniform mixture
of mineral aggregate and asphalt material. The percent asphalt in the mixture shall be
determined to meet the Marshall Stability criteria as follows:
Marshall Criteria Type "C" Type "D"
Percent Asphalt Content Optimum plus 0.25% to 0.50%
- No. Blows (each end of specimen) 75 50
Stability (Lb.) 1500 1200
Flow (units of 0.01 inch) 8 min 16 max 8 min 18 max
Percent Air Voids 2 min 5 max 3 min 6 max
If approved by the Engineer, the contractor may provide an alternate mix design based on
his proposed materials. The contractor's materials and mix design shall meet all the
performance criteria addressed in these specifications, and will retain the optimum plus
0.25% to 0.50% asphalt content.
6.4 COARSE AGGREGATE
The coarse aggregate shall be the material retained on a No. 4 sieve, and shall consist of
clean, Washed, tough, durable fragments of crushed stone of uniform quality.
19
Mixing or combining of crushed gravel and crushed stone will not be permitted. Coarse
aggregate shall be crushed to the extent that produces a minimum of 80% crushed faces
for both Type "C" HMAC, and Type "D" HMAC, when tested in accordance with Test
Method Tex -460-A Part I "Determination of Crushed Face Count".
Coarse aggregate shall have a maximum loss of 15% when subjected to 4 cycles of the
Magnesium Sulfate Soundness Test ASTM C-88. The amount of organic matter, clays,
loams, or particles coated therewith, or other undesirable materials shall not exceed 2
percent. When subjected to the Los Angeles Abrasion Test, the coarse aggregate shall not
have a loss greater than 40 percent by weight.
Coarse aggregate may be enhanced by addition of crushed concrete (Class A minimum).
The crushed concrete shall be processed and blended at the contractor's batch plant. The
material shall be processed to remove wood, steel, and other objectionable materials so as
to produce a crushed aggregate in conformance with these specifications.
6.5 FINE AGGREGATE
The fine aggregate shall be that part of the material passing the No. 4 sieve and shall
consist of sand and/or screenings. The plasticity index of that part of the sand passing the
40 sieve shall not exceed 6. The plasticity index of the screenings shall not exceed 9.
Sand shall be composed of durable stone particles free from injurious foreign matter.
Sand content in mix design shall not be greater than 15%. Screenings shall be of the
same or similar material as specified for coarse aggregate.
Mineral filler shall consist of thoroughly dry stone dust, slate dust, Portland cement or
other material dust approved by the Engineer. The mineral filler shall be free of foreign
and other injurious matter and shall meet the following gradation:
Percent by Weight Retained on No. 30 Sieve 0
Percent by Weight Retained on No. 80 Sieve 10 maximum
Percent by Weight Retained on No. 200 Sieve 35 maximum
6.6 ASPHALT
Asphalt shall be AC 10 with Latex (3% by weight of asphalt, or the performance grade
asphalt currently used by the local TxDOT district. The contractor shall notify the
Engineer of the source of asphaltic material for approval prior to production of the
asphaltic mixture. The optimum asphalt content shall be determined by the Marshall
Stability method. The percent asphalt content in produced HMAC surface shall be
optimum plus 0.25% to 0.50% for Type "C" and Type "D" HMAC.
P
6.7 PLACING HMAC
HMAC surface shall be constructed to a minimum compacted thickness of 1-1/2 inches.
The pavement shall be constructed on the previously approved base. Placing of HMAC
shall not start until sunrise, and must stop one hour before sunset. HMAC surface shall
not be placed until at least 48 hours after the application of the prime coat.
Air temperature requirements for placing HMAC shall be as follows:
November 1 to April 1
HMAC shall not be placed when the air temperature is below 55 degrees F and falling.
HMAC may be placed when the air temperature is above 50 degrees F and rising.
April 1 to November 1
HMAC shall not be placed when the air temperature is below 50 degrees F and falling.
HMAC may be placed when the air temperature is above 45 degrees and rising.
Air temperature shall be determined by the National Weather Service hourly report,
748-1071 selection 2. If the temperature of any HMAC, measured while passing through
the lay down machine, is 25 degrees F more or less than the mixing temperature, the load
- shall be rejected. No payment will be made for rejected material. Any HMAC material
t that is rejected shall be disposed of at a location observed and approved by the engineer's
representative.
The asphaltic mixture shall be dumped and spread on the approved prepared surface using
an approved spreading and finishing machine. The material shall be placed in such a
manner that when properly compacted the finished course is smooth, of uniform density,
and in conformance with the cross -sections and grades shown on the associated plans.
Raking loose material back across the HMAC mat will not be permitted. Wings of the
laydown machine may not be dumped unless they are dumped after every load.
A level up course, 1/2 inch or more in thickness, shall require the use of ASB or a coarse
grade of HMAC approved by the Engineer.
When the asphaltic mixture is placed in a small area where use of a finishing machine is
not practical, the contractor may use other methods approved by the Engineer provided a
satisfactory surface can be obtained.
Adjacent to curbs gutters or other flush structures, the surface shall be finished uniformly
high so that when compacted it will be 1/4 inch above the curb or flush structure.
21
All joints shall present the same texture, density, and smoothness as other sections of the
course. The joints between old and new pavements or between successive day's work
shall be made to insure a continuous bond between the old and new sections of the
course. The transverse edges of old pavement and, if required by the Engineer, the
successive day's pavement shall be cut with an approved concrete saw to expose an even
vertical surface for the full thickness of the course. All contact surfaces of previously
constructed pavement shall be painted with a thin uniform coat of hot Bituminous
material before the fresh mixture is placed.
6.8 COMPACTION
HMAC surface compaction shall be 94% to 98% of Marshall density (2% to 6% air
voids). Using appropriate rollers approved by the Engineer, the pavement shall be
compacted thoroughly and uniformly to a density consistent with the density developed in
the laboratory Marshall test method of molding stability specimens. At a minimum one
tandem roller weighing not less than 8 tons, two pneumatic rollers with a weight capable
of being uniformly varied from 275 to 550 psi per inch width of tire tread, and one three
wheel roller weighing not less than 10 tons shall be provided for each job. Additional
rollers shall be provided by the contractor if needed.
Rolling with three wheel and tandem rollers shall start longitudinally at the sides and
proceed toward the center of the pavement, overlapping on successive trips by at least
half the width of the rear wheels. Alternate trips of the roller shall be slightly different in
length. On super -elevated curves rolling shall begin at the low side and progress toward
the high side.
Rolling with pneumatic rollers shall be done as directed by the Engineer and shall be
continued until required compaction is obtained and all roller marks are eliminated.
The motion of the rollers shall be slow enough to avoid displacement of the mixture.
Rollers shall not be permitted to stand on pavement which has not been fully compacted.
Any displacement of the mixture shall be corrected immediately by the use of rakes and
fresh mixture where required.
Gasoline, oil, grease, solvents, or other foreign matter shall not be permitted to fall on the
pavement when rollers are in operation or standing.
Places inaccessible to the rollers may be compacted using lightly oiled tamps. Trenches
and other limited areas where required compaction cannot be obtained using a three
wheel roller shall be compacted with a trench type roller.
22
The surface of the pavement after compaction shall be smooth and true to the established
line, grade, and cross-section. When tested with a 10 foot straight edge placed parallel to
the centerline of the roadway, or other means acceptable to the Engineer, the maximum
deviation shall be not exceed 1/8 inch in 10 feet. An acceptable 10 foot straight edge
shall be provided by the contractor. Any point in the surface not meeting this requirement
shall be corrected as directed by the Engineer. When placed on existing surfaces, the 1/8
inch maximum deviation requirement may be waived by the Engineer.
6.9 PRIME AND TACK COATS
Prior to placing HMAC on flexible base, the surface shall be primed using an application
of 0.20 gallons of asphalt per square yard of surface.
Before any asphaltic mixture is laid, the surfaces against which the pavement is to be
placed shall be cleaned to the satisfaction of the Engineer. The surfaces shall be given a
uniform application of tack coat using asphaltic materials of this specification. The tack
coat shall be applied as directed by the Engineer with an approved sprayer. Where the
pavement mixture will adhere, as determined by the Engineer, to the surfaces on which it
is to be placed without the use of a tack coat, the Engineer may waive the requirement for
the tack coat. All contact surfaces of curbs, structures, and joints shall be painted with a
thin uniform tack coat.
The prime, or tack coat, shall be asphalt materials such as AC-10, undiluted CSS-1H,
or a similar product as approved by the engineer.
6.10 EMULSIFIED ASPHALT SEALER
All HMAC surface courses shall be sprayed with an emulsified asphalt sealer consisting
of a 15/85 mixture of CSS-1H, or 20/80 SS-1, liquid anionic asphalt and distilled water.
The emulsified asphalt sealer shall be applied after the HMAC surface has cooled to
below 70 degrees F, and shall be applied at a rate of 0.10 to 0.12 gallons per square yard
of surface.
7.1 STORM SEWER
Storm sewer shall include installation of pipe, manholes, inlet structures and outlet
structures. Contractor shall use only materials, tools, methods, and equipment considered
standard by the pipeline construction industry, and approved by the Engineer. Grade and
horizontal alignment shall be maintained using a laser or batter boards.
23
7.2 REINFORCED CONCRETE PIPE
Storm sewer shall be constructed using reinforced concrete pipe, either precast or cast in
place. The pipe shall conform to the requirements of AASHTO M-170 or ASTM C-76.
Pipe shall be Class III unless otherwise noted on plan sheets.
7.3 MORTAR
Mortar shall be used for caulking and filling between pipe and drainage structures.
Mortar shall be composed of 1 part, by volume, of Portland cement and 2 parts of mortar
sand. The Portland cement shall conform to the requirements of ASTM C-150, Type I.
The sand shall conform to the requirements of ASTM C-144. Hydrated lime maybe
added to the mixture of sand and cement in an amount equal to 15% of the weight of
cement used. The hydrated lime shall meet the requirements of ASTM C-6.
Mortar which has not been used after 45 minutes of having water added shall be
discarded. Mortar may not be retempered by having water added.
7.4 PREFORMED BITUMINUS GASKET JOINTS
Preformed bituminous gaskets for concrete non -pressure pipe shall conform to the
requirements of Fed. Spec. SS-S-00210 (GSA-FSS), and shall be Ram-Nek or approved
equal. Gaskets shall be installed in accordance with manufacturer's recommendations
and shall form a water -tight joint.
7.5 MANHOLES
Manhole barrel, cone and extension sections shall be constructed of precast concrete. A
plant inspection may be required for production facility inspection and to review record -
keeping for material certification.
The manufacturer must provide certification that all materials used for manufacturing
meet with the following ASTM Specifications.
Aggregates ASTM C-33
Cement ASTM C-150
Sampling Specimens ASTM C-39
Reinforcing ASTM C-185
Sand and Mortar ASTM C-144
24
Precast concrete sections for manholes shall conform to ASTM C-478 specifications.
Compressive strength test results must verify concrete strengths meet or exceed 4,000 psi.
Aggregate shall be crushed limestone and shall conform to ASTM C-33 specifications.
Joints, excepting grade rings, shall be tongue and groove or an equivalent male and
female type joint as approved by the Engineer. All joints shall be effectively jointed to
prevent leakage and infiltration. All connections between wall sections shall be joined
with Conseal Joint Sealant or approved equal to provide a watertight manhole. This
sealant will be provided by supplier and will be considered an essential part of each
shipment. All cones and adjusting rings shall maintain a clear 24" opening. Adjusting
rings shall be reinforced with the same percentage of steel as risers and tops and will also
meet ASTM
C-478 specifications. Adjusting rings, as well as all precast concrete manhole products,
shall be smooth, uniform in size and dimensions, consistent in components throughout
and free of voids or honeycombs.
All manholes shall be designed to withstand H-20 AASHTO loading. They shall also
have lifting holes that do not protrude through manhole wall; one full inch of concrete
thickness must remain between lift hole and outside wall of manhole.
Manhole barrels shall be assembled of precast riser section. Riser sections and top cone
sections shall be placed vertically with tongues and grooves properly keyed.
Invert channels shall be smooth and semi -circular in shape conforming to the inside of the
adjacent pipe section. Changes in direction of flow shall be made with a smooth curve of
as large a radius as the size of the manhole with permit. Changes in size and grade of the
channels shall be made gradually and evenly. The invert channels may be formed directly
in the concrete of the manhole base or may be half -pipe laid in concrete. The floor of the
manhole outside the channel shall be smooth and shall slope toward the channel not less
than one inch per foot, nor more than two inches per foot.
All connections between the riser or base sections and the sewer pipe shall be joined in
such a manner as to make the manholes watertight. Preformed rubber waterstop gaskets
cast into the riser or base section are acceptable. Preformed flexible plastic sealing
compounds equivalent to "Ram-nek" or "Kent Seal" may be used provided a watertight
v. seal is achieved.
Adjusting rings may be used for adjusting the top elevation, except that the total height of
the adjusting rings shall not exceed 12 inches at any manhole. Concrete shall be placed
around and under the rings to provide a seal and seat the ring at the proper elevation.
Each manhole shall have a minimum of 6 inches of grade adjustment.
25
7.6 MANHOLE FRAMES AND COVERS
Manhole frames and covers shall be of good quality gray iron casting and conform to
ASTM A-48, having a clear opening of not less than 22 inches. The casting shall be
designed with a full bearing ring so as to provide a continuous seat between frame and
cover. The cover shall be furnished with lifting ring cast into the cover in such manner as
to prevent water leaking through. Frame and cover shall have a weight of not less than
275 pounds. The manhole ring and cover shall be Western Iron Works #40 or approved
equal.
7.7 CONSTRUCTION METHODS
All equipment necessary and required for the proper construction of storm sewers,
manholes and culverts shall be on the project, in first-class working condition, and
approved by the Engineer before construction is permitted to start. If precast concrete
pipe or manhole sections are used, the Contractor shall provide appropriate hoisting
equipment to handle the pipe or sections while unloading and placing it in its final
position without damage to the pipe.
The Contractor shall provide hand tampers and pneumatic tampers to obtain the required
compaction of the pipe bed, the manhole bed and the backfill, as specified.
7.8 EXCAVATION
The Contractor shall do all excavation to the depth shown on the plans. Where rock, or
soil containing rocks or gravel, hard pan or other unyielding foundation material is
encountered in trench excavation, the pipe shall be bedded in accordance with the
requirements of one of the classes of bedding, and the hard unyielding material shall be
excavated below the elevation of the bottom of the pipe or pipe bell to a depth of at least
8 inches or 1/2 inch for each foot of fill over the top of the pipe, whichever is greater, but
not more than three -fourths the nominal diameter of the pipe. The cushion shall consist
of a fine compressive material, such as silty clay or loam, lightly compacted, and shaped
as required for the specified class of bedding. The cost of furnishing and placing the
cushion material shall be included in the bid price per linear foot of pipe in place. The
bottom of the trench shall be excavated to a horizontal section as far as practicable.
Excavated material not required or acceptable for backfill shall be disposed of by the
Contractor as directed by the Engineer. Excavation shall not be carried below the
required depth; but when it is, the trench shall be backfilled at the Contractor's expense
with material approved by the Engineer and compacted to the density of the surrounding
earth material as determined by AASHTO T-180.
FM
When directed, unstable soil shall be removed for the full width of the trench and
replaced with sand or with approved granular material. The Engineer shall determine the
depth of removal of unstable soil and the amount of backfill necessary. The backfill shall
be compacted and shaped to a firm but slightly yielding condition to form the bed for the
pipe.
Grades for pipe shall be as shown on the drawings. No changes in grade will be made
unless so directed by the Engineer. The minimum width of the trench at the top of the
pipe, when placed, shall be a width which will permit the proper construction of joints
and compaction of backfill around the pipe. The sides of the trench shall be vertical,
unless otherwise approved by the Engineer. The maximum allowable width of the trench
shall not exceed the widths shown below unless otherwise approved by the Engineer.
NOMINAL PIPE
MINIMUM TRENCH
MAXIMUM TRENCH
SIZE
WIDTH AT SPRINGLINE
WIDTH AT TOP OF PIPE
Less than 18"
Pipe O.D. + 12"
Pipe O.D. + 18"
18" thru 36"
Pipe O.D. + 18"
Pipe O.D. + 24"
37" thru 60"
Pipe O.D. + 24"
Pipe O.D. + 30"
The width of the trench above the top of the pipe may be as wide as necessary for shoring,
bracing or proper installation of the pipe. Excavation in paved areas shall be confined to
a minimum practical width. The bed for pipe shall be so shaped that at least the lower
quarter of the pipe circumference shall be in continuous contact with the bottom of the
trench.
The excavation for manholes shall be essentially the same as that for the piping. The
-W sides of the excavation shall be vertical unless otherwise approved by the Engineer. The
Contractor shall do such trench bracing, sheathing or shoring necessary to perform and
protect the excavation as required for safety and conformance to applicable laws and
regulations. The bracing, sheathing, or shoring shall not be removed in one operation but
shall be done in successive stages to prevent overloading of the pipe during backfilling
operations. The cost of the bracing, sheathing, or shoring and the removal of same, shall
be included in the unit price bid per foot for the pipe.
Surface water shall be prevented from entering the excavation. Heavy equipment, except
for excavating equipment, shall not be operated within 20 feet of the edge of the
excavation. Excavated materials shall be stockpiled no closer than 3 feet from the edge
of the excavation.
27
7.9 PIPE INSTALLATION
The Contractor shall provide the appropriate tools and methods to insure installation of
the pipe to line and grade, as shown on the drawings. The Contractor's facilities for
lowering precast pipe into the trench shall be such that neither the pipe nor the trench will
be damaged or disturbed. The Engineer shall inspect all precast pipe before it is placed.
Any section that is damaged by handling or is defective to a degree which in the opinion
of the Engineer will materially affect the function and service of the pipe shall be rejected
and removed from the job site.
Installing the precast pipe in the finished trench shall be started at the lowest point and is
laid upgrade. For tongue and groove precast pipe, the grooved end shall be laid upgrade.
The pipe shall be firmly and accurately installed to line and grade so that the invert will
be smooth and uniform. The pipe shall be protected from water during placing and until
the concrete, in cast -in -place pipe, or the mortar, in the joints of precast or cast in place
pipe, has thoroughly set. The contractor shall provide temporary diversions as necessary
to prevent surface water flow into the excavation.
Pipe shall not be laid or installed on frozen ground.
Pipe which is not true in alignment, or which shows any change in grade after laying or
installing, shall be taken up and re-laid or re -installed without extra compensation.
Mortar shall be used for caulking and filling between the pipe and the drainage structures.
Mortar that is not used within 45 minutes after water has been added shall be discarded.
Retempering of mortar shall not be permitted. Pipe joints for precast concrete pipe shall
be of the tongue and groove type. The joints shall be of a water tight joint. Each joint
shall be sealed with a preformed bituminous gasket as specified. The gasket shall be
installed as recommended by the pipe manufacturer.
Field poured concrete bases shall be at least 12 inches thick and not less than 1 (one) foot
greater diameter than the outside diameter of the manhole riser section. Concrete shall be
Class A at a minimum 3000 psi 28 day compressive strength. Concrete placement shall
conform to ACI and good construction practices. Concrete shall be consolidated and
struck -off to a horizontal surface within the forms or pouring rings.
Field poured concrete bases shall be reinforced as detailed on the Plans or as shown in the
Standard Details. The manhole shall be constructed to ASTM C-891 standards.
Precast reinforced concrete bases shall be of the size and shape detailed on the Plans or as
shown in the Standard Details.
►:
7.10 BACKFILLING
All trenches and excavations shall be backfilled as the pipes and manholes are installed,
unless otherwise directed by the Engineer. Outside of street right of way the backfill
material shall be selected granular material from excavation or borrow; material which is
placed at the sides of the pipe and manhole and 1 foot over the top shall be material
which can be readily compacted. It shall not contain stones retained on a 2-inch sieve,
frozen lumps, chunks of highly plastic clay, or any other material which is objectionable
to the Engineer. The Material shall be moistened or dried, if necessary, to be compacted
by the method in use. Backfill material shall be approved by the Engineer.
The backfill shall be placed in loose layers not to exceed 6 inches in depth along each
side of the pipe and manhole. Special care shall be taken to secure thorough compaction
under the haunches and at the sides of the pipe and manhole. This backfill shall be
brought up evenly on each side of the structure to an elevation of 1 foot over the top of
the pipe, or such greater elevation as directed by the Engineer.
Backfilling shall be done in a manner to avoid injurious top or side pressures on the pipe
and manhole. Backfill shall be compacted to 95% (min.) Standard Proctor Density.
Unless otherwise directed by the Engineer or plans, excavation within street right of way
shall be backfilled with flowable fill material (2-sacks of cement per cubic yard concrete
mix) to 1-1/2 inches below the asphalt surface. The pipe shall be restrained so that during
the pour the pipe shall not be displaced.
Movement of construction machinery over a culvert, pipeline, or manhole shall be at the
Contractor's risk. Any damaged construction shall be removed and replaced at the
expense of the Contractor.
7.11 TRENCH PROTECTION
Trench excavations not exceeding five feet in depth shall be protected in accordance with
applicable OSHA, state, and local requirements. Trench excavations greater than five
feet in depth shall be protected in accordance with the following specifications. All work
performed under this section shall also comply with OSHA Part 1926, Subpart P and all
State and Local codes. The Contractor shall be responsible for complying with all trench
safety requirements, the requirements of the specifications, drawings and all applicable
codes.
29
Trench protection shall be performed by forces having at least two years experience with
similar types of trench safety systems. The manufacturer of prefabricated items used in
trench safety systems shall have at least two years of experience in fabricating the items.
The contractor shall provide detailed drawings for proposed trench safety systems. The
drawings shall identify where each system is proposed for use and type of system to be
used. Trench excavations shall not be started until trench safety systems have been
submitted and approved by the Engineer.
If trench boxes are to be used, the contractor shall submit manufacturer's standard data
sheet and certificate of compliance stating the maximum allowable depth for the given
design pressure for each type of trench box proposed for use.
If alternative systems composed of steel, aluminum, wood or a combination of materials
are proposed, the contractor shall submit design data demonstrating the ability of the
proposed materials to provide the necessary trench protection.
Materials used for trench safety shall be capable of withstanding imposed loads without
excessive deflections. Materials shall be clean, free of rust, holes, knots and other
defects, and shall conform to the following:
Steel — Steel shall be of type and thickness as required and shall have a minimum
yield stress of 36 ksi.
Aluminum — Type 6061-T6, thickness as required.
Wood in Contact with Earth — Pressure treated woods.
Wood not in Contact with Earth — Soft or hardwood as required.
8.1 FENCES
Unless otherwise indicated on plans, existing fences which must be adjusted or relocated
shall be reconstructed using the same or equivalent materials, height, and construction in
the proper location. The contractor shall remove existing fence and either store for reuse
or legally dispose of the fence materials, whichever is appropriate.
New fence construction shall be in accordance with specifications and details included on
plan sheets.
30
9.1 SALVAGE OF ASPHALT PAVING
All salvage asphalt material shall be broken into pieces not more than 1 inch in size and
stockpiled at a location indicated in the plans. Any non -asphaltic materials, such as
flexible base and soil, shall be kept separated from the salvaged asphalt.
10.1 BARRICADES
Prior to starting work on any project covered by these specifications, the contractor shall
submit a Traffic Control Plan for approval by the Engineer. The contractor shall have the
sole responsibility for providing, installing, moving, replacing, maintaining, cleaning, and
removing upon completion of work, all traffic control devices. The Traffic Control Plan
and devices shall be in compliance with the Texas Manual of Uniform Traffic Control
Devices (MUTCD) and the 1993 National Cooperative Highway Research Program
Report 350 (NCHRP 350).
The Traffic Control Plan approved by the Engineer shall be considered the minimum
requirement for the project. The contractor shall provide additional devices as
determined to be necessary during the project. If at any time during construction the
approved plan does not accomplish the intended purpose, due to weather or other
conditions affecting the safe handling of traffic, the contractor shall immediately make
necessary changes to correct the unsatisfactory conditions.
The contractor shall maintain ingress and egress to private property at all times.
All signing and barricading shall be in place before construction operations are started
and during all times construction is in progress. All hazards shall be clearly marked and
adequately protected. If pedestrian walkways are blocked, pedestrian control shall
conform to "Typical Sidewalk and Curb -Lane Closure for Pedestrian Control" as
indicated in Texas MUTCD.
No separate payment will be made for traffic control. The required plan and devices shall
be considered to be subsidiary to pay items.
31
11.1 PROSECUTION OF THE WORK AND WORKING DAYS
During the period the contractor is directing traffic over the base, the surface shall be
satisfactorily maintained by the use of sprinkling and blading as required, so that no
hazard will result. The base course shall be maintained until the wearing surface is
placed thereon.
At no time during the period of construction shall driveways and/or alleys be left
impassable between the night hours of 6:00 PM to 6:00 AM, except during the
construction of curb and gutter for which the driveways and/or alley's shall remain closed
not more than 4 days.
No work will be performed after dark or before daylight.
11.2 WORKING DAYS DEFINITION
City contracted paving projects will be based on working days allowed. No requests for
extensions of time will be considered. A working day is defined as a calendar day, not
including Saturdays, Sundays, or City of Lubbock designated holidays, in which weather
or other conditions beyond control of the contractor will permit the performance of the
principal unit of work for a continuous period of not less than 7 hours between 7:00 am
and 6:00 pm.
Work on Saturdays, Sundays, or City of Lubbock designated holidays must be authorized
by the Engineer (see item 11.3). For each Saturday, Sunday, or City of Lubbock
designated holiday on which the Contractor chooses to work and has authorization from
the Engineer to work, 1 day will be charged against the contract working time when
conditions will permit at least 7 hours of work as described above. Work on Sunday will
not be authorized except in cases of extreme emergency, as determined by the Engineer.
Working days will be considered to begin on the effective date stated in the Notice to
Proceed, unless the contractor is unable to begin work on that date due to factors beyond
his control as determined by the Engineer. In that event, time charged against the project
will begin on the date the contractor could first work a minimum of 7 hours as described
above.
The Engineer will furnish the contractor a monthly statement showing the number of
working days used and the working days remaining. The contractor shall be allowed 10
calendar days in which to protest the correctness of each statement. The protest shall be
32
in writing, addressed to the Engineer, and shall indicate basis of the protest. The
Engineer shall respond to the protest within 10 calendar days of receiving the protest.
Failure to file a protest within the allotted 10 days for any statement shall indicate the
contractor's approval of the time charges as shown on that period's time statement, and
future consideration of that time statement will not be permitted.
11.3 WORK BETWEEN NOVEMBER 1 AND JANUARY 2, AND ON OTHER
HOLIDAYS
If conditions are such that, in the opinion of the Engineer, construction will negatively
affect local businesses during holiday periods, the Engineer may suspend construction
operations from November 1 to January 2.
The City of Lubbock observes specific holidays, and City staff is not required to work
those days. As standard procedure, construction operations that require testing/inspection
may not be performed on those holidays. If the contractor needs to perform construction
operations that require City personnel on holidays, the contractor shall make a written
request for authorization to work from the Engineer. The request shall state the reason
the work is necessary, and shall state that the contractor agrees to pay the City for the
related personnel expenses including salary, overtime, and benefits. If City personnel are
available, the Engineer may approve the request.
12.1 MEASUREMENT AND PAYMENT
The unit price bid on each item as stated in the bid proposal shall include furnishing all
labor, superintendence, machinery, equipment, and materials, except as otherwise
specified, necessary or incidental to complete the various items of work in accordance
with the plans and specifications. Cost of work or materials shown on the plans or called
for in the specifications and on which no separate payment is made shall be included in
the bid prices on the various pay items.
Payment will not be made for any item that is not complete, including all associated
incidental work. All of the items covered by these standard specifications may not be
included in a particular project. Only those items indicated on bid documents and plan
sheets shall be included for construction and payment.
33
12.2 CURB AND GUTTER
Measurement will be made of the linear feet of curb and gutter actually constructed. Curb
and gutter will be paid for at the unit price bid per linear foot. The unit price bid shall
include furnishing and installing all materials, excavation, filling, backfilling, forming,
finishing, and all incidentals necessary to complete the work.
12.3 CONCRETE FLAT SLABS - SIDEWALK, DRIVEWAY, ALLEY RETURN,
ALLEY PAVING, AND VALLEY GUTTER
Measurement will be made of the area, in square feet, of flat slab actually constructed.
Flat slabs will be paid for at the unit price bid per square foot for each specific type of
slab. Curb on alley returns shall be included in the area measured for the slab and will
not be paid as a separate item. The unit price bid shall include furnishing and installing
all materials, excavation, filling, backfilling, reinforcement, forming, finishing, joint
cutting, joint sealing, and all incidentals necessary to complete the work.
12.4 CURB RAMPS (HANDICAP RAMPS)
Measurement will be made of the area, in square feet, of curb ramp actually constructed,
excluding top surface area of any retaining wall. Curb ramps will be paid for at the unit
price bid per square foot. The unit price bid shall include furnishing and installing all
materials, excavation and filling within two feet of the ramp, back filling, reinforcement,
forming, finishing, and all incidentals necessary to complete the work.
12.5 CONCRETE DRAINAGE CHANNEL
Measurement will be made of the area, in square feet, of drainage channel actually
constructed, including top surface area of any retaining wall or curb. Drainage channel
will be paid for at the unit price bid per square foot. The unit price bid shall include
furnishing and installing all materials, excavation and filling within two feet of the
channel, backfilling, reinforcement, forming, finishing, and all incidentals necessary to
complete the work.
12.6 RETAINING WALL OR CURB ON DRAINAGE CHANNELS AND CURB
RAMPS
Measurement will be made of the height from bottom of footing or slab to top of wall,
and linear feet of wall or curb actually constructed. Retaining wall or curb will be paid
for at the unit price bid per cubic foot.
34
The unit price bid shall include furnishing and installing all materials, excavation, filling,
backfilling, reinforcement, forming, finishing, and all incidentals necessary to complete
the work.
12.7 CONCRETE MEDIAN
Measurement will be made of the area, in square feet, of median actually constructed.
Median will be paid for at the unit price bid per square foot. The unit price bid shall
include furnishing and installing all materials, excavation, filling, reinforcement, forming,
finishing, and all incidentals necessary to complete the work.
12.8 CONCRETE STREET PAVING
Measurement will be made of the area, in square yards, of concrete street paving actually
constructed. Concrete street paving will be paid for at the unit price bid per square yard.
The unit price bid shall include furnishing and installing all materials, excavation, filling,
backfilling, reinforcement, forming, finishing, and all incidentals necessary to complete
the work.
Sawing and sealing of joints shall not be included and will be paid for as a separate bid
item.
12.9 SAWING AND SEALING OF JOINTS IN CONCRETE STREET PAVING
Measurement will be made of the linear feet of sawed and sealed joints actually
constructed. Sawing and sealing of joints will be paid for at the unit price bid per linear
foot. The unit price bid shall include furnishing and installing all materials, equipment,
sawing, cleaning, seal components, and all incidentals necessary to complete the work.
12.10 STORM SEWER INLET BOX AND MANHOLES
Storm sewer inlet boxes and manholes will be paid for at the unit price bid per each. The
unit price bid shall include furnishing and installing all materials, excavation, filling
(except flowable fill), floor, connection to pipes, reinforcement, forming, finishing,
manhole rings and covers, and all incidentals necessary to complete the work.
12.11 HEADWALLS
Storm sewer headwalls will be paid for at the unit price bid per each. The unit price bid
- shall include furnishing and installing all materials, excavation, filling, reinforcement,
forming, finishing, grates, and all incidentals necessary to complete the work.
35
12.12 STORM SEWER PIPE
Measurement along the centerline of the pipe will be made of the actual length of pipe
constructed, from face of structure to face of structure or to centerline of manhole, and
will be paid for at the unit price bid for Storm Sewer. Depth of cut shall be considered to
be from the top of the adjacent grade stake to the flowline of the pipe. The unit price bid
shall include furnishing and installing all materials, pavement removal, excavation,
filling, backfilling with compacted soil where applicable, and all incidentals necessary to
complete the work. Flowable fill will be paid for as a separate pay item.
12.13 EXTRA VERTICAL FEET OF MANHOLE
The actual constructed manhole will be measured from the top of the base to the top of
the ring and cover. Any depth of manhole exceeding 6 feet in depth will be paid for at the
unit price bid for extra vertical feet of manhole. The unit price bid shall include
furnishing and installing all materials and all incidentals necessary to complete the work.
12.14 CURB AND GUTTER REMOVAL
Measurement will be made of the linear feet of curb and gutter actually removed.
Payment will be made at the unit price bid per linear foot of curb and gutter removed.
The contractor shall ensure that the Engineer has the opportunity to measure the linear
feet of curb and gutter prior to removal. If curb and gutter is removed without
measurement by the Engineer, no payment will be made for that removal. The unit price
bid shall include sawing, hauling, labor and equipment, and legal disposal for removal of
the curb and gutter.
12.15 CONCRETE SLAB REMOVAL
Measurement will be made of the area in square feet of concrete slab actually removed.
Payment will be made at the unit price bid per square foot of concrete slab removed. The
contractor shall ensure that the Engineer has the opportunity to measure the area of
concrete slab prior to removal. If concrete slab is removed without measurement by the
Engineer, no payment will be made for that removal. The unit price bid shall include
sawing, breaking, hauling, labor and equipment, and legal disposal for removal of the
concrete slab.
36
12.16 2 SACK FLOWABLE FILL
Quantities of 2 sack flowable fill will be determined from tickets provided by the drivers
of the delivery trucks.
Payment will be made at the unit price bid per cubic yard of in place 2 sack flowable fill.
The unit price bid shall include furnishing and placing the material and all incidentals
necessary to complete the work.
12.17 ASPHALT PAVING
Measurement will be made of the area, in square yards, of asphalt paving actually
constructed. Payment will be made at the unit price bid per square yard. The unit price
bid shall include furnishing and installing all materials, subgrade preparation,
construction of caliche or asphalt stabilized base as specified, excavation, filling, tack and
prime coats, HMAC surface, emulsion seal, and all incidentals necessary to complete the
work.
12.18 ASPHALT PAVING REPAIR
Measurement will be made of the area, in square yards, of in place asphalt paving repair.
Payment will be made at the unit price bid per square yard of paving repair. The unit
price bid shall include furnishing and placing all asphaltic materials, sawing of existing
paving edges, smoothing and preparation of the existing base, flowable fill if required,
tack and prime coats, compaction, and all incidentals necessary to complete the work.
12.19 EXCAVATION AND GRADING (OUTSIDE LIMITS OF
CONSTRUCTION)
Volume of excavation or fill, in cubic yards, will be determined by average end area
method. Payment will be made at the unit price bid per cubic yard of completed
excavation or fill. The unit price bid shall include all labor, equipment, and incidentals
necessary to excavate or fill the site to the grades established by the Engineer. No
separate payment will be made for disposing of excess material.
12.20 DITCH GRADING AND UNPAVED STREET SURFACE GRADING
The volume of ditch grading, in cubic yards, will be determined by average end area
method. Measurement will be made of the area, in square yards, of completed surface
grading of unpaved streets. Payment will be made at the unit price bid per cubic yard of
37
completed ditch grading per cubic yard, or surface grading per square yard. The unit
price bid shall include all labor, equipment, and incidentals necessary to grade ditches or
surface grade unpaved streets to the grades established by the Engineer. No separate
payment will be made for disposing of excess material.
13.1 STANDARD DETAILS
Construction shall be in accordance with the following standard details unless otherwise
indicated on plans, or directed by the Engineer. The 24 inch curb and gutter details shall
be considered to be standard. 30 inch curb and gutter details shall apply only if
specifically indicated on plans or bid documents.
STREET CROWN ELEVATIONS
PAVEMENT WIDTH
FINISHED PAVING SURFACE
CURB FACE TO CURB FACE
ABOVE GUTTER
22 feet
0.32 feet
24 feet
0.35 feet
26 feet
0.37 feet
28 feet
0.40 feet
30 feet
0.42 feet
32 feet
0.45 feet
36 feet
0.50 feet
42 feet
0.57 feet
46 feet
0.62 feet
52 feet
0.69 feet
64 feet
0.85 feet
66 feet
0.86 feet
86 feet
1.14 feet
88 feet
1.15 feet
All street paving shall incorporate a centerline crown at the listed elevation unless
otherwise indicated on plans, or as directed by the Engineer. The widths listed above
refer to the total proposed future full width of street.