HomeMy WebLinkAboutMinutes - City Council - Regular - 9/26/1955RECESSED REGULAR MEETING Lubbock., Texas
September 26, 1955
The City Commission of the City of Lubbock, Texas, met at 2 o'clock P.M. in recessed regular
meeting at 2 P.M. in recessed regular session, recessed from Regular Meeting of September 22, 1955,
at the regular meeting place in the City Hall, the following members thereof being present to -wit:
Mayor Murrell R. Tripp, Commissioners Hurley Carpenter and Lucian Thomas, City Ranager H. P. Clifton,.
City Secretary -Treasurer Lavenia Lowe.
Absent: CommissionersLennis Baker and S. S. Forrestp City Attorney, Vaughn E. Wilson
;5-14-285-609 This b�•ing the date set to receive bids for purchase of one or more 22,000 K. W. H. steam turbo -
generating units, including steam genc-rator, turbo generator and ccndenser, with auxiliaries and
supervision of erection as listed in specifications, notice to bidders being of record in Minute
Book 14, Page 265 . Motion was made by Commissioner Carpenter, seconded by Commissioner Thomas,
motion carried, Mayor Tripp and Commissioners Carpenter and Thomas voting Yea, none voting Nay,
that the bids be opened and read, whereupon the following bids were opened and read.
PART 11 - BASE
ONE -TURBO -
GENERATOR UNIT
MAKE
Price for one
Delivery -Calendar
CITY OF LUBBOCK, LUBBOCK, TEXAS
BID TABULATION
22,000 KW TURBO - GENERATOR UNIT
BIDDERS
General Electric Company
GE
34,108.
Days 13 mo.
Escalation or firm Yes, if within time
stated.
Cancellation charges None if before 12/15/55
Remarks
PART 11 - ALTERNATE
2-1
TWO-TURBO-
GENERAT OR UN IT S
Price for two
Delivery of second
Calendar Days
Escalation or firm
Cancellation charges
PART 111 - BASE
General Plectric Company
$1,668,216.
Allis Chalmers Uo,
A.C.
$792,000
432 Cal. days
September 26, 1955
2e00 P.M.
Westinghouse Elec.
Mfg. Company
WESTINGHOUSE
$708,691 L
Firm
None if within 90 days
after date of this proposal
Allis Chalmers Co.
$1,584.000
436 Cal* days
Firm
No remarks
Westinghouse
124172382.00
From date - 14 months 2nd in 850 cal. days 2nd in 526 cal. days.
Yes Firm - no escalation Firm
Ditto as befae --
CITY OF LUBBOCK, LUBBOCK, TEXAS
BID TABULATION September 26, 1955
2:00 P.M.
ONE 19,000 A.M. Locket
SQUARE FT.
CONDENSER
MAKE Worthington
Price for one $137,300.00
Delivery -Cal
days 240 Cal. days
Escalation or
firm ---
Cancellation charges --
PART 111, ALTERNATE 3-1
TWO 19,000 SQUARE FT.
CONDENSERS
19,000 SQUARE FEET SUE FACE CONDENSER
BIDDERS
Westinghouse Alliger & Sears
Price for two $274,600.00
Delivery of
second -Cal. days 254 cal days
Escalation or firm ---
Cancellation charges ---
Westinghouse
$135,425.00
330 cal days
No remarks
270,850.00
360 cal days
Firm
C.H. Wheeler
135,855.00
180 cal. days
271.710.00
240 cal days
10% up to 24 mo
20% over 24 mo
None prior to
Jan. 2, 1956
Remarks --- Except tubes price ---
factory � 10% handling
Allis Chalmers
Allis Chalmers
135,930.00
300 cal. days
271,860.00
360 cal days
Firm
No remarks
Not over 10% for
tubes. Tubes Q time
of invoice 4. 10%.
Westinghouse Elec. Corp. Bid: On Part 111 is firm with the exception of condenser tubes. Condenser
Part 111 and tubes have been included at $31,380.00 for each condenser. The
Part 111 Alternate condenser tubes will be billed at the price in effect at the time of
shipment from the tube mill plus a ten percent handling charge. This
is subject to ten percent maximum escalation with no limit for price
decreases. Because of the present abnormally high copper prices we
feel that prices on condenser tubes will be lower at the time of
shipment.
Oneral Electric Company The prices are firm if shipment is completed in the normal time quoted
Part 11. above, and the terms are Progressive, as listed on Page 13 of the
specifications.
Allis Chalmers Condenser and Auxiliaries - - - - - - - - - - - - $104,580.00
Part 111. Condenser Tubes - - - - - - - - - - - - - - - - - - 31050.00
n The above prices are firm with the exception of condenser tubes.
Condenser tubes will be invoiced at the price charged by the tube
supplier at the time of shipment plus a 10% handling charge. In no
event will the condenser tube price increase exceed 10%
A.M. Lockett & Company,
Limited by W.D. Gregory,
Dallas Dist. Mgr.
Prices for Part 111 and Part
111 Altemate 3-1 shall be subject to escalation as follows: Shipments up to 12 months
inclusive:
Price Firm except for tubes, which are included in price at 131,355.00
per unit, and will be adjusted to Vendor's price at time of shipment,
with any increase not to exceed 10%.
Shipments from 12 to 24 months from date of quotation:
The prices named herein will be adjusted to the prices in effect at
the time of shipment, such adjustment, if any, not to exceed 10% of
the contract price except for the following purchased equipment, the
prices for which will be adjusted to the Vendor's prices in effect at
the time of shipment but in no case shall any price exceed the maximum
price permitted by Federal laws, orders or regulations: (9)
1. Condenser Tubes.
In the event of cancellation, the following, formula is proposed as
the basis of cancellation oharges:
1. If cancelled not later than thirty (30) days after award and
providing no major engineering has been effected - No charge.
2. If cancelled after completion of engineering but prior to release
for manufacture - 15% of price for one unit.
3. If cancelled after start of manufacture -
The price provided in this agreement for all equipment which has
been completed prior to termination, actual expenditures made
by the vendor in connection with the uncompleted portion of this
agreement including reasonable cancellation charges paid by the
vendor on account of commitments made under this agreement , and
reasonable extimated profits on the uncompleted portion of this
agreement multiplied by the percentage of completion of the
uncompleted portion of this agreement.
It was brought to the attention of the City Commission that Allis Chalmers Co. had not filed with
the City, five days prior for bids to be received, a statement of their qualifications as bidders as
required by paragraph 11 - (3) of Instructions to Bidders, and motion was made by Commissioner
Thomas, seconded by Commissioner Carpenter, motion carried, Mayor Tripp and Commissioners Carpenter
and Thomas voting Yea, none voting Nay, that this requirement be waived as it is a well known fact
that Allis Chalmers is an old established and reliable Company. The following letter was received
from Ingersoll Rand Co. wherein it is stated they are unable to bid on this project.
INGERSOLL-RAND COMPANY
DALLAS, TEXAS
September 23, 1955
City of Lubbock
% Honorable Murrell R. Tripp, Mayor
City Hall
Lubbock, Texas
7C-7 SUBJ: Power Plant Improvements
Part 111 - Condenser
Our: Dal-3750
2 z c-T- ' Gentlemen:
We have your subject specifications of September, 1955 covering power plant improvements for the
City of Lubbock. We regret to advise that we will not be able to submit a bid on this project.
However, we appreciate our request, and trust we m be of service on future � Pp Y q , may jobs.
Yours very truly,
INGERSOLL-RAND CO.
/s/ Stanton Ehrlich
The following letter was received from Elliott Co. stating they were unable to bid on this equipment.
EIMTT COMPANY
DALLAS,TEXAS
A�4
/g/r,
Municipal Power Plant
City of Lubbock, Texas
September 23, 1955
Attention: Mr. F. G. Posey
New Turbine -Generator Unit
Gentlemen:
We wish to acknowledge and thank you for sending us the specifications on the turbine -generator
and condenser.
We sincerely regret that we are not able to bid on either unit since on the turbine -generators,
the experience clause rules us out.
On the condenser, we are at a disadvantage because of the specifications requiring a cast iron
water box. However, if you do issue a tabulation to the manufacturers, we would certainly
appreciate receiving a tabulation of both the turbine -generators and condensers since one of
these days we will be able to meet experience clauses, etc.
Thank you.
Yours very truly,
ELLIOTT COMPANY
/s/ W. K. Bernhard
DISTRICT MANAGER
After considering all bids submitted it was unanimously agreed by the City Commission that the bids
be r :ferred to the City of Lubbock Electrical Dept. for tabulation4 The Mayor stated to the bidders
present that the award would probably be made by the City Commission on October 12, 1955.
NO FURTHER BUSINESS COMING UP FOR CONSIDERATION. THE CITY COMMISSION RECESSED TO MEET
OCTOBER 3, 1955 AT 2:00 O'CLOCK P.M.
READ AND APPROVED THIS THE 6th DAY OF October
ll!
Lav is Lowe, City( Secretar -Treasurer
, 1955.