RESOLUTION
RESOLUTION ACCEPTING IMPROVEMENTS ON PORTIONS OF STREETS, AND/OR
AVENUES AS LISTED BELOW AND ORDERING THE ISSUANCE OF CERTIFICATES IN EVIDENCE
OF ASSESSMENTS LEVIED.
WHEREAS, the City of Lubbock heretofore passed various street improvement
ordinances and resolutions and entered into contract with Kerr Construction Company
(G.W.O. 2993) for the making and construction of street improvements on portions
of numerous streets and/or avenues in said City including among others the followin
Peoria Avenue from its intersection with a line 3.0 feet South of the South
property line of the alley North of 16th Street to its intersection with a line
8.0 feet North of the North property line of 16th Street, known and designated
as Sub -Unit No. 22 of Unit 2208.
AND WHEREAS, the improvements upon the said portions of the abovementione
streets and/or avenues, have been inspected and found to have been constructed
in accordance with terms of said contract (G.W.O. 2993).
THEREFORE, BE IT RESOLVED BY THE CITY OF LUBBOCK, TEXAS:
I.
That the improvements on said portions of the abovementioned streets,
and/or avenues,beaand'.the tame�are hereby accepted, and the City Engineer be and
he is hereby authorized to direct payment of the City's portion of the cost.
U.
That the Mayor and City Secretary be, and they are hereby instructed
to execute and deliver certificates in evidence of the assessments levied against
the parcels of property abutting upon the said portions of the streets and/or
avenues listed above and against the owners of such property in accordance with
law and in the manner provided in said contract, and the proceedings with reference
to said improvements and assessments where such assessments were levied.
III.
This resolution shall take effect and be in forte from and after its
passage.
PASSED AND APPROVED THIS 23RD DAY OF J Y 0.
ATTEST:
Q , I— ff&!!T
Lavenia Lowe, City Se retary
'0A� �s
1Wi 33 acila ', 33!t3P2M .neer
r
APPROVED : „
;.� 16ery�e�,Jr�'_,Gity". �ft,�gfrne
41 (i
PORTER 2-6411
BOX 2000
LUBBOCK. TEXAS 7 9 4 0 a
July 23, 1970
Honorable Mayor and City Council
Lubbock, Texas
Gentlemen:
I have examined the paving improvements constructed by Kerr Construction
Company, paving contractor, under their contract dated April 9, 19709
designated,as G.W.O. 2993, and find the improvements on Sub -Unit no. 22
of Unit 2208 from the South property line of the alley North of 16th Street
to the North property line of 16th Street as listed on the final estimate
and assessment sheet to have been completed in accordance with the plans
and specifications and recommend that you accept the improvements on said
streets and/or avenues, authorizing payment to the contractor the amount
shown on the attached consolidated final estimate sheet as due them by
the City of Lubbock and issue assignable certificates against property
owners for the respective amounts shown on the attached final assessment
sheets as being due against them and their respective properties.
Yours very truly,
Watson
City
CONSOLIDATED FINAL ESTIMATE
G.W.O. 2993
Accepted July 23, 1970
QUANTITIES
S.Y.
Paving
Unit &
6"
L.F.
Sub -Unit
Location
Base
C & G
2208-22
Peoria Avenue
from 30 S.
of the SPL of
the alley
N. of 16th St.
to 8' N.
of the NPL of
16th St.
523.84
294.66
TOTAL
523.84
294.66
COST ESTIMATE
523.84 S.Y. Paving 6" Base @2.69 $1,409.13
294.66 L.F. Curb & Gutter @2.45 721.92
CONTRACT COST $2,131.05
COST DISTRIBUTION
Property City -
Unit & Contractor Owner to
Sub -Unit Cost Cost Contractor
2208-22 $2131.05 $2079.30 $51.75
Plan No.
30.1653
Acceptance Date 7-23-70
G.W.O. 2993
ENGINEER'S ROLL
,
FINAL PAVING ASSESSMENT
PEORIA AVENUE
Sheet No. 33 of 45
CITY OF LUBBOCK
Sub -Unit No. 22 of
Width 36 Feet
From 3 Feet S. of the SPL of the alley North of 16th St. to 8 Feet N.
of the Unit No. 2208
NPL of 16th St.
Paving Curb & Gutter
Blk.
$3.9938539 Rate/L.F. $2.5725 Rate/L.F. Total
Owner
Lots
No. Addition
No, Ft, Cost Cost
Cost
WEST SIDE
Juanita Jones Brock
5
1 Cowan
158.33 632.35 407.30
1,039.65
EAST SIDE
Henry Holmes
1
2 Cowan
158.33 632.35 407.30
1,039.65
TOTAL PROPERTY OWNER COST $2079.30
CITY'S SHARE '.158.30
TOTAL FINAL SUB -UNIT COST $2237.60